SAF Market Overview: Demand, Supply and Costs in One Place
10 min read · Nov 2, 2026 · By Alex
When I read sustainable aviation fuel as an investment question, the direct answer is that the market is still small. Regulation has written the demand: 1.9 million tonnes expected in 2025, 0.6 percent of total jet fuel consumption. In addition, installed capacity was 4.4 million tonnes at the end of 2024, meaning what built plants produce once running. A further 5.8 million tonnes need a final investment decision (FID) by 2026, the point where a board commits capital. Volume lags capacity, price lags both, and compliance lags both again. Those three gaps are the whole market. A saf market overview has to keep them apart.
I write this for an equity investor at concept stage. Specifically, I ask where the market actually stands and what a project has to show before money moves. The short version: rules write demand, capital writes supply, and feedstock writes the price.
In short
- Volumes: 1.9 million tonnes expected in 2025, 0.6 percent of jet fuel (IATA Press Release No 57).
- Capacity: 4.4 million tonnes installed by the end of 2024. In addition, 6.9 million tonnes are planned. A further 5.8 million tonnes need an FID by 2026 (World Economic Forum and Kearney).
- Price: between 2 and 5 times fossil jet fuel, up to a factor of five in mandated markets (IATA).
- Rules: Singapore at 1 percent in 2026, with Malaysia and Indonesia planning. Thailand and the Philippines are in progress, and the rest of the region has no policy (IRENA).
- Money: 19 billion to 45 billion US dollars of capital expenditure by 2030 (World Economic Forum and Kearney).
In this article
The short answer: three layers, one market
I read the market as three lines rather than one. The first line is what actually moves. IATA’s Press Release No 57 of 9 December 2025 puts SAF output at 1.9 million tonnes in 2025. That is 2.4 billion liters, double the 1 million tonnes produced in 2024. Also, it is only 0.6 percent of total jet fuel consumption, rising to 0.8 percent the following year. The second line is what exists. The World Economic Forum and Kearney put global installed capacity at 4.4 million tonnes by the end of 2024. In addition, a further 6.9 million tonnes of expansion are planned through greenfield projects and retrofitting. The third line is price, which I treat separately. Every database I read counts installed but idle capacity as capacity.
What this means for you: I would put produced volume, installed capacity and price side by side in the model. The reason is that the ratio between the first two tells me whether the constraint is steel or sales.
What is actually being built
Capacity is not fuel: the build queue matters more than the announcements. Reaching anticipated 2030 demand would require an additional 5.8 million tonnes of production capacity. That volume needs a final investment decision by 2026. Also, it sits on top of 4.4 million tonnes installed and 6.9 million tonnes planned (World Economic Forum and Kearney). The four principal technologies differ sharply. HEFA is the most mature and cost-effective, expected to dominate to 2030, but it faces feedstock constraints. Alcohol-to-Jet carries higher capital costs from on-site ethanol processing. Gasification-Fischer Tropsch needs solid feedstock handling and carbon capture. Power-to-Liquid has the highest capital requirements: renewable electricity, electrolysis and CO2 capture. ICAO counts 12 approved pathways, three of them for co-processing, with blend limits from 5 percent to 50 percent. Also, pathway fit depends on regional feedstock availability and processing capabilities.
Specifically, that is the question I put to the feedstock availability page.
What this means for you: I would ask which pathway the project certifies against, and whether that feedstock is contracted, before I read a production curve.
What the rules require
Demand in this market is written by regulation: a mandate is a legal requirement to blend a given share of SAF, and mandates in Southeast Asia sit at very different stages. Singapore’s mandate was to start at 1 percent in 2026. Malaysia and Indonesia have mandates planned, with blueprints or road maps launched in 2024. Meanwhile, Thailand and the Philippines are in progress. The rest of Southeast Asia has no policy (IRENA). Malaysia’s National Energy Transition Roadmap targets a 1 percent blend rising to 47 percent by 2050. In addition, its Aviation Decarbonisation Blueprint assigns SAF 46 percent of emissions reduction by 2050. Indonesia targets international flights at 1 percent SAF by 2027, 30 percent by 2050 and 50 percent by 2060.
Blending mandates took effect at the start of 2025 in Europe and the United Kingdom (International Council on Clean Transportation). I track the detail on the mandates page.
What this means for you: I would read the mandate text rather than the headline percentage. The reason is that dates, penalties and eligible feedstocks decide whether a project has a buyer.
What it costs and how it is priced
Three numbers govern the money. SAF generally costs between 2 and 5 times more than fossil jet fuel. In addition, average production cost in 2024 ranged from 1 461 euros per tonne for biofuels. For e-fuels, it reached 7 695 euros per tonne. That is a premium of 2.1 to 10.6 times (International Council on Clean Transportation). IATA records prices at a factor of two and up to a factor of five in mandated markets. IRENA also tracks the minimum jet fuel selling price (MJSP), the price a plant must reach to cover lifetime costs. Three pricing structures sit on top. The first is a SAF premium marked to a conventional fuel index, which shifts feedstock risk to the supplier. The second is a cost plus model, which transfers variable cost risk including feedstock to the customer.
The third is price reporting agency assessment from Platts and Argus, which runs higher until the market is liquid. The structures are set out on the SAF price page.
What this means for you: I would ask which structure sits in the term sheet. That decides who absorbs a feedstock spike after signing.
The gap between announcements and money
This is where the market is thinnest. Only three airlines, Air France-KLM, DHL and IAG, consumed over 1 percent of SAF in 2023. Also, DHL reached 3 percent, and 15 airlines drive more than 80 percent of demand (World Economic Forum and Kearney). Demand is narrow, and the same few names set the price for everyone else. On the supply side, it takes up to 5 years for SAF projects to reach final investment decision. In addition, fewer than 30 percent of projects had reached it globally by early 2025 (International Council on Clean Transportation). The 1.9 million tonnes expected for 2025 is a downward revision from earlier forecasts. Specifically, it reflects a lack of policy support to take full advantage of installed capacities (IATA Press Release No 57). Fulcrum BioEnergy broke ground in 2016 and filed for bankruptcy in 2024 after missing optimistic deadlines and overstating progress.
What this means for you: I would treat announced targets as an option rather than cash flow. Also, I would underwrite only volumes a counterparty has signed.
Where Southeast Asia sits
The region is both feedstock base and demand centre. IRENA puts progress in this order: Singapore first, followed by Malaysia, Indonesia, Thailand and the Philippines. In addition, most countries rely on mandates rather than subsidies to drive adoption. They promote production through fiscal and non-fiscal incentives. Singapore is the region’s largest aviation fuel consumer at more than 5 million tonnes of fuel per year. In addition, its central location plus Changi Airport’s growth plans make it a favourable location for investors. Neste’s Singapore refinery expansion in 2024 doubled capacity from 1.3 to 2.6 million tonnes per year. Also, Singapore Airlines and Scoot bought 1 000 tonnes in 2024. Malaysia has at least eight active players in refinery construction and feedstock development. That is more than any other country in the region. The wider picture sits on the Southeast Asia SAF page.
What this means for you: I would place the project on that map before I model it. The reason is that the same pathway lands very differently in Singapore, Malaysia and Indonesia.
How investors read these numbers
I read the market as a demand signal with an execution problem, not a demand problem. The industry may require between 19 billion and 45 billion US dollars in capital expenditure by 2030. The range depends on the proportion of HEFA in the production mix (World Economic Forum and Kearney). Ten financial levers are on the table. The first four are research and innovation grants, multilateral development bank support, guarantees and insurance, and strategic investments. Next come long-term offtake agreements, book and claim, private equity, infrastructure investors, tolling and green bonds. Book and claim is a system that sells the environmental benefit of SAF separately from the physical fuel. Long-term offtake is the lever that carries projects to final investment decision. For example, IAG signed a 14-year agreement with a power-to-liquid producer.
The scale requirement underneath is a factor of 1 000 between 2023 and 2050. Also, it implies thousands of new or converted facilities by 2050 (IATA).
What this means for you: I would check which of the ten levers is already committed in the term sheet. The reason is that a project with one lever has one point of failure.
How I would run this if it were my file
I would run this file in a fixed order. I would read capacity, commitments and delivered volume as three separate lines. With 4.4 million tonnes installed against 1.9 million produced, utilisation is the first question (World Economic Forum and Kearney; IATA Press Release No 57). I would test the policy line before the price line. The reason is that mandates drive demand, and poor design stalls momentum. I would price the pathway, not the molecule. The reason is that feedstock drives cost, and capital intensity differs by an order of magnitude between HEFA and power-to-liquid. I would require binding offtake covering the loan tenor before I underwrite anything. That is the lever critical to reach final investment decision. I would also map the regional feedstock position early. Southeast Asia’s strength is also its exposure, and that feeds into how I would finance the project.
What this means for you: if a file answers those five questions, I can take it to an investment committee. I would not need to rebuild the model.
Sources
- IATA, SAF Handbook, May 2024.
- World Economic Forum and Kearney, February 2025.
- IATA Press Release No 57, 9 December 2025.
- IRENA, December 2024.
- International Council on Clean Transportation, 6 October 2025.
- ICAO, Aviation Benefits Beyond Borders, consulted 16 November 2026.
Frequently asked questions
How big is the SAF market today?
SAF output is expected to reach 1.9 million tonnes in 2025, 2.4 billion liters, double the 1 million tonnes of 2024, and 2.4 million tonnes in 2026, which is 0.6 percent of total jet fuel consumption in 2025 and 0.8 percent the following year (IATA, Press Release No 57).
Why is installed capacity higher than produced volume?
Because capacity has to be built and financed before it runs: installed capacity reached 4.4 million tonnes by the end of 2024 with 6.9 million tonnes of expansion planned, and a further 5.8 million tonnes would need a final investment decision by 2026 to meet 2030 demand (World Economic Forum and Kearney).
What drives the price of SAF?
Feedstock is the primary cost driver, with capital expenditure and conversion yield on top; the estimated average production cost for 2024 ranged from 1 461 euros per tonne for biofuels to 7 695 euros per tonne for e-fuels (International Council on Clean Transportation).
Where is Southeast Asia in the SAF market?
Progress varies, with Singapore first, then Malaysia, Indonesia, Thailand and the Philippines; Singapore is the region’s largest aviation fuel consumer at more than 5 million tonnes per year and Malaysia has at least eight active players in refinery construction and feedstock development (IRENA).
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If you want to test one pathway or one country against these numbers, I offer introductions to investors who already work in this market, and I prepare the file so the first meeting starts from evidence rather than from ambition.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.