Home » SAF Co-Processing in Existing Refineries: Fast on Capital, Capped on Volume
SAF Co-Processing in Existing Refineries: Fast on Capital, Capped on Volume
10 min read · Nov 2, 2026 · By Alex
can be made inside a refinery you already have rather than in a new plant, but ASTM D1655 caps the renewable share of the incoming stream at 5 percent for the oils and fats route and for the Fischer-Tropsch route, and it caps the HEFA route at 24 percent input with 10 percent output in the finished fuel. That is the whole trade in one sentence: the capital question is answered fast. The volume question is not answered at all. I am looking at saf co processing as a pre-feasibility developer in Southeast Asia, and the only real question is what it is worth in a financing file.
The framing matters because co-processing is easy to oversell. It borrows an existing refinery, an existing pipeline and an existing airport fuelling operation, and in exchange it accepts a published ceiling on every litre it can claim.
In short
- Definition: mixing a base feedstock, typically fossil crude oil, with a biogenic feedstock inside a petroleum refinery, with no new plant and no modified facility.
- Cap: ASTM D1655 allows co-processing of biomass feedstocks in blends up to 5 percent, with 5 percent input for two routes and 24 percent input plus 10 percent output for the HEFA route.
- Feedstock: the regional picture consists of used cooking oil, animal fats, palm kernel oil, POME, non-edible oil feedstock trees and municipal solid waste.
- Price: SAF exceeded fossil jet fuel by a factor of two in 2025, and by up to a factor of five in mandated markets, against demand of 17 million tonnes per annum expected by 2030.
- Sequence: fix the feedstock contract first, then the route, then the claim, then the standard, then the offtake, then walk the five phases.
In this article
The short answer: no new plant, no big volume
Co-processing is mixing a base feedstock, typically fossil crude oil, with a biogenic feedstock such as vegetable oils, used cooking oil or pyrolysis oil, within a petroleum refinery (IATA SAF Handbook). Specifically, The benefit is the immediate replacement with renewables of a share of the fossil feedstock, up to a certain limit, without the need for building new or modifying production facilities, because the process introduces a renewable share into the product slate of the co-processing facility.
Saf co processing: what ASTM D1655 allows
ASTM D1655, the standard specification for aviation turbine fuel, allows co-processing of biomass feedstocks at a petroleum refinery in blends up to 5 percent (US Department of Energy Alternative Fuels Data Center). Moreover, The volume ceiling is the other half of the answer. Therefore, As of July 2023, eight of the eleven approved conversion processes follow ASTM D7566 and the remaining three follow ASTM D1655 because of co-processing with conventional fossil jet (IRENA).
What this means for you: you can put a co-processing case in front of a lender without a greenfield engineering study. However, you must model the tonnes as a fraction of an existing refinery’s slate rather than as a plant you own.
What goes into the refinery
The limits are published as input and output limits rather than as a single blend number. Consequently, IATA’s table, adapted from ICAO approved conversion processes, gives an input limit of 5 percent for co-hydroprocessing of esters and fatty acids in a conventional petroleum refinery, an input limit of 5 percent for co-hydroprocessing of Fischer-Tropsch hydrocarbons, and an input limit of 24 percent with an output limit of 10 percent for co-processing of HEFA (IATA SAF Handbook).
ICAO lists the same rows under ASTM D1655 Annex A1: co-hydroprocessing of esters and fatty acids 5 percent, co-hydroprocessing of Fischer-Tropsch hydrocarbons 5 percent, co-processing of HEFA 10 percent (ICAO). Meanwhile, The US list is narrower still. Specifically, The Department of Energy records that ASTM approved 5 percent fats, oils and greases coprocessing with petroleum intermediates, and, in association with the University of Dayton Research Institute, 5 percent Fischer-Tropsch syncrude coprocessing with petroleum crude oil (US Department of Energy Alternative Fuels Data Center). Meanwhile, Before you pick a route, check regional feedstock availability first.
What this means for you: the 24 percent input against 10 percent output gap on the HEFA route is the single line that will move your mass balance. Therefore, i model the input I can physically take and the output I can legally claim as two separate numbers.
Who supplies the feedstock, and what that contract costs
The biogenic side of a co-processing deal is a waste oil supply. Also, the regional picture in Southeast Asia leans on used cooking oil, animal fats, palm kernel oil, POME, non-edible oil feedstock trees and municipal solid waste across the planned and operating plants IRENA lists (IRENA). By contrast, Neste at Tuas in Singapore runs on used cooking oil and animal fats and has been operating since the third quarter of 2023 at 1,000,000 tonnes (IRENA). For example, Waste and lower carbon intensity feedstocks such as fats, oils and greases will soon limit production of renewable diesel. Also, SAF via the HEFA pathway. Meanwhile, crop-derived lipids typically come at a higher carbon intensity or have other sustainability challenges, and commercial availability of alternative oilseed crops such as carinata and camelina is currently insignificant (IEA Bioenergy Task 39).
Because increasing attention will on-site and optimised pretreatment for low-quality waste feedstocks containing numerous contaminants, I price pretreatment into the supply contract rather than into the plant (IEA Bioenergy Task 39). Instead, The commercial terms live at the feedstock supply agreement.
What this means for you: I would sign a supply contract that carries the pretreatment obligation and the contaminant specification than own equipment that degrades the moment the oil quality shifts.
What the fuel has to clear in price
SAF production in 2025 reached 1.9 million tonnes. By contrast, Only 0.6 percent of total jet fuel consumption, and 2026 should reach 2.4 million tonnes and 0.8 percent (IATA). In addition, SAF prices exceed fossil-based jet fuel by a factor of two, and by up to a factor of five in mandated markets, and at current price levels the SAF premium translates into an additional USD 3.6 billion in fuel costs for the industry in 2025 (IATA). Furthermore, Demand for global SAF should reach 17 million tonnes per annum by 2030, approximately 4 to 5 percent of total jet fuel consumption. Also, the industry may require between 19 billion and 45 billion US dollars of capital expenditure by 2030 depending on the technology mix (World Economic Forum with Kearney). Meanwhile, The mechanism behind that spread sits at the price spread explained.
What this means for you: I write the price case as a premium I must survive rather than as a premium I can rely on, because the mandated markets that pay up to a factor of five are not the markets my fuel is guaranteed to reach.
Where co-processing sits against the other approved pathways
There are currently 12 sustainable aviation fuel production pathways approved by ASTM International, and three of them are co-processing pathways (ICAO Aviation Benefits). By contrast, On blend limits, the hydroprocessed lipids co-processing route allows up to 10 percent, fats, oils and greases co-processing up to 5 percent and Fischer-Tropsch co-processing up to 5 percent (ICAO Aviation Benefits).
Work is also ongoing to increase the maximum blending for co-processing from 5 percent to 30 percent (ICAO).
What this means for you: I read the 30 percent work as a reason to keep the co-processing option alive in the file, not as a number I can put in a model today, because a pathway under evaluation is not a limit a lender will underwrite.
What co-processing solves, and what it leaves open
By contrast, What it solves is time and capital. Moreover, No new or modified production facility is needed (IATA SAF Handbook), and a fuel co-processed with conventional Jet A at an existing petroleum refinery flows through the supply chain in a business-as-usual model via pipeline to terminals and onwards by pipeline or truck to airports, with no change to fuel operations at the airport (US Department of Energy Alternative Fuels Data Center).
What it leaves open is the claim. Lower carbon aviation fuels are fossil aviation fuels whose emissions are reduced through other measures. Both SAF and LCAF are CORSIA Eligible Fuels but by definition LCAF are not the same as SAF, and to comply with CORSIA they must demonstrate a lifecycle emissions improvement of at least 10 percent relative to the average global fossil fuel carbon intensity (IATA SAF Handbook). There is also a precedent to read carefully: the first small-scale commercial facility using gasification with Fischer-Tropsch synthesis began operation in 2022 with municipal solid waste as feedstock and sent its FT liquids to a petroleum refinery for co-processing, and it is not clear whether any substantial amounts of SAF had been produced via this process (IEA Bioenergy Task 39). The mechanics of both routes are set out in how to finance a SAF project.
What this means for you: I separate the fuel I can move through the existing chain from the fuel I can certify as SAF, because a refinery that runs does not automatically produce a claim that holds.
The order I would run the co-processing file in
I would fix the feedstock contract first, because the biogenic share is what the whole claim rests on. Also, the waste oils compete with other plants in the region (IRENA). Then I would fix which of the three ASTM D1655 routes the deal uses and hold the published limits in the model, 5 percent input for two of them and 24 percent input with 10 percent output for HEFA (IATA SAF Handbook). Then I would confirm the certification and claim route, since ASTM D1655. Also, the UK Defence Standard 91-091 have nearly identical requirements. Also, the specification is applied upstream of the airport (IATA SAF Handbook, US Department of Energy Alternative Fuels Data Center).
Then I would watch the standard itself, because ASTM is working to increase the maximum blending for co-processing from 5 percent to 30 percent (ICAO). Then I would write the offtake to cover the debt tenor, since investors often require at least 70 to 80 percent of annual capacity to be covered by offtake agreements. Also, the contract needs to cover the tenure of debt financing, for example 8 to 14 years (World Economic Forum with Kearney). Then I would walk the five critical phases of the SAF refinery lifecycle, conceptualization, pre-feasibility, FID, construction and commissioning (World Economic Forum with Kearney). The financing sequence runs through how to reach FID.
What this means for you: the order is deliberate, because a feedstock contract signed after the offtake gives a buyer a volume I cannot underwrite. Also, a model that ignores the 10 percent output cap gives a lender a number I cannot deliver.
How I would run this if it were my file
I would treat co-processing as a bridge with a defined end date, because the volume I can sell is capped while the plant I ultimately need is not. The demand side is published. The Sustainable Aviation Fuel Grand Challenge aims at domestic consumption of 3 billion gallons in 2030 and 35 billion gallons in 2050 while achieving at least a 50 percent reduction in lifecycle emissions (US Department of Energy Alternative Fuels Data Center).
Actual consumption tells me how far that is. Approximately 5 million gallons of SAF were consumed in 2021, 15.84 million gallons in 2022 and 24.5 million gallons in 2023 (US Department of Energy Alternative Fuels Data Center). For plant references I keep the record straight. World Energy began SAF production in 2016 at its facility in Paramount, California, and Montana Renewables began production in 2023 in partnership with Shell at an existing petroleum production plant (US Department of Energy Alternative Fuels Data Center).
And I read the policy horizon as an investor does, because the long-term certainty of mandates should reduce risk for investors while creating a level playing field for all airlines, even though ReFuelEU Aviation did not include incentives that would bridge the price gap between conventional jet fuel and SAF (IEA Bioenergy Task 39).
What this means for you: I would sign the co-processing file with a date attached, because the ceiling is published, the demand is published, and the only variable I control is how quickly I convert a capped stream into the offtake that funds the plant behind it.
Sources
- ICAO, 16 November 2026.
- IATA SAF Handbook, May 2024.
- US DOE Alternative Fuels Data Center, 16 November 2026.
- ICAO Aviation Benefits, 16 November 2026.
- IEA Bioenergy Task 39, January 2024.
- IRENA, December 2024.
- World Economic Forum with Kearney, February 2025.
Frequently asked questions
What is SAF co-processing?
It is mixing a base feedstock, typically fossil crude oil, with a biogenic feedstock such as vegetable oils, used cooking oil or pyrolysis oil inside a petroleum refinery, which replaces a share of the fossil feedstock without building new or modifying production facilities (IATA SAF Handbook).
How much can a refinery co-process into jet fuel?
ASTM D1655 allows co-processing of biomass feedstocks in blends up to 5 percent, and the published table gives 5 percent input for co-hydroprocessing of esters and fatty acids and for Fischer-Tropsch hydrocarbons and 24 percent input with 10 percent output for co-processing of HEFA (US Department of Energy Alternative Fuels Data Center, IATA SAF Handbook).
Is co-processed fuel the same fuel as fuel from a dedicated SAF plant?
SAF has to have the same chemical qualities and characteristics as conventional jet fuel so that engines and aircraft do not have to be redesigned, while co-processing simply introduces a renewable share into the product slate of the existing refinery (ICAO Aviation Benefits, IATA SAF Handbook).
Is co-processing the cheaper route for a developer?
It removes the need to build new or modify production facilities and keeps the fuel moving through the existing supply chain, but the volume stays inside the published limits, so I judge it on the tonnes I can certify and sell rather than on the capital I did not spend (IATA SAF Handbook, US Department of Energy Alternative Fuels Data Center).
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If you want to take this file forward, the next useful step is an introduction to the right capital: my investor introductions service.
I do not provide investment advice or arrange investments. In addition, I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.