Green Methanol in Southeast Asia:
From MOU to FID

10 min read  ·  Feb 25, 2026  ·  By Alex

Port with cargo ships, containers and storage tanks

Sarawak Petchem broke ground on a green methanol facility in Bintulu in January 2025. A six-party consortium in Singapore announced a feasibility study for a green e-methanol plant years earlier. For instance, the group includes Maersk, PTT Exploration and Production, Air Liquide and YTL PowerSeraya. Neither has reached final investment decision. I track both because they show more than any market report. In Southeast Asia, the gap between announcing a green methanol project and financing one is still wide. That means it is not a technology gap.

In short: Southeast Asia has real green methanol activity. Meanwhile, hydro and renewable power sit in Sarawak, with captured CO2 ambitions in Singapore and shipping demand from Maersk’s methanol-ready fleet. However, no green methanol plant in the region has reached FID on a committed offtake and a bankable feedstock structure. The projects elsewhere that did reach FID share a pattern. This article sets it out, and what it means for a developer building a mandate in this region.

Facebook
Twitter
LinkedIn

In this article

What is actually happening with green methanol in Southeast Asia

Sarawak Petchem operates an existing methanol complex at Tanjung Kidurong in Bintulu. It has 1.75 million tonnes per year of capacity. Samsung Engineering built the plant for roughly RM7 billion. That plant runs on natural gas. The green methanol ambition sits alongside it. Instead, the design uses water electrolysis powered by renewable energy, with captured carbon dioxide as feedstock. For instance, Sarawak’s premier has cited solar and hydro as the power sources. A Japanese consortium is working on a parallel clean hydrogen project in Sarawak. For instance, members include Japan Petroleum Exploration, GC Holdings and Kawasaki Kisen, with Sarawak Economic Development Corp and Petroleum Sarawak Bhd. In February 2024 the parties signed a storage site agreement for the M3 oilfield ([Biofuels Digest](https://biofuelsdigest.com/sarawaks-methanol-sets-sail-for-china/), [MIDA](https://www.mida.gov.my/mida-news/sarawak-sets-sights-on-green-methanol/)). As a result, the green methanol portion has no published capacity figure, financing structure or offtake agreement.

In Singapore, six companies formed the Green Methanol Value Chain Collaboration. The group includes Maersk, PTT Exploration and Production, Air Liquide, YTL PowerSeraya, Oiltanking Asia Pacific and Kenoil Marine Services. It will study a plant targeting at least 50,000 tonnes per year, using green hydrogen and captured biogenic CO2. The feasibility study was due to conclude by the end of 2022. Then a pilot plant was the next step, pending results ([Maritime Executive](https://maritime-executive.com/article/southeast-asia-s-first-green-e-methanol-plant-planned-for-singapore), [offshore-energy.biz](https://offshore-energy.biz/?p=549399)). No FID, construction timeline or offtake contract has followed that announcement, at least none that is public.

Both projects have real sponsors, real feedstock logic and a real buyer in the room. In addition, Maersk alone has more than 19 methanol-powered vessels on order globally. Neither has closed. That is the pattern worth understanding before a developer writes a financing plan around “the market is moving.”

What reached FID elsewhere for green methanol, and why

European Energy’s plant at Kassø in Denmark started operating in March 2025. Meanwhile, Maersk is the primary offtaker, and the site is now one of the largest e-methanol facilities in the world. Proman secured roughly USD 2 billion in financing in 2026 for a world-scale methanol plant in the UAE. ACME Group’s project in Odisha, India, has a committed offtake from Mitsubishi Gas Chemical. Then the contract covers 100,000 tonnes per annum once the plant is running ([enkiai.com](https://enkiai.com/maritime/green-methanol-marine-fuel-projects/)). Sun Gas Renewables in Louisiana had a long-term Maersk offtake agreement in place. Even so, the project fell through in mid-2026. That is a reminder: an offtake alone does not guarantee FID. As a result, every project that did close had locked one before the money moved.

What separates Kassø and ACME-Mitsubishi from the Sarawak and Singapore announcements is not the power source. It is sequencing. The projects that reached FID had a named buyer committed to a volume and a price mechanism. Only then did lenders underwrite construction risk. The projects still at MOU or feasibility stage have sponsors, technology partners and sometimes a shipping company in the consortium. However, the buyer has not signed a binding volume commitment. That means the price has to survive a 2 to 3 times premium over conventional fuel.

What a lender checks before financing green methanol

They want to see What that means in practice
A binding offtake, not a partnership announcement A volume, a tenor and a price mechanism that survives the green premium, signed, not “in discussion”
A feedstock structure you contract, not aspire to Renewable power and CO2 supply secured on terms that match the plant’s operating life, not a generic reference to “solar and hydro potential”
A capex figure with a source Published or at minimum disclosed to lenders, benchmarked against comparable plants (Kassø, Proman, ACME)
A sponsor with construction and operating experience in methanol, not just in shipping or power Sarawak Petchem’s existing 1.75Mtpa complex is an asset here; a shipping line alone is not an operator
A path through the cost premium Who absorbs the 2 to 3x cost gap versus grey methanol, and for how long, stated in the offtake pricing

Where green methanol projects break in practice

The most common failure point I see in this region is a consortium with complementary interests. For instance, it brings a shipping line that needs the fuel, plus a power or gas company that can supply feedstock. Because a government agency also wants the investment, nobody owns the commercial close. Everyone agrees the project is a good idea. No one is driving the offtake negotiation to a signature. That is how a feasibility study from 2022 is still a feasibility study years later.

The second failure point is treating government support as a substitute for a financing structure. Sarawak’s state backing, the existing petrochemical hub and the CCS storage agreement all lower execution risk. However, they do not replace a lender’s need for a contracted buyer and a contracted feedstock price. A groundbreaking ceremony is not a financial close.

A four-step method to move green methanol from MOU to FID

  1. Name the buyer and the volume first. Before modelling capex or shopping for lenders, get one offtaker to commit to a tonnage and a tenor. Even a smaller volume works, as long as the green premium pricing is clear.
  2. Contract the feedstock on the same timeline as the offtake. Renewable power purchase agreements and CO2 supply terms need to match the offtake’s tenor, not lag behind it. A plant with a signed buyer and an unsecured power contract is still unbankable.
  3. Bring in an operator with methanol experience, not just capital. A shipping company or a power utility in the consortium adds credibility on demand or supply. Instead, it does not add credibility on running a chemical plant. Lenders look for whoever will actually operate the facility.
  4. Take the capex and the premium-sharing structure to lenders early, before signing the offtake. Running project finance conversations in parallel with offtake negotiation shortens the path to FID. It also surfaces financing conditions that should shape the offtake terms.

Common mistakes

  • Announcing a consortium before any party has committed to a volume, then treating the announcement itself as momentum.
  • Assuming shipping demand (19-plus Maersk vessels on order globally) automatically becomes a Southeast Asian offtake. As a result, there is no named counterparty and no signed contract.
  • Under-pricing the green premium in early investor conversations, then losing credibility when the real feedstock and carbon capture costs land.
  • Leaning on state or government backing as if it substitutes for a contracted feedstock and offtake structure.

Checklist before you take this to investors or lenders

  • Is there a named offtaker with a signed, or at least termsheet-stage, volume and price commitment?
  • Is the renewable power and CO2 feedstock contracted, or still “available in the region”?
  • Does the consortium include an operator with methanol or comparable chemical plant experience?
  • Did you benchmark the capex against Kassø, Proman or comparable plants and share it with prospective lenders?
  • Is there a clear answer to who absorbs the cost premium over conventional methanol, and for how long?
  • Is one party clearly accountable for driving the commercial close, rather than the consortium managing it by committee?

Sources

FAQ

if you are developing a green methanol project in Southeast Asia, this is the conversation I have. The gaps I close are a committed offtaker, a contracted feedstock structure, or lenders who understand the region. Book a 30-minute call or see how I work on offtake agreements, feedstock supply and project finance.

Not sure your project would survive a credit conversation?

A short call is usually enough to see where your project stands against what a lender or an equity investor will ask for. Tell me where your project is today, and I will tell you what the next conversation needs to look like.

Alex, Founder of WeConnect Asia

I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.