Home » SAF Fuel Suppliers and Traders: Selling Through an Intermediary or Direct
SAF Fuel Suppliers and Traders: Selling Through an Intermediary or Direct
10 min read · Nov 2, 2026 · By Alex
At pre-FID stage, choosing how to sell your sustainable aviation fuel (SAF) looks like a distribution decision. It is not. The published answer is a question of obligor (who owes the payment). Also, the bridge is an aggregator of sufficient creditworthiness. That middleman places its own balance sheet behind the payment obligation. It sits between the SAF producer selling long term and the end-customer buying short or mid-term. Lenders stay reluctant to take significant merchant exposure, which means selling into the market without a locked-up contract. They prefer a locked-up offtake agreement with a creditworthy counterparty. The wider structure sits in how to secure SAF offtake agreements.
I am working from published material on project finance offtake structures, SAF pricing options. In addition, the credit tests lenders apply to a young sector. Every point traces to a named source. In addition, the comparison runs between selling direct to the buyer and selling through an intermediary.
In short
- Obligor: the bridge is an intermediary of sufficient creditworthiness between a long seller and a short buyer (Dentons).
- Contract: take-or-pay means the buyer pays whether or not it takes delivery, which covers fixed costs (Global Trade Funding).
- Price: the 2024 market premium in Europe reached as high as around 1000 USD/tonne of HEFA SAF (IATA).
- Coverage: offtake agreements must cover at least 70 to 80 percent of annual capacity (World Economic Forum).
- Choice: direct selling keeps the margin and hands me merchant exposure (Bracewell).
In this article
The question is the obligor, not the channel
Dentons states the mismatch plainly. Airlines do not typically forward-hedge their fuel requirements beyond two to three years. Project finance lenders, by contrast, require a long-term, fixed-price offtake agreement. Even a 10 year airline purchase commitment would leave a large, uncontracted tail. A long-term debt tenor can run 20 to 25 years (Dentons, 15 April 2025).
A potential solution to bridge the gap is an intermediary, an aggregator of sufficient creditworthiness. It sits between the SAF producer selling long term and the end-customer buying short or mid-term (Dentons). Bracewell lists the published offtaker types. They are a utility, a trader or marketer, a tolling counterparty, and a creditworthy corporate buyer. A trader or marketer buys in order to resell rather than to consume. In addition, a retailer or retail end user (Bracewell LLP, 10 September 2026).
Under such an agreement the buyer commits to purchase all or a specified portion of the output. Who signs therefore matters more than the route (Bracewell).
What this means for you. I ask which legal entity sits behind the payment obligation, and what happens to that entity if it is downgraded or distressed.
What the intermediary actually does
A take-or-pay obligation means the offtaker pays for the products on a regular basis. It pays whether or not it actually takes delivery. In addition, the published rationale is direct. It allows the supplier to cover its fixed costs and be ready to supply in the future. Producers want that protection because lenders like predictable revenue. Buyers resist it when their forecast demand is uncertain (Global Trade Funding, 13 March 2022. Mayo Law, consulted 15 November 2026).
The contract is the container for scale: offtake agreements establish the contractual framework for a long-term arrangement between the project company and an offtaker for the purchase and sale of all or substantially all of the project output, at fixed or contractually adjusted prices for as long as ten years or more (Global Trade Funding). Larger projects may struggle to secure one offtaker for the entirety of the plant’s production. They may enter several offtake arrangements with different buyers to spread the credit risk (Dentons, 15 April 2025).
That is the function I buy when I take an intermediary. A tenor the end customer will not sign, coverage of output I cannot place alone. Also, a second credit standing between the plant and the buyer.
What this means for you. I price the intermediary as a substitute for volume I could not contract directly. In addition, I compare its margin with what I would spend marketing the same tonnes myself.
What sits between plant gate and invoice
The price airlines pay for SAF incorporates add-on costs on top of production. Those add-ons are a market premium, logistics, certification, transaction-related costs, and markups throughout the supply chain (IATA, 12 May 2024). Near-term pricing mirrors conventional aviation fuel: a CAF price index with a SAF premium applied, or a SAF price index, and Argus FOB Singapore and Platts CIF ARA are examples of assessments used as the base to which logistics costs, fees. In addition, the supplier adds its margin.
Also, in 2024, the difference between production cost and market prices. In Europe the market premium reached as high as around 1000 USD/tonne of HEFA SAF. The market nevertheless lacks transparency on deals and prices paid (IATA). For scale, IATA reports that SAF prices exceed fossil-based jet fuel by a factor of two. In mandated markets the factor runs up to five (IATA, 9 December 2025).
Every intermediary margin is one of those published lines, so I negotiate the lines before I negotiate the discount. The price context sits in sustainable aviation fuel price.
What this means for you: I list each add-on separately in my own model, because one blended premium hides which part of the chain I am actually paying for.
Selling across a border
For cross-border deals fixed pricing can create currency risk and indexed pricing can create benchmark risk. In addition, a floor, a ceiling or an adjustment formula often works better than either extreme (Mayo Law, consulted 15 November 2026). Market price is not a pricing mechanism. Disputes are common because parties believe they agreed on economics when they only agreed on a concept.
A complex pricing formula needs four things in the contract: the source, the timing and the fallback mechanism. It also needs to say who calculates adjustments. The contract should already say what happens if the benchmark does not publish on a given date (Mayo Law). The indices come from a price reporting agency such as Argus Media or S&P Global Commodity Insights. They cover specific trading markets, for example Singapore (IATA, 12 May 2024).
A bare agreement to agree on price or volume is generally not enforceable. A defined formula with a named benchmark, a fallback source and a stated calculation method generally is (Mayo Law). An export route is therefore a pricing problem before it is a logistics problem. The route itself is set out in export SAF.
What this means for you. I write the benchmark, the fallback and the currency clause before I fix the shipment date. A missing assessment on pricing day is a contractual event, not an inconvenience.
Selling direct: what you take on
Most facilities use limited-recourse project financing. Therefore, a bankable offtake agreement is often the single most important document in the transaction. To be financeable it must provide stable, predictable revenue over the life of the debt and involve a creditworthy offtaker. It must also mitigate the project’s material operating and market risks, and avoid provisions that would stop lenders from exercising remedies if the project defaults (Bracewell LLP, 10 September 2026).
Lenders continue to prefer projects with a locked-up offtake agreement over merchant exposure to market prices. Merchant exposure means selling output directly into the market without a locked-up contract. In addition, some financings permit a limited merchant tail that remains the exception rather than the rule (Bracewell). Lenders will be reluctant to take significant merchant exposure for a new sector. In addition, any limited merchant offtake strategy needs detailed marketing analysis and a hard look at debt-sizing (Dentons, 15 April 2025).
Direct selling keeps the margin and hands me the marketing risk. I have to write that risk into the debt-sizing conversation. The direct route is set out in how to secure offtake agreements.
What this means for you. I take the direct route only when I can produce the marketing analysis a lender will ask for. I also have to accept that an uncontracted tail sits on my own file.
The credit test both routes must pass
The offtaker’s financial quality can matter as much as the promised volume. A practical credit review asks who the actual obligor is and what support exists, in the form of a guarantee, letter of credit, security package or reserve account. It also asks what happens on downgrade or distress, and whether revenue can be captured (Mayo Law, consulted 15 November 2026).
Investors often require offtake agreements to cover at least 70 to 80 percent of annual capacity. In addition, some lenders require 100 percent of the SAF produced to have reliable offtake covering the full loan tenor (World Economic Forum, February 2025). The offtake contract also needs to cover the tenure of debt financing, for example 8 to 14 years (World Economic Forum).
Airline credit ratings are on average lower, so spreading default risk across several parties matters (World Economic Forum). Lenders are reading the credit file behind the signature. This is the same exercise set out at bankability. A beautifully drafted contract with a weak buyer is often not bankable (Mayo Law).
What this means for you. I run one credit test and apply it to both routes, because the same obligor question decides whether the contract supports the debt or merely describes a sale.
Where each route breaks
Published red flags for these contracts start with vague pricing language, unclear testing methods, one-sided termination rights and broad rejection rights. Force majeure clauses are the fifth: they read well but do not allocate actual operational risks (Mayo Law, consulted 15 November 2026). One-sided termination for convenience is often a financing problem because it makes projected revenue less reliable.
Most offtake agreements contain a force majeure clause. It allows either party to modify or cancel the agreement if something beyond anyone’s control puts undue hardship on either party (Global Trade Funding, 13 March 2022). On its own, that clause assigns very little.
Pricing clauses are the other break point. Clauses that allow the seller to renegotiate pricing mid-contract or even yearly can add complexity to an airline’s fuel budget. If uncapped, that scope for price adjustment adds another layer of risk to SAF supply (IATA, 12 May 2024).
What this means for you. I read termination, force majeure and price reopener clauses on both routes before I compare margins. Those are the clauses a lender reads during due diligence.
How I would run this if it were my file
I write two columns, direct and intermediary, and I fill five rows. They are the tenor the counterparty can sign, who the obligor is and what support stands behind the signature. The rest covers the benchmark and fallback behind the price, plus what a credit review asks on downgrade or distress.
I test both columns against the published coverage floor: at least 70 to 80 percent of annual capacity. Where the lender requires it, the floor rises to 100 percent of the SAF produced across the full loan tenor (World Economic Forum, February 2025).
Then I price the channel. The published add-ons of market premium, logistics, certification, transaction-related costs and markups throughout the supply chain (IATA, 12 May 2024) tell me what the intermediary margin is replacing.
What this means for you: my decision is one sentence. I sell direct only when my own credit file passes the test I would run on the intermediary. In addition, I use a trader when the tenor or the coverage I need would otherwise not exist.
Sources
- Dentons, 15 April 2025.
- Bracewell, 10 September 2026.
- IATA, 12 May 2024.
- Global Trade Funding, 13 March 2022.
- Mayo Law, consulted 15 November 2026.
- World Economic Forum, February 2025.
- IATA, 9 December 2025.
Frequently asked questions
What does a SAF trader actually add?
A trader or marketer is one of the published offtaker types, alongside a utility, a tolling counterparty, a creditworthy corporate buyer and a retailer or retail end user (Bracewell LLP, 10 September 2026). What the intermediary of sufficient creditworthiness adds is structural rather than physical: it bridges the gap between a producer selling long term and an end-customer buying short or mid-term, which brings a tenor the end customer will not sign and a second credit standing between the plant and the buyer (Dentons, 15 April 2025).
Is selling through an intermediary weaker for financing?
Not if the intermediary passes the same test a lender applies to any buyer. Lenders continue to strongly prefer projects with a locked-up offtake agreement rather than merchant exposure to market prices, and an offtake agreement must provide stable, predictable revenue over the life of the debt, involve a creditworthy offtaker, mitigate the project’s material operating and market risks, and avoid provisions that would prevent lenders from exercising remedies if the project defaults (Bracewell LLP, 10 September 2026). The route is secondary to those four conditions.
How do I check the credit of a counterparty?
What the credit review asks
A practical credit review asks who the actual obligor is, what support exists in the form of a guarantee, letter of credit, security package or reserve account, what happens on downgrade or distress, and whether revenue can be captured (Mayo Law, consulted 15 November 2026). I run that list before I compare prices, because the offtaker’s financial quality can matter as much as the promised volume.
Can I sell direct and use an intermediary at the same time?
The published pattern for larger projects is to enter several offtake arrangements with different buyers to spread the credit risk (Dentons, 15 April 2025), and investors often require at least 70 to 80 percent of annual capacity to be covered by offtake agreements, with some lenders requiring 100 percent of the SAF produced to cover the full loan tenor (World Economic Forum, February 2025). Splitting the book is therefore a normal published pattern, provided every slice passes the same credit test.
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If you are at pre-FID stage and weighing a direct contract against an intermediary, I run that comparison against your own coverage and credit position. My work on investor introductions starts from the same obligor test, because the route you choose has to survive the file a lender will build.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.