Home » The Green Hydrogen Investment Landscape in Southeast Asia: Where the Money Actually Is
The Green Hydrogen Investment Landscape in Southeast Asia:
Where the Money Actually Is
7 min read · Nov 17, 2025 · By Alex
Every investor I talk to about green hydrogen in this region asks some version of the same question: is the capital actually flowing, or is this still a slide-deck story? The honest answer, based on what’s actually being tracked and announced, is that the capital intentions are large and the capital deployed is still small. That gap is itself the opportunity, and understanding where it sits is more useful than any single project announcement.
In short: Industrial Info Resources tracks roughly USD 19 billion in green hydrogen projects across Southeast Asia, with Thailand and Indonesia together accounting for more than half that value. But the IEA reports that only about 6% of announced low-emissions hydrogen capacity regionally has actually reached final investment decision (FID). The money being discussed and the money being committed are two very different numbers.
In this article
The scale of what's being discussed
Indonesia’s government has estimated that up to USD 25.2 billion in investment will be needed to develop green hydrogen domestically between 2031 and 2060, with mass adoption targeted by 2050. Separately, state energy company Pertamina has committed to roughly USD 11 billion in clean energy transition investment over five years, part of a broader plan to add 10 GW of clean energy generation, of which hydrogen is one component alongside gas-to-power and renewables.
In Thailand, PTT, the Electricity Generating Authority of Thailand (EGAT), and Saudi Arabia’s ACWA Power signed an MoU to develop a green hydrogen/ammonia value chain targeting about 225,000 tonnes per year of green hydrogen, convertible to roughly 1.2 million tonnes per year of green ammonia, at an estimated investment of USD 7 billion. As of the MoU, the partners had only started a feasibility study, no construction or financing timeline had been set.
| Figure | What it represents |
| USD 19 billion | Total green hydrogen project value tracked across Southeast Asia (Industrial Info Resources) |
| Thailand + Indonesia | More than half of that USD 19 billion total |
| USD 25.2 billion | Indonesia’s own government estimate of hydrogen investment needed, 2031-2060 |
| USD 11 billion | Pertamina’s five-year clean energy transition commitment (hydrogen is one component) |
| USD 7 billion | Thailand’s PTT/EGAT/ACWA Power green hydrogen-ammonia MoU, feasibility stage only |
| 6% | Share of announced regional low-emissions hydrogen capacity that has reached FID (IEA) |
Why the FID gap exists
The IEA’s own framing of this is blunt: Southeast Asia risks remaining a green hydrogen consumer rather than a producer. Southeast Asian hydrogen demand reached about 4 million tonnes in 2024, which is real and growing, but demand existing is not the same as supply-side projects clearing investment committees. The IEA points to three structural issues behind the gap: industrial demand is concentrated rather than broad-based, project pipelines are moving slowly from announcement to execution, and policy action is still needed to actually unlock private investment rather than just government intention.
For a developer or investor, that 6% FID rate is the single most important number in this list. It tells you that the binding constraint on this market isn’t resource potential or demand, it’s the pipeline of bankable projects making it through to a financial close.
Where this breaks in practice
- Treating a headline investment figure as committed capital. The USD 25 billion Indonesia estimate and the USD 7 billion Thailand MoU are both government or consortium intentions, not financed projects. An investor reading the headline number without checking the FID status is working from the wrong baseline.
- Assuming regional demand automatically translates to regional production investment. The IEA’s own warning is specifically that demand and domestic production investment are decoupling, a project aimed at serving regional demand doesn’t automatically clear the barriers that are holding back FID elsewhere.
- Underestimating how much of the committed capital is government or state-energy-company led. Pertamina and PTT/EGAT are both state-linked entities. A private developer entering this market is often competing with, or needing to partner alongside, state capital rather than operating in a purely private market.
A practical method for reading hydrogen investment announcements
- Check FID status before valuing a headline investment figure. A feasibility study, an MoU, and a committed financial close are three very different stages, and most regional announcements stop at the first two.
- Identify whether the capital is state-linked, private, or blended. This changes what kind of co-investment or partnership structure makes sense.
- Weigh the project against the country’s structural demand profile, not just its announced capacity, since the IEA’s core warning is about a demand-supply mismatch at the regional level.
- Track the project pipeline over time, not a single announcement, since the gap between announced and FID-stage capacity is itself the leading indicator of how fast this market is actually maturing.
Common mistakes I see investors make
- Citing a government investment estimate as if it represents committed, deployable capital.
- Not distinguishing between an MoU-stage project and one that has reached financial close.
- Assuming the region’s hydrogen demand growth automatically de-risks a new production project’s offtake.
- Overlooking that much of the largest committed capital in the region is state-linked rather than purely private.
A quick checklist before you take this to lenders
- Confirmation of your project’s actual stage: feasibility, MoU, or financial close
- A clear view of whether comparable regional capital is state-linked or private
- An offtake structure that doesn’t simply assume regional demand growth will absorb your output
- A realistic read of how your project’s timeline compares to the region’s 6% FID conversion rate
Sources
- Biofuels Digest, IEA warns Southeast Asia may remain green hydrogen consumer as only 6% of capacity advances
- Energy Voice, Indonesia needs $25bn for green hydrogen
- Industrial Info Resources, Thailand Pursues $7 Billion Green Hydrogen/Ammonia Value Chain
FAQ
Is Southeast Asia actually a good place to invest in green hydrogen production right now?
The resource and demand fundamentals are real, regional hydrogen demand reached about 4 million tonnes in 2024, but the IEA’s own data shows only about 6% of announced capacity has reached FID. That gap means the opportunity exists for projects that can actually clear the bankability bar, not for capital simply following the headline announcements.
Why is so much of the largest hydrogen capital in the region state-linked?
Pertamina in Indonesia and PTT/EGAT in Thailand are both state or state-linked entities, and they’re behind two of the largest committed figures in the region. This reflects both the scale of capital needed and the strategic, national-energy-security framing governments are putting on hydrogen, which private developers often need to navigate as partners rather than pure competitors.
What does it mean that a project has only reached an MoU or feasibility stage?
It means the headline investment figure attached to the project is an estimate or intention, not committed capital. Thailand’s USD 7 billion PTT/EGAT/ACWA Power green hydrogen-ammonia project, for example, had only started a feasibility study as of its MoU, with no construction or financing timeline disclosed.
If you’re trying to size up a green hydrogen investment opportunity in this region, or figure out where a specific project actually sits between announcement and bankability, that’s exactly the kind of question I help investors and developers work through. Get in touch and we can look at the specifics together.
I’m part of the WeConnect Asia team, working with developers and investors on low-carbon infrastructure projects across Southeast Asia.
This article is for general informational purposes and does not constitute financial, legal, or engineering advice. Figures cited are drawn from publicly reported data and should be independently verified before use in any financial model.
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands against what a lender or an equity investor will ask for. Tell me where your project is today, and I will tell you what the next conversation needs to look like.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

Southeast Asia SAF: Policies, Demand and Project Status
Southeast Asia SAF policy is moving country by country. Here is where demand is forming, who the buyers are and what a developer can rely on today.

e-SAF Project Finance: Why the Sub-Mandate Is Not Enough
The synthetic fuel sub-mandate creates demand for e-SAF, but not a bankable project. Here is what e-SAF project finance still needs in Southeast Asia.

SAF Mandates by Country: A Developer’s Comparison
SAF mandates differ by country in scope, target and penalty. Here is a side-by-side comparison and what each one means for project revenue.

Sustainable Aviation Fuel: Pathways, Mandates and What Gets Financed
Sustainable aviation fuel has several pathways and sells into mandates. I explain the routes, the demand and what gets financed in Asia.

ReFuelEU Offtake: Who Actually Buys Your SAF?
The ReFuelEU mandate sits on fuel suppliers, not airlines. Here is what that means for ReFuelEU offtake contracts and what lenders expect to see.