Advanced Biofuels and Biomass: Which Routes Are Financeable

10 min read  ·  Sep 2, 2025  ·  By Alex

advanced biofuels and biomass

An advanced biofuel is financeable when four things are already true: the feedstock can be contracted and counted, a regulation or offtake obligation creates the buyer, the conversion step has run at reference commercial scale, and the policy frame has not been waived since. A route that fails any one of those four is not financeable, however good the chemistry is. I apply that test to every advanced biofuels and biomass route before I write a credit paper, because the tracked record of the last decade shows that losses come from contracts and rules, not from molecules. This article sits under the parent article on biomethane explained, where the same discipline already decides which plant deserves a second look.

I take the tests in the order a lender reads them: the record of what has been built, then the buyer, the feedstock, the conversion step and the market that carries the volume. Sections 7 and 8 turn the four tests into a checklist and a row I write.

In short

  • Four tests: feedstock, buyer, commercial maturity, policy frame.
  • Tracked record: 119 facilities followed in 2024, of which 31 plans canceled.
  • Demand: the biofuel share of transport fuel rises from 5.6 percent in 2023 to 6.4 percent in 2030.
  • Southeast Asia: one national programme backs biodiesel, not advanced biofuels.
  • Maturity: the lipid pathway is fully commercial, the thermochemical ones are nearing it.
Facebook
Twitter
LinkedIn

In this article

What advanced biofuel means in a credit paper

The four tests, in the order I apply them: a feedstock that can be contracted and counted, a buyer created by a mandate or an offtake obligation, a conversion step that has run at reference commercial scale, and a policy frame that has not been waived since. A route that fails any one of them is not financeable, however good the chemistry is.

Terms first. An advanced biofuel comes from a feedstock that is not food or feed and a conversion step past the first generation, also called second-generation fuel. Lignocellulose is the woody fibre of plants, made of cellulose 35 percent to 50 percent, hemicellulose 20 percent to 35 percent and lignin 10 percent to 25 percent; cellulosic ethanol is the alcohol made from it. Feedstock is the material delivered to the plant gate, a mandate is a regulation requiring a quantity of fuel to be blended or sold, and an offtake obligation is a contract where a buyer commits to take the product. Commercial scale means a plant of the same step has run long enough to publish a result, FID is the final investment decision where capital is committed, and bankable is what I call a project a lender will lend against.

What this means for you: write the four tests into the concept note before any process design work, because the first gap is where the file stops.

The four tests, in the order a lender reads them

Evidence before enthusiasm. The count in the IEA Bioenergy Task 39 tracking review published in 2025 runs to 119 facilities in 2024: 41 operational, 10 under construction, 16 planned, 21 idle and 31 canceled plans. Up to 2015, 50 facilities were operational worldwide, and many were then canceled or idled without the expected capacities arriving. European operational capacity reached around 90 000 t per year in 2013 and peaked at about 165 000 t per year in 2022. A route that shares its feedstock with advanced biofuels in multi-product plants still has to survive this count.

The stated causes of the slow advance are technological complexity, limited feedstock availability, high production costs, modest commercial outcomes, inconsistent policy support and competition from lower-cost biofuels: the four tests in other words. A waiver is the official suspension of an obligation the regulation would otherwise impose, and a file carrying one has already failed the policy test.

What this means for you: bring the count, not the ambition. If a plant near your route was canceled, I will find it, so arrive with the reason it stopped.

The demand is written, not hoped

A mandate creates the buyer: it turns an intention into a legal obligation to blend or sell. The logic is easiest to read in low-carbon fuel mandates, and one national programme shows both the strength and the limit. The USDA Foreign Agricultural Service biofuels annual for Indonesia published in 2024 records a 35 percent biodiesel blending rate maintained in 2024, with B35 nationwide in August 2023 after B30 in January 2020 and B20 in 2018. Estimated biodiesel production in 2024 was 13 billion liters, 3 percent higher than in 2023. The programme is financed by a levy on palm oil product exports collected by a fund agency that subsidises the price spread between biodiesel and fossil diesel.

The limit matters more to me. Hydrogenation derived renewable diesel, also called hydrotreated vegetable oil, and sustainable aviation fuel are not supported by that mandate, and no incentives exist to lower the carbon intensity of the biodiesel supplied. Fuel-grade ethanol stays small: E5 stations increased from 15 in 2023 to 65 as of April 2024. The same report lists 477 kilolitres per day of renewable diesel and aviation fuel capacity operational at one refinery, 3 180 kilolitres per day under development and 159 kilolitres per day in trial, and the mandate obliges no one to buy any of it. A rule that stops at the first generation buys the first generation.

What this means for you: identify who is obliged to take your product, in which volume and under which article. If the answer is a blend that already exists, you have no new buyer.

Feedstock that is already counted

SAF feedstock availability in Southeast Asia is the clearest case of residues that are physically present and still not contracted. The ICCT techno-economic analysis of cellulosic ethanol in Indonesia published in 2020 states that palm biomass residues such as palm trunk and empty fruit bunch, currently wasted, could support dozens of commercial-scale plants. It also models 30 commercial facilities over 10 years: 2 billion liters of cellulosic ethanol annually, replacing a conservative estimate of 4 percent of the country’s gasoline consumption.

Counting the feedstock is only half. The same 2020 analysis puts the subsidy needed as low as IDR 6,720 (US$0.46) per liter, almost 60 percent lower than the subsidy needed in European countries. For the first 10 commercial facilities it puts upfront grants at IDR 90 to 116 trillion (US$6.1 to 7.9 billion), or an annual subsidy of IDR 4.7 to 6 trillion for the whole industry, which is 20 percent lower than the palm biodiesel subsidy of 2015 to 2019. Its recommendations follow the same pairing: name palm residues as eligible feedstocks, offer a production subsidy or investment grants, build a supply chain with rural infrastructure, and site plants in special economic zones to cut transport costs.

That pairing, counted feedstock plus a written incentive, is what I take to a lender. Feedstock without the incentive stays a study: the cost gap becomes the lender’s exposure.

What this means for you: contract the tonnes first, then get the incentive written into a regulation with a review date. Neither document moves the file alone.

Which conversion step is already commercial

Sustainable aviation fuel is where the maturity test is easiest to read, because volumes are tracked and pathways ranked. HEFA, hydrotreated esters and fatty acids, is the lipid-derived pathway: it is fully commercial and will continue to supply the majority of aviation fuel volumes up to 2030, according to the IEA Bioenergy Task 39 report on sustainable aviation fuel published in 2024, which also notes that 62 percent of aviation emissions reductions have to come from that fuel.

That 2024 report sets the limits beside the promise. Only about 15 percent of hydrotreated fats and oils fall in the jet range, and raising the share costs more and loses overall liquid yield; new facilities can divert up to 70 percent of total liquid product to aviation fuel. Gasification with Fischer-Tropsch synthesis and alcohol-to-jet are nearing commercial status, and in the conventional Fischer-Tropsch process the product split follows the Anderson-Schulz-Flory statistical model, which holds the straight-run jet fraction to about 40 percent.

The first small-scale commercial facility using gasification with Fischer-Tropsch synthesis started operation in 2022 on municipal solid waste, and its liquids are approved for co-processing at a maximum of 5 percent blends. Power-to-liquids sits at a lower technology readiness level, with the reverse water gas shift reaction still to be resolved. Gasification is designed around the specific feedstock, so preparation, reactor choice and gas cleanup move with it. I read a pathway as commercial only when the same step has run at reference scale with a published yield.

What this means for you: take the fully commercial pathway to the first FID and treat the nearer-commercial ones as a later phase, with a buyer signed before capital is committed.

Where the volume actually grows

Book and claim only works where there is a volume to claim, so I start with where the volume lands. The IEA renewables report published in 2024 puts renewable fuel demand in industry, buildings and transport at 22 EJ in 2023, which is 5 percent of global energy demand for those sectors: modern solid bioenergy 75 percent, liquid biofuels 20 percent in transport, biogases 5 percent.

On the transport line, the share of biofuels in total liquid fuel transport demand expands from 5.6 percent in 2023 to 6.4 percent in 2030, reaching 215 billion liters a year, 5.7 EJ. Five markets account for 85 percent of that growth, and by 2030 aviation and shipping take more than 75 percent of new biofuel demand. In 2024, more than 80 countries had liquid biofuel policies: a wide mandate base on a thin volume base.

That is where a certificate can change hands without changing a plant: a book and claim arrangement transfers a claim on a volume that must physically exist, it does not create it. A certificate market on a thin volume reprices the claim, not the plant: a high certificate price tells me the supply is short, not that a project is well built.

What this means for you: size the route against the physical volume in your region before you price a certificate, and never let a certificate price stand in for an offtake.

The evidence I ask for before I call a route financeable

Five items, in the order I ask for them:

  • Contracted feedstock with tonnage and season: tonnes per year, delivery months, counterparty signature.
  • A written mandate or a signed offtake with tenor: the article that obliges the buyer, the volume, the years it runs.
  • A reference plant of the same conversion step that has run at commercial scale: a published result, not an announcement.
  • A policy frame with no waiver history: the rule that creates the buyer has survived review without suspension.
  • A product specification the buyer accepts: the standard, the blend level, the test method.

The waiver history is the item sponsors skip. The pattern is visible in 2015, when 18 cellulosic ethanol facilities were operational in the United States, four at TRL 8, eight at TRL 6 to 7 and six pilot facilities, and large-scale production failed to develop as anticipated: the cellulosic mandates of the Renewable Fuel Standard were repeatedly waived. The obligation existed, the capacity behind it did not, and the rule was suspended rather than the build accelerated.

What this means for you: collect the five documents before you price anything. Four are public, and the fifth, the feedstock contract, is the one that tells me whether the route is real.

How I would write the route into the credit paper

Four rows, and each holds cells rather than adjectives:

  • Feedstock and contract: tonnes per year, season, haul distance, contract tenor, counterparty.
  • Buyer and mandate or offtake: the obligation, the volume it covers, its start and end dates.
  • Conversion step and its reference plant: the step, the plant that has run it at commercial scale, its published yield.
  • Policy frame and its review dates: the regulation, the body that applies it, the dates it is next reviewed.

The row is finished only when every cell cites a document: a contract, a regulation, a permit, a published result, a review date. Three of the four cells is a screening result, not a financeable project, and I will say so before a lender has to.

What this means for you: fill the four rows with citations and the credit paper writes itself; leave one cell empty and you are back at concept stage with a process deck.

Sources

Frequently asked questions

Four pieces of evidence, not four opinions: feedstock contracted with tonnage and season, a buyer created by a written mandate or an offtake with a stated tenor, a reference plant of the same step run at commercial scale, and a policy frame never waived. Three of the four is a screening result.

No source I use prints a unit price for both, so I give none. What is printed in 2020 is a subsidy level: cellulosic ethanol in Indonesia could need as little as IDR 6,720 (US$0.46) per liter, almost 60 percent lower than in European countries, A lender prices the gap an incentive closes, how long it is written for, and whether a buyer is obliged to take the product.

Palm residues, specifically palm trunk and empty fruit bunch, described in 2020 as currently wasted and able to support dozens of commercial-scale plants. The fats and oils chain that feeds the fully commercial lipid pathway is the other documented route. On the demand side, fuel-grade ethanol stations grew from 15 in 2023 to 65 as of April 2024, real growth from a small base.

I give no duration, because none is printed in the sources I use. What is printed is a record: in 2024, 605 000 t per year of planned capacity had an unknown outcome, while an earlier wave promising 880 000 t per year produced none of it. Plants that did run came online between 2012 and 2024, including a Brazilian plant of 62 000 t per year, while another of 31 767 t per year has been idle since 2025.

1

A short call is usually enough to see where your project stands.

Before a route goes to lenders, I test the feedstock line through my feedstock supply work: tonnage against season, contract tenor, haul distance and counterparty, and I hand back the gaps in writing.

I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia