Home » Why SAF Projects Stall Before FID: The Pieces That Are Missing
Why SAF Projects Stall Before FID: The Pieces That Are Missing
10 min read · Nov 2, 2026 · By Alex
Fewer than 30 percent of sustainable aviation fuel initiatives reach a final investment decision (FID). In addition, the binding constraint is contractual rather than technical (BCG). The chemistry works and developers announce the plants, yet nobody signs the agreement that would carry the debt. If you are a developer in Southeast Asia asking why your project sits pre-FID. The answer usually sits in a file you have not closed. This piece follows the chain upward from the project through the sustainable aviation fuel market it depends on. It then sets out which pieces are typically missing.
I have set this out as a checklist rather than a survey, because the gap is rarely one document. It is a sequence, and a lender reads it in order.
In short
- The verdict: fewer than 30 percent of SAF initiatives reach FID. Facilities typically take three to five years after funding to produce at scale.
- The gate: a binding take-or-pay offtake agreement, binding feedstock supply, completed permits, binding debt and equity, and a technology agreement.
- The stall: offtake contracts are often non-binding memoranda of understanding, and only binding agreements carry a project to decision.
- The horizon: developers need predictable incentives and mandates for at least a decade beyond commissioning.
- The number: pre-FID costs run from 40 to 70 million US dollars before the decision itself.
In this article
The short answer: the contract, not the chemistry
Fewer than 30 percent of SAF initiatives reach a final investment decision. Facilities typically take three to five years after funding before they start producing at scale. Progress has slowed for three reasons. Economic and regulatory uncertainty comes first, then high production costs, then weak demand signals. The missing long-term off-take agreements sit behind all three. The interview evidence points the same way. Respondents name the lack of a clear business case as the biggest barrier to investment.
I find this reassuring rather than discouraging, because it relocates the problem. Also, nobody asks me to prove a conversion pathway. Each ASTM D7566 annex already specifies the feedstock and the conversion process. In addition, the blending limits for an approved pathway. What I must prove is that someone will buy the output at a price that services debt. That buyer must stay for longer than the debt runs.
What this means for you: stop treating a technology problem as the constraint. Start treating your contract file as the project.
What a decision actually requires
For a positive FID I need five things in place, all of them resting on the FEED study. That is the front-end engineering design package, which confirms economic viability. The first is a binding take-or-pay offtake agreement for the fuel produced at the facility. Then binding long-term supply agreements for the relevant feedstocks. After that, completed construction permits. Fourth, binding debt and equity commitments. Finally, an agreement with the technology provider plus the necessary permits.
The lifecycle runs through five critical phases: conceptualization, pre-feasibility, FID, construction and commissioning. Each phase can only start when the prior phase has delivered a document the next party accepts. Missing any one piece moves the decision date, and the sequence is exactly what a lender checks. I map my file against how to reach FID in a SAF project before I brief anyone.
What this means for you: write the five requirements down and mark each one signed or unsigned. Then date the gap rather than the announcement.
The offtake that will not sign
Investors often want offtake agreements covering at least 70 to 80 percent of annual capacity. Some lenders want reliable offtake on 100 percent of the SAF produced for the full loan tenor. That tenor runs 8 to 14 years (World Economic Forum with Kearney). An offtake agreement is the contract under which a buyer takes the output. Take-or-pay means the buyer pays whether or not it lifts the volume.
The problem is that these contracts are often non-binding memoranda of understanding. A project needs contractually binding agreements to reach FID. The widespread use of non-binding memoranda of understanding, rather than firm long-term off-take agreements, makes financing harder. Only three airlines consumed over 1 percent of SAF in their fuel mix as of 2023. Therefore, the credible buyer pool is small. I work through how to secure SAF offtake agreements when the memorandum is the only paper I hold.
What this means for you: if your offtake is a memorandum, you do not have an offtake. In addition, no lender will price it as one.
The policy horizon that will not hold
New offtake volumes fell significantly in 2023 to 2024, after the surge of activity in 2021 to 2022. Developers struggled to secure the long-term purchase agreements that unlock project finance. Many projects remain technically and environmentally ready. However, few reach final investment decision without creditworthy offtakers or predictable price support (Global Biofuels Alliance).
The cause sits above the developer. Also, the lack of durable and clearly defined policy horizons makes it difficult for offtakers to make long-term binding agreements. In addition, developers need predictable incentives and mandates for at least a decade beyond commissioning. In addition, the European Union delayed its final SAF eligibility criteria under ReFuelEU Aviation. It also delayed the timelines that clarify implementation, which slowed new project announcements. Moreover, airlines in Europe pay up to five times the price of conventional jet fuel. That premium, double the market price of SAF, weakens the offtaker’s own appetite to sign.
What this means for you: check whether the mandate behind your margin lasts longer than your debt. A short horizon cannot carry an 8 to 14 year loan.
The feedstock and the capital gap
Establishing advanced SAF facilities at commercial scale is extremely capital intensive. In addition, a single facility may represent a multi-billion-dollar investment. Debt providers stay risk-averse and often refuse to back pioneering facilities that supply an immature market (ICCT). Pre-FID costs run at between 40 and 70 million US dollars. One project cites expenditures above 30 million US dollars for the FEED study and other planning work. Project announcements for new SAF facilities declined 50 to 70 percent from 2022 to 2023.
Feedstock is a separate gate. HEFA is the most mature and cost-effective pathway, and it faces feedstock constraints. Gasification-Fischer Tropsch needs solid feedstock handling. Power-to-Liquid carries the highest capital requirements. Installed capacity reached 4.4 Mt by end 2024, with 6.9 Mt of expansion planned. In addition, an additional 5.8 Mt would need final investment decisions by 2026 to meet 2030 demand. My regional gate sits in SAF feedstock availability in Southeast Asia.
What this means for you: confirm your feedstock pool can promise volume on the same tenor as your debt. Then price the pre-FID spend against the equity you can actually raise.
The projects that took the decision and still died
FlagshipONE cancelled its e-fuels project after a positive final investment decision, for lack of offtake demand. Shell withdrew from the HySkies e-SAF facility despite an award from the EU Innovation Fund. Both show that a signed decision without demand does not hold. These are not scandals; they are ordinary outcomes when demand arrives after the capital.
Uncertainty about the future price of advanced fuels keeps developers from securing funding and reaching a positive final investment decision. Respondents point to a revenue certainty mechanism as the straightforward way to cut financial risk for all parties. A revenue certainty mechanism is an instrument that fixes or floors the return so the cash flow is predictable. Bankability, meaning the condition under which a lender will lend, depends on that predictability. SAF projects remain capital intensive and high risk. In addition, few blended-finance, insurance, guarantee or concessional instruments fit the sector. I read this through how to finance a SAF project.
What this means for you: treat price support as a piece of the file, not a hope. A decision taken without demand has already reversed.
The order I would run the work in
I would build the offtake file first, because it is the piece every other party waits for. Next I would lock the feedstock supply on the same tenor as the debt. After that I would confirm which policy instrument funds my margin, and for how long it runs. Fourth, I would price the pre-FID spend against the equity I can raise. The development bill runs into tens of millions of US dollars before a decision.
Fifth, I would prepare the lender package with the security, direct agreements and insurance that a first-of-a-kind facility attracts. A first-of-a-kind facility has no directly comparable operating reference. That is why lenders ask for more cover rather than less. Each step produces the document the next step needs. Running them in parallel therefore leaves a gap exactly where the lender looks hardest. My sequencing sits alongside project finance services.
What this means for you: order the work so each deliverable feeds the next. Do not brief a lender before the first three files carry signatures.
How I would run this if it were my file
I would measure my project against the published conversion rate rather than my own optimism. Fewer than 30 percent of SAF initiatives reach FID. Only 14 percent of the executives BCG surveyed feel well prepared for the challenges along the way. Also, I would test the volume against the market. SAF production in 2025 was 1.9 Mt, 0.6 percent of total jet fuel consumption. For 2026 IATA projects 2.4 Mt and 0.8 percent.
I would test the price. SAF costs twice as much as fossil-based jet fuel, and up to five times as much in mandated markets. In addition, I would test capacity cover. Meeting 2030 demand required final investment decisions on an extra 5.8 million tonnes of SAF by 2026. Four tests, four numbers, and my file either survives them or tells me where to work next.
What this means for you: run the four tests before you announce another date. Let the result set the milestone, not the ambition.
Sources
- BCG, consulted 15 November 2026.
- ICCT, July 2025.
- Global Biofuels Alliance, consulted 15 November 2026.
- World Economic Forum with Kearney, February 2025.
- IATA, 9 December 2025.
Frequently asked questions
What is the most common reason a SAF project misses FID?
The published evidence points to demand rather than technology: the lack of firm long-term off-take agreements and the absence of a clear business case are named as leading barriers, and off-take volumes fell in 2023 to 2024 as developers struggled to secure the long-term purchase agreements needed to unlock project finance (BCG, Global Biofuels Alliance).
How long does it take to build a SAF plant after the decision?
Facilities typically take three to five years after being funded to start producing at scale, on top of the five phases of the lifecycle from conceptualization through pre-feasibility to FID, construction and commissioning (BCG, World Economic Forum with Kearney).
Does a signed offtake memorandum satisfy lenders?
No: offtake contracts are often non-binding memoranda of understanding, and contractually binding agreements are what a project needs to reach FID, with investors commonly asking for 70 to 80 percent of annual capacity covered and some lenders asking for 100 percent of production covered for the full loan tenor (World Economic Forum with Kearney).
How much does it cost to get a SAF project to the decision point?
Developers surveyed put pre-FID costs at between 40 and 70 million US dollars, with one project citing more than 30 million US dollars spent on the FEED study and other planning efforts, before the decision itself (ICCT).
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If you want me to read your own file against these eight sections and tell you which piece is missing, I offer investor introductions for developers who have reached the point where a credible counterpart is the binding constraint.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia find the commercial and financial partners they need to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.