Home » UCO Price Volatility: Writing a Feedstock Contract a Lender Can Live With
UCO Price Volatility: Writing a Feedstock Contract a Lender Can Live With
10 min read · Nov 2, 2026 · By Alex
No, the price of used cooking oil cannot be fixed in a contract for the life of a loan. Feedstock is the lion’s share of total HEFA (hydroprocessed esters and fatty acids) production costs. Its price varies significantly with market supply and demand. What a lender can give you is a published index (a named, dated price assessment) and a defined band. In addition, a model that shows the project still services its debt at the top of that band. I build that around the feedstock availability picture in Southeast Asia, starting from used cooking oil (UCO) as the reference material. This is why uco price volatility belongs in the credit file rather than in a footnote.
A sustainable aviation fuel project file usually arrives with one feedstock price, held flat for the whole debt tenor. I do not argue with the number, I ask what the record shows it doing in the months it moved. The answer sets the width of the band you have to accept.
In short
- The answer: I do not fix the price, I document the band around a published index.
- The drivers: Seasonality, a cancelled export tax rebate, slower collection and export permits all move it.
- The proof: UCO fob ARA averaged $1,203.92/t in 2025 and peaked at $1,250/t on 24 March.
- The mechanism: An index, a band, review dates and a volume that can still be sourced.
- The test: The model services its debt at the top of the band, not at the average.
In this article
The short answer: you document the band, you do not fix the price
Feedstock accounts for the lion’s share of total HEFA production costs. In addition, the price of that feedstock can vary significantly with market supply and demand (IATA, September 2025). SAF prices already exceed fossil-based jet fuel by a factor of two, and by up to a factor of five in mandated markets. At current price levels that premium translated into an additional USD 3.6 billion in fuel costs for the industry in 2025 (IATA, 9 December 2025). On the feedstock side, UCO fob ARA prices averaged $1,203.92/t so far in 2025 and peaked at $1,250/t on 24 March, the highest level since 10 October 2022 (Argus, 25 March 2025). That is the whole answer, and everything below is how I build it.
What this means for you: a flat feedstock line is not a conservative assumption, it is an undocumented one. I want the band in the model before any stress case, and I want the top of that band to be the case that still services the debt.
Why the price moves, month by month
I read the record as four separate drivers, none of them forecastable at underwriting. First, a seasonal shift to blending biodiesel with a higher cold filter plugging point (CFPP), the temperature at which fuel stops flowing, including Ucome, which raises demand from Ucome producers as warmer months approach. Second, China’s cancellation of a 13pc export tax rebate on UCO, which limited availability. Third, the seasonal slowdown of European UCO collection in February and March. Fourth, the pause on new export permits for UCO, POME and Hapor announced by Indonesia’s trade ministry at the start of the year.
Since Indonesia suspended exports on 8 January, waste oil export values have mostly been at a premium to crude palm oil, reversing the historical pattern, in which Pome oil carried a set discount to CPO. I turn that into a contracting structure: one named index, plus a forward curve, the series of prices quoted today for future delivery.
What this means for you: each driver gets named in the file with the month it bites. Therefore, the band is read against a calendar, not a hope.
What that movement does to a project file
1.9 million tonnes of SAF in 2025 represented only 0.6% of total jet fuel consumption. Airlines still paid a premium for every tonne of it. At current price levels that premium translated into an additional USD 3.6 billion in fuel costs for the industry in 2025 (IATA, 9 December 2025). In fact, the premium is born in the feedstock, because feedstock is the largest single cost in HEFA production. HEFA holds over 90% of current or upcoming SAF capabilities at costs currently 2 to 2.5 times that of conventional aviation fuel (IATA, September 2025). e-SAF faces a much higher cost base, potentially up to 12 times that of conventional jet fuel, which is the outer edge of the same problem. This is also why the sustainability criteria carried by the feedstock belong beside its price: a cheaper tonne that fails the criteria is not supply.
What this means for you. I model the feedstock line with a stated top rather than a point estimate, and I show debt service at that top. That is where the premium lands.
How this material is actually priced today
Independent assessors publish daily and weekly IOSCO-aligned physical UCO spot prices across US FOB and delivered hubs and FOB China. They add forward delivery curves and regional price spreads. Traders settle physical contracts across the global biofuels trade against those benchmarks (Fastmarkets). I do not have to invent a reference: the sustainable aviation fuel price in the model can point at a published number with a date and an audit trail.
The published record also shows the amplitude a contract has to survive. UCO fob ARA averaged $1,203.92/t in 2025 and peaked at $1,250/t on 24 March. Pome oil cif ARA reached around $1,178/t in the same period, against $926.67/t a year earlier. Pome oil fob Malaysia rose $45/t to $1,075/t on 25 March, above crude palm oil. Collecting UCO in Asia is around 30% cheaper than in Europe. That sets the floor of the arbitrage between origins (Transport & Environment, 18 June 2024).
What this means for you. I name one assessment in the supply agreement and write its publication schedule next to the review dates. I size the band from the spread the record already shows.
What regulation does to the demand side of the curve
In fact, law sets demand here, rather than negotiation. ReFuelEU Aviation sets a 2% share of SAF at EU airports from 2025, rising to 70% from 2050, and a 1.2% share of synthetic aviation fuels from 2030, rising to 35% from 2050, with more than 95% of air transport departing from EU airports covered. That calendar fixes the shape of the request curve (European Commission). Asia follows. Singapore targets 1% SAF for all departing flights from 2026, increasing to 3 to 5% by 2030, supported by a levy. South Korea and Indonesia require 1% SAF from 2027. Japan has set a 10% SAF blending target for domestic airlines by 2030 (IATA, September 2025). Supply answers slowly. Specifically, global UCO supplies should rise from 3.7 billion gallons in 2022 to between 5 and 10 billion gallons in 2030 (LMC, GlobalData for Clean Fuels Alliance America).
What this means for you. I read the mandate dates as fixed demand and the supply forecast as a slow response. I price the gap between them rather than assuming it away.
Three ways a price clause fails
First, a fixed price with no reference. When the market moves, one side performs and the other restructures. The contract stops being a contract and becomes a renegotiation. Second, a reference to a market that policy can close. If governments limit the use of UCO, demand can fall and the incentive to increase supplies declines. Fraud concerns could lead to UCO being banned from use. Stricter certification could push collectors to other markets (LMC, GlobalData for Clean Fuels Alliance America). Third, a formula that ignores seasonality. European collection slowed in February and March and prices held firm anyway (Argus, 25 March 2025).
None of the three shows up in a single price number. That is why uco price volatility has to be described in the clause itself. It is also why I ask which origin closes first.
What this means for you. I look for those three failure modes in the draft clause before I look at the price, because a well-priced clause that cannot survive a policy change is still a defect.
The order I would run the work in
I start from the index, not from a number. Name one published assessment and define the band around it. State who takes which side of the band and for how long. Then write the review dates next to the mandate calendar, and only then size the volume. Two facts anchor the sequence. For example, Europe consumes 130,000 barrels of UCO a day, 8 times more than it collects (Transport & Environment, 18 June 2024). The EU takes a 2% SAF share from 2025 rising to 70% from 2050 (European Commission). The demand side of the curve is not discretionary. Alongside the price clause I put a mass balance clause. It pools certified and non-certified volumes and tracks the certified share through records, so the tonne delivered can be traced back to its origin. I run feedstock supply work in the same order.
What this means for you. I would rather present a documented sequence than a defensible number, because the sequence is what a reviewer can test.
How I would run this if it were my file
I take my model to the published record before I take it to committee: feedstock as the lion’s share of HEFA production costs (IATA, September 2025); SAF at a factor of two over fossil jet fuel and up to a factor of five in mandated markets, with USD 3.6 billion of premium in 2025 (IATA, 9 December 2025); UCO fob ARA averaging $1,203.92/t with a peak of $1,250/t (Argus, 25 March 2025); Pome oil at a premium to crude palm oil since 8 January, with regional waste oil prices at three-year highs in September (Argus, 15 December 2025); and 3.7 billion gallons of global UCO supply in 2022, rising to between 5 and 10 billion gallons in 2030 (LMC, GlobalData for Clean Fuels Alliance America). Every one of those numbers is already public. Therefore, the model either sits inside the band they describe or it does not.
What this means for you. I would rather defend a structure that documents the volatility than a number that assumes it away. In addition, I would want the same file on my desk if I were on the other side of the table.
Sources
- IATA, 9 December 2025.
- IATA, September 2025.
- Argus, 25 March 2025.
- Argus, 15 December 2025.
- Transport & Environment, 18 June 2024.
- Fastmarkets, 16 November 2026.
- LMC GlobalData, September 2023.
Frequently asked questions
Can I fix the price of used cooking oil for the life of the loan?
Not credibly. Feedstock is the lion’s share of total HEFA production costs and its price varies significantly with supply and demand, and the published record shows UCO fob ARA averaging $1,203.92/t with a peak of $1,250/t inside a single quarter (IATA, September 2025; Argus, 25 March 2025). A fixed price is therefore a transfer of risk, not a removal of it.
Which index should my supply agreement reference?
One that already exists and is auditable. Independent assessors publish daily and weekly IOSCO-aligned physical UCO spot prices with forward delivery curves and regional price spreads, and those benchmarks are used to settle physical contracts across the global biofuels trade (Fastmarkets). I would name a single assessment and its publication schedule in the agreement, and define the band around it in the same clause.
How much price movement should my financial model absorb?
How much movement the model absorbs
At least the band visible in the published record: from $1,203.92/t on average to a peak of $1,250/t in the same period, and from $926.67/t to around $1,178/t for Pome oil cif ARA year on year (Argus, 25 March 2025). I would then test the case in which collection slows in the same months the mandate volume is due.
Who carries the risk when feedstock prices spike?
The contract says so in advance. The party holding the band between the index and its edges carries it, with review dates written next to the mandate calendar and a volume that can still be sourced when one origin is closed (European Commission; IATA, September 2025). I write that allocation into the supply agreement and into the model, so the answer does not depend on who is in a stronger position at the time, or on any promise that prices will hold.
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If you are at pre-FID and the feedstock line in your model still sits flat, I can walk the structure through with your credit team and put the band, the index and the review dates on one page: investor introductions start from that shared document.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.