How to Secure SAF Feedstock for a Project: What a Credit Committee Actually Checks

10 min read  ·  Nov 2, 2026  ·  By Alex

saf feedstock security

Securing sustainable aviation fuel feedstock for a project means showing four verifiable things. First, a volume contracted for as long as the debt runs. Second, a source that meets the eligibility criteria of the market you sell into. Third, sustainability evidence that survives an audit. Fourth, a back-up plan, which is a named alternative source I can switch to if the primary volume does not arrive. Feedstock here means the raw material that becomes the fuel. This part of the file takes the hardest challenge. I keep the regional availability picture beside me while I structure, because supply that cannot be traced cannot be contracted. SAF feedstock security is a documentation exercise first and a procurement exercise second.

I am writing for a developer at pre-FID stage in Indonesia, Malaysia or Singapore, holding a file and asking how to get a credit committee to a yes. That committee reads the evidence before it reads the model. Everything below follows what lenders, certifiers and industry data actually publish.

In short

  • Volume: I contract the tonne for as long as the debt runs, not for the first few years.
  • Eligibility: the source has to meet the criteria of the market I sell into.
  • Evidence: auditable documents, with the depth of audit known before signature.
  • Price: feedstock is the largest cost component and it moves with the market.
  • Back-up plan: a named alternative volume and a stated route if the first one fails.
Facebook
Twitter
LinkedIn

In this article

What a credit committee means by secured feedstock

Secured does not mean bought today. It means arranged, evidenced and backed. Dentons reports that lenders will expect a long-term feedstock supply arrangement from a credible and reliable source that meets the EU’s strict eligibility criteria, plus a back-up plan in case of critical feedstock unavailability. Someone else can claim the same tonnes. Dentons notes competition for feedstock supply in light of other EU-mandated targets that also require biogenic feedstocks for other fuels. Specifically, Dentons says this competition adds a greater level of uncertainty to feedstock cost and value in SAF production.

Due diligence is not a formality in a nascent sector. Lenders will perform detailed due diligence and greenhouse gas modelling to make sure the fuel meets the EU’s regulatory requirements. HEFA, or hydrotreated esters and fatty acids, is the most proven process. It runs on bio feedstocks, which puts its production economics in direct competition with hydrotreated vegetable oil and biodiesel.

What this means for you: SAF feedstock security, on my page, is four lines I can show with a document rather than describe in a meeting.

Where the tonnes have to come from

Eligibility is a contractual condition, not a bonus. CO2 and biogenic feedstock supply must comply with the greenhouse gas reduction and sustainability criteria under RED III and the delegated acts. RED III is the EU renewable energy directive that carries those criteria for transport fuels. I run my draft past the criteria that decide eligibility before I approach a supplier.

The eligible waste side is narrow. Second generation feedstocks cover used cooking oil, animal fat, industrial grease and residues such as palm oil mill effluent. These carry high emission reduction potential but relatively limited availability.

The region matters for a Southeast Asian file. Together with the People’s Republic of China, ASEAN will emerge as a critical feedstock hotspot. It offers about 240 Mt of biomass feedstock for SAF production by 2050, about 15% of the global total. ASEAN contributes over 80% of the world’s palm oil production as of 2023, and land caps further expansion.

What this means for you: I name the rule that makes a tonne eligible before I name its price. In addition, I keep a second source in the same file.

The evidence I ask for before I sign

Voluntary schemes use a mass balance approach. Nobody segregates the physical material, accounting documents track the product, and auditors check those documents. In plain terms, the certificate follows the paperwork, not the pipe.

The scheme publishes the audit depth. An audit of a point of origin, the site where the waste is collected, only kicks in above 5 tonnes of used cooking oil (UCO) per month. Only 9% of ISCC-certified collecting points in China, Malaysia and Indonesia saw a sample of their points of origin audited. The remaining 91% went without any audit.

On the mill side the rule has tightened. Since April 2023 ISCC EU makes Points of Origin, that is the palm oil mills, individually certified and annually audited. Auditors check the annual amount of processed fresh fruit bunches and the sterilisation technology. They also check the recovery method of POME oil and the annual amounts of generated waste streams.

Every supplier has to tell me which of these regimes it sits under: mass balance, points of origin, or book and claim. That answer is where the supply file starts.

What this means for you: I ask for the audit trail before I ask for the price.

Volume and price in the same paragraph

Feedstock accounts for the lion’s share of total HEFA production costs. In addition, the price of the feedstock can vary significantly with market supply and demand dynamics. That is why I never write the price page without the supply page.

The levelised cost sits above the incumbent. HEFA offers the lowest levelised cost compared to other pathways, with costs currently 2 to 2.5 times that of conventional aviation fuel.

The market the project sells into is still thin. By 2030 global SAF production capacity should reach around 20 Mt with the project success factor applied. HEFA refineries are likely to still dominate, accounting for about 95% of total volume.

Policy instruments identified as decisive for SAF production include economic incentives, financial instruments such as contracts for difference, guarantees and insurance, and infrastructure and supply chain commitments including SAF accounting mechanisms and registries.

I read how the market prices the fuel beside my feedstock quote, because the offtake carries the premium.

What this means for you: I put the feedstock quote and the fuel price in one sentence. I also name who carries the move.

The supply contract next to the offtake

The two contracts are read together. Investors often require offtake agreements to cover at least 70 to 80 percent of annual capacity. In addition, some lenders require reliable offtake for 100 percent of the SAF they finance across the full loan tenor. Moreover, the offtake contract needs to cover the tenure of debt financing, for example 8 to 14 years.

Offtake contracts are often non-binding memoranda of understanding. A project needs contractually binding agreements to reach FID.

The same tail problem hits supply. Even a 10 year airline purchase commitment would leave a large, uncontracted tail for a long-term debt tenor of perhaps 20 to 25 years. In addition, the published fix is to interpose an intermediary of sufficient creditworthiness between the parties.

So I write the offtake strategy and the supply contract as one negotiation, with the same counterparty credit question on both sides.

What this means for you: I ask the same question of the supplier as of the buyer. How long does your commitment run and who stands behind it.

The route to FID this evidence has to travel

The SAF refinery lifecycle has five critical phases: conceptualization, pre-feasibility, FID, construction and commissioning. Also, the feedstock file has to be complete by the time pre-feasibility closes. This is because that is when the numbers are first tested against a lender’s view.

I count the capital behind those phases too. Installed SAF capacity globally reached 4.4 Mt by end 2024, with 6.9 Mt of expansion planned. An additional 5.8 Mt would need final investment decisions by 2026 to meet 2030 demand. In addition, the industry may require between 19 billion and 45 billion US dollars of capital expenditure by 2030 depending on the technology mix.

Time is part of the evidence. I can process HEFA feedstocks in standalone SAF plants, which typically take 3 to 5 years to build and start production. Alternatively, co-processing in existing refineries works with modest modifications.

That is why the route to FID is scheduled around the supply contract and not after it.

What this means for you: I time the supply contract, the audit and the construction schedule on one calendar. This is because a delay in any one of them moves FID.

Who else wants the same tonnes

The competition is measurable. Europe consumes 130,000 barrels of UCO a day, 8 times more than it collects, the United States consumes 40,000 barrels a day, and global airlines will triple demand for UCO by 2030.

Cost is why the volumes move. Collecting UCO in Asia is around 30% cheaper than in Europe. In addition, more than 80% of current SAF volumes come from UCO.

Lenders see the same squeeze from the regulation side: other EU-mandated targets also require the use of biogenic feedstocks for other fuels. I model that overlap as a cost risk rather than a background assumption.

I also check the second generation side against what is physically available. This is because high emission reduction potential does not mean unlimited supply. In addition, a project that assumes a tonne it cannot get has already failed before the committee reads it.

What this means for you: I price the feedstock as if someone else is bidding for the same tonne. This is because someone else is.

How I would run this if it were my file

I test the file against what financiers say blocks them. The largest barrier to providing the necessary financing is uncertainty about technology maturity, and beyond technology, securing long-term regulatory certainty is a key requirement. That technology uncertainty covers sufficient feedstock supply and pricing.

The scale of the gap sets the tone. ATAG’s Waypoint 2050 estimates demand for between 330 million and 445 million tonnes of sustainable aviation fuels, against production of just 0.2 million tonnes in 2022. Specifically, that gap necessitates 5,000 to 7,000 new facilities and an investment between $1 trillion and $1.5 trillion. Nothing in that gap closes on optimism; it closes on documents.

My committee page then holds four lines. The volume I have contracted, the source that is eligible, the evidence that auditors actually checked, and the back-up plan.

What this means for you: if one of those four lines is empty, I stop and fill it before I send the file. This is because the committee will read it as a gap rather than a plan.

Sources

Frequently asked questions

It means a long-term feedstock supply arrangement from a credible and reliable source that meets the eligibility criteria of the market selling into, plus a back-up plan in case of critical feedstock unavailability, with the lender performing detailed due diligence and greenhouse gas modelling to confirm the fuel against the regulatory requirements.

A contract helps, but lenders expect the arrangement to be long-term and paired with a back-up plan. They are reluctant to take significant merchant exposure for a new sector, so any uncontracted portion needs a detailed marketing analysis and stated implications for debt sizing.

Eligibility follows the greenhouse gas reduction and sustainability criteria under RED III and the delegated acts. On the waste side these are second generation feedstocks such as used cooking oil, animal fat, industrial grease and palm oil mill effluent, and Annex IX lists palm oil mill effluent and empty palm fruit bunches among the materials that qualify.

Auditable documents. Voluntary schemes run on mass balance, where accounting documents track the product and those documents are audited rather than the physical material being segregated. A point of origin is audited only above a published monthly volume threshold, and since April 2023 palm oil mills are individually certified and annually audited.

Not sure your project would survive a credit conversation?

A short call is usually enough to see where your project stands.

When the four lines hold, the next question is who funds the gap between pre-feasibility and FID. I can make the introduction at that point. In addition, investor introductions work best once the volume, the eligibility, the evidence and the back-up plan are all on paper.

I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia

I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.

More about me·Get in touch

Facebook
Twitter
LinkedIn

Related articles