We Connect Asia

SAF

SAF Heads of Terms vs Binding Offtake: What Actually Raises the Money

10 min read  ·  Nov 2, 2026  ·  By Alex

saf heads of terms vs binding offtake

No, an agreed heads of terms, meaning the short document that lists the points two parties have settled in principle, is not enough to raise money. Pre-deal documents are generally not intended to be legally binding except for named clauses such as confidentiality, exclusivity and expense reimbursement, and an offtake contract that starts life as a non-binding memorandum of understanding, a document listing the points intended for a later contract, has to become a contractually binding agreement before a project reaches final investment decision. That is the answer I give the developer at pre-FID stage, and the wider context sits in how to secure SAF offtake agreements. The comparison you are running is a SAF heads of terms vs binding offtake, and the two documents do different jobs.

In this piece I set the pre-FID document set for sustainable aviation fuel against what a credit committee actually reads, clause by clause. The distinction decides whether the file moves forward, and it is far cheaper to settle at the heads stage than after a term has been tabled with a lender.

In short

  • Heads of terms: a negotiating record that is generally not legally binding and is not the contract that sells the fuel.
  • Binding clauses: confidentiality, exclusivity and expense reimbursement, named expressly so a court can identify them.
  • Credit test: a contractually binding offtake covering the loan tenor and at least 70 to 80 percent of annual capacity.
  • Pricing: cost, adjustment formula and credit support belong in the binding document, not in the principle list.
  • Sequence: sign the heads, write the binding column, then close the definitive offtake before FID.
Facebook
Twitter
LinkedIn

In this article

Two documents, two jobs

Pre-deal documents set out certain key terms of a transaction agreed in principle between parties, negotiated and signed at the beginning of a transaction, before the definitive documentation is drafted. The typical forms are a term sheet, which I read as an abbreviated list of key points, a letter of intent, which takes letter form and may carry more detail, and a memorandum of understanding, generally more comprehensive than both.

In a SAF file the heads of terms is a negotiating instrument. It records where the parties have agreed in principle and it gives both sides one shared list to argue about. It does not oblige an airline to lift fuel and it does not oblige a producer to deliver.

The two documents answer different questions: the heads of terms answers whether the parties are aligned, the binding offtake answers who pays, for how long, at what price and with what recourse.

What this means for you: I treat the heads of terms as a milestone on the pre-FID path, not a financing document, and I keep the definitive offtake on my critical path.

What binds you anyway

Pre-deal documents are generally not intended to be legally binding, with key exceptions. They can be used to bind a counterparty to legally enforceable obligations during negotiation of the final agreement, for example confidentiality, exclusivity and expense reimbursement, and ambiguously drafted pre-deal documents may be interpreted by courts to create other binding obligations. A binding clause is a provision the parties intend to be enforceable from signature, so I name mine.

Even where the terms are not legally binding, parties may feel a moral commitment to them, and a signed list becomes expensive to reopen. The practice tip is to expressly specify any key terms that should be legally binding on either party, because that raises transaction certainty.

Whether a document binds depends on its language, and a court looks at multiple factors, so the label on the front page settles nothing.

What this means for you: when I am weighing the offtake agreement work, I sign a heads of terms only after the binding column is written out and checked against the definitive contract.

What the lender waits for

Offtake contracts are often non-binding memoranda of understanding, and contractually binding agreements are needed for a project to reach final investment decision (World Economic Forum, February 2025).

Every project finance lender scrutinizes offtake agreements because lenders rely on them to provide the financial assurances needed to validate the cash flow forecasts that form the basis for loan repayment, and quite simply, offtake agreements make many projects bankable (Global Trade Funding, 13 March 2022).

Because the project is not yet built or operating, there is no existing cash flow to pay debt service, only financial models that are far less certain, and the offtake agreement supplies the documentary evidence that validates them.

A credit committee does not read intentions. It reads the document that obliges a buyer to pay, for how long, at what price, and with what recourse when the buyer fails.

What this means for you: before I build the model for reaching FID on a SAF project, I check whether the signed page in front of me is an obligation or a statement of intent, because the two are read very differently.

The test a court and a lender apply

An offtake contract is enforceable when the essential terms are certain enough. A bare agreement to agree on price or volume generally is not enforceable, while a defined formula with a named benchmark, a fallback source and a stated calculation method generally is (Mayo Law, consulted 15 November 2026).

Price disputes are common because parties think they agreed on economics when they only agreed on a concept, and market price is not a pricing mechanism. If the formula is complex, I define the source, timing, fallback mechanism and who calculates the adjustment, because a benchmark missing on a given date should already have a stated answer.

The same draft has to survive lender review. Projects can expect the change in law risk, meaning a shift in the regulatory rules during the term, to feature prominently in lender due diligence, and ideally the costs of compliance with tightened SAF regulatory requirements should be passed to the offtaker under the offtake contract (Dentons, 15 April 2025).

What this means for you: I test the pricing and change-in-law wording with my contracting and risk management process before circulation, because the clause that fails in a dispute is usually the one nobody tested.

Where price and risk sit between the two documents

The pricing decision belongs in the binding contract, not in the heads of terms. In cost-of-production and cost-plus models, more risk is passed to the buyer, who would absorb variations in feedstock price or other operational costs incurred by the SAF producer (IATA, 12 May 2024).

Clauses that allow the seller to renegotiate pricing mid-contract or even yearly can be introduced, and if uncapped they add complexity to an airline’s fuel budget and another layer of risk to SAF supply (IATA, 12 May 2024).

Performance assurance, also called credit support or security, is a central negotiated issue: who posts collateral, how much, in what form, and when a party can draw on it (Bracewell, 10 September 2026).

Those terms decide whether the revenue line holds, and they do not belong in a document that says agreed in principle.

What this means for you: I keep price mechanics and collateral out of the SAF price discussion at heads stage, and I carry them into the definitive offtake where the airline’s budget and my debt service both live.

Why a signed heads of terms still fails at credit

Lenders will be reluctant to take significant merchant exposure for a new sector, and any limited merchant offtake strategy will need to be supported by detailed marketing analysis and considered implications for debt-sizing (Dentons, 15 April 2025).

Investors often require at least 70 to 80 percent of annual capacity to be covered by offtake agreements, some lenders require 100 percent of the SAF produced to have reliable offtake covering the full loan tenor, and the offtake contract needs to cover the tenure of debt financing, for example 8 to 14 years (World Economic Forum, February 2025).

To be financeable, an offtake agreement must provide stable, predictable revenue over the life of the debt, involve a creditworthy offtaker, mitigate the project’s material operating and market risks, and avoid provisions that would prevent lenders from exercising remedies if the project defaults (Bracewell, 10 September 2026).

What this means for you: I run the file through the bankability question before any lender call, because a signed heads of terms that leaves an uncovered tail will not clear that test.

The cost of stopping halfway

Although most term sheet provisions are legally non-binding, it is very difficult and can be politically and economically expensive to attempt to renegotiate an executed term sheet (WilmerHale, 7 July 2020).

Ambiguity and differing intentions can result in a dispute, and insufficiently detailed letters of intent can result in subsequent disputes, because customary and typical standards leave many details to be negotiated later. A document that leaves the hard points for later has only postponed the argument.

Template contracts carry the same risk: a generic purchase template may save drafting time up front, but the mismatch shows up later in dispute spend, project delay or refinancing trouble.

Other recurring red flags are vague pricing language, unclear testing methods, one-sided termination rights and broad rejection rights, plus a draft negotiated only by procurement and sales teams without finance, tax and operations pressure-testing it.

What this means for you: I would rather spend that time at the heads stage than defend an executed list that never answered the questions a lender will ask.

How I would run this if it were my file

I run the pre-deal document as a two-column page. Column one, binding: confidentiality, exclusivity, expense reimbursement and any clause I expressly name as binding. Column two, not binding: price, volume, term, termination and everything that still depends on the definitive agreement.

Then I push contentious terms into the pre-deal phase to save time and expense later, and I identify deal-breakers before committing time and money to due diligence.

Then I ask the credit question: does this project have a contractually binding offtake covering the loan tenor, covering at least 70 to 80 percent of annual capacity, with a creditworthy offtaker?

I also write the conditions precedent, meaning the gates that must open before the contract is fully operative: financing closing, permits, board approval and completion testing.

My file goes to the lender with the binding column attached, not with the intention.

What this means for you: I sign nothing I cannot hand to a credit committee as an obligation, and I keep everything else marked as a plan.

Sources

Frequently asked questions

Generally no. Pre-deal documents are generally not intended to be legally binding, but whether a document is binding or non-binding depends on the language, and a court looks at multiple factors. The risk runs the other way: ambiguously drafted pre-deal documents may be interpreted to create binding obligations that nobody intended (WilmerHale). I therefore treat every sentence as potentially operative and mark the clauses I intend to be enforceable from signature.

The classic set is confidentiality, exclusivity and expense reimbursement. These obligations can be used to bind a counterparty during negotiation of the final agreement, and the published practice tip is to expressly specify any key terms that should be legally binding on either party, because that raises transaction certainty (WilmerHale).

Because it does not carry the obligation the model needs. Offtake contracts are often non-binding memoranda of understanding, while contractually binding agreements are needed for a project to reach final investment decision, and lenders rely on the offtake to validate the cash flow forecasts that form the basis for loan repayment (World Economic Forum; Global Trade Funding). An expression of intent cannot be drawn on when debt service falls due.

I sign the heads of terms with the binding clauses named, then work straight to the definitive offtake covering the loan tenor with a creditworthy offtaker, because that is the document the credit committee reads (WilmerHale; World Economic Forum; Bracewell). Signing the list first is useful only if the binding column is short, explicit and consistent with the contract I intend to negotiate next.

Not sure your project would survive a credit conversation?

A short call is usually enough to see where your project stands.

If you are at the heads stage and you want to know whether your draft will clear a credit review, I can introduce the conversation to investors and lenders who read these documents before they commit capital. Bring the binding column and the open points, and I will tell you what is missing before the first call.

I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia

I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.

More about me·Get in touch

Facebook
Twitter
LinkedIn

Related articles