Home » SAF Offtake Risk Allocation: Change in Law, Force Majeure, Credit Support
SAF Offtake Risk Allocation: Change in Law, Force Majeure, Credit Support
10 min read · Nov 2, 2026 · By Alex
Change in law risk features prominently in lender due diligence on a sustainable aviation fuel project, and compliance costs should pass to the offtaker under the offtake agreement. Most offtake agreements already contain a force majeure clause, yet many of those clauses read well without allocating real operational risk. Performance assurance, meaning who posts collateral, how much, in what form and when it can be drawn, is one of the most negotiated provisions. Investors often require 70 to 80 percent of annual capacity covered by offtake. In addition, some lenders require 100 percent across the loan tenor. SAF offtake risk allocation is what I work through below. In addition, I start from the published guidance on securing a SAF offtake.
A SAF project reaches final investment decision only when the offtake is credible enough to carry the debt. I treat the contract as a map of risk ownership, because every clause either names an owner or leaves one unnamed. In addition, the credit committee reads the gaps first.
In short
- Change in law: compliance costs under tightened SAF rules should pass to the offtaker under the offtake contract.
- Force majeure: present in most agreements, but it has to allocate operational risk rather than only read well.
- Credit support: who the obligor is, what guarantee or letter of credit stands behind it. In addition, when it can be drawn.
- Coverage: investors often ask for 70 to 80 percent of annual capacity, some lenders for 100 percent across the tenor.
- Price line: a fixed cost basis, or a commodity index the lenders already know.
In this article
The short answer: every risk needs a named owner
Three risks sit at the centre of every SAF offtake I review. In addition, each needs a named owner before the credit committee sees the file. Also, in practice they sit in different places: change in law in the regulatory line of the model, force majeure in the operating assumptions, and credit support in the counterparty assessment.
Change in law means the risk that a change in regulation or legislation raises the cost or alters an obligation of the contract after signing. Dentons reports that change in law will feature prominently in lender due diligence, and ideally the costs of compliance with tightened SAF regulatory requirements are passed to the offtaker under the offtake contract.
Force majeure is the clause that lets either party modify or cancel the agreement if something beyond anyone’s control puts undue hardship on either party, in the wording Global Trade Funding uses.
Credit support, which Bracewell calls performance assurance, is who posts collateral. How much, in what form and when a party can draw on it.
What this means for you: I name the owner of all three on the first page of my risk schedule. This is because an unnamed owner is a risk the lender will quietly assign to the project.
Why the offtake carries the loan
Every project finance lender scrutinises the offtake agreement because lenders rely on it for the financial assurances that validate the cash flow forecasts behind repayment. Global Trade Funding puts it directly: offtake agreements make many projects bankable. This is because a project that is not yet built has only a financial model.
The coverage requirement follows from that logic. Also, the World Economic Forum reports that investors often require at least 70 to 80 percent of annual capacity to be covered by offtake agreements. In addition, some lenders require 100 percent of the SAF produced to have reliable offtake covering the full debt tenor. That is the period from financial close to loan maturity. Contractually binding agreements are needed for a project to reach FID, with a tenure such as 8 to 14 years, and airline credit ratings are on average lower, so spreading default risk across several parties matters.
I set that coverage question against the current SAF demand picture.
What this means for you: I size the contracted percentage against the tenor the lender is actually underwriting, not the tenor I would prefer. In addition, I show the uncontracted tail that remains.
Change in law: who pays when the rule tightens
Dentons places change in law squarely in lender due diligence, and the intended answer is contractual. The costs of compliance with tightened SAF regulatory requirements should be passed to the offtaker under the offtake contract. That is the allocation I draft for first, because leaving it open invites a re-pricing the debt model cannot absorb.
The drafting around it matters as much as the principle. Mayo Law describes conditions precedent as the gates that must open before the contract is fully operative, with financing closing, permits and completion testing as common examples. The same source stresses that termination rights need symmetry, because one-sided termination for convenience makes projected revenue less reliable. On enforceability, a defined formula with a named benchmark. In addition, a stated calculation method generally holds, while a bare agreement to agree generally does not.
I test that package with a contract risk review before the lenders open the file.
What this means for you: I draft change in law together with termination rights and conditions precedent. This is because the credit committee reads the three as one question: who pays, and who can walk away.
Mandate risk and the price line
In the absence of any well-established pricing index for SAF. Dentons reports that project finance lenders will likely require offtake on a fixed-cost basis or by reference to a commodity index they already know. IATA names the price reporting agencies as Argus Media and S&P Global Commodity Insights, commonly called Platts, whose assessments form the base to which logistics costs, fees. In addition, a supplier margin are added.
On the demand side the line is volatile. IATA reports that in 2024 the difference between production cost and market prices. The market premium, reached as high as around 1000 USD per tonne of HEFA SAF in Europe, and that the market lacks transparency in terms of deals and prices paid. Under ReFuelEU Aviation airlines pay up to five times more than conventional jet fuel. In addition, the UK SAF mandate has triggered price spikes that airlines absorb.
Those demand signals are the subject of my note on SAF policy risk. In addition, they are why I never treat a mandate as a revenue floor.
What this means for you: I put the price line on a named index with a fixed-cost fallback. In addition, I say what happens when no benchmark is published on a given date.
Credit support: what backs the promise
Mayo Law sets out the practical credit review I would run on any offtaker. Who the actual obligor is, what support exists in the form of a guarantee, letter of credit, security package or reserve account, what happens on downgrade or distress. In addition, whether revenue can be captured. The blunt line from the same source is that a beautifully drafted contract with a weak buyer is often not bankable.
Bracewell places performance assurance among the heavily negotiated provisions, alongside events of default, termination payments and force majeure provisions, and treats who posts collateral. How much, in what form and when a party can draw on it as a central negotiated issue. Bracewell also gives a term range of approximately 5 to 25 years. Therefore, the support has to be sized against the whole debt rather than only the early operating years.
I test the buyer before I test the clause, using my framework for financing a SAF project.
What this means for you: I name the obligor, list the instrument that backs it, and state the trigger for drawing on it. This is because an unnamed trigger is a question the committee will send back.
Force majeure: what the clause does and does not do
The clause is standard. Global Trade Funding notes that most offtake agreements contain a force majeure clause allowing either party to modify or cancel the agreement if something beyond anyone’s control puts undue hardship on either party.
That breadth is where the problem starts. Mayo Law reports that force majeure clauses read well but do not allocate actual operational risks, and lists the recurring dispute areas: quality, quantity, timing, price adjustment and excuse clauses. The mitigations that source gives are independent verification, cure periods, escalation steps, separating payment disputes from performance disputes, and writing for partial failure.
Bracewell adds the dimension I check next, which is firmness. Whether the seller’s obligation is firm, subject only to force majeure or buyer default, or structured on a unit-contingent basis. A firm obligation carrying a vague excuse clause is a worse trade than it looks. This is because the excuse becomes the whole commercial position in a bad year.
What this means for you: I treat force majeure as a schedule of named triggers with cure steps and notice periods, not as a paragraph of general language that neither side has tested.
The order I would negotiate the clauses in
I start with quantity and firmness, then the price mechanism, then change in law, then force majeure. In addition, I leave credit support last at the table while sizing it first in the model. That is the sequence I build into my offtake agreement work.
Quantity comes first because long-term offtake, as IATA describes it, refers to supply further in the future, for example in 3 to 5 years, for a tenure such as 5 to 10 years. A take-or-pay obligation requires the buyer to pay for the product on a regular basis whether or not it takes delivery. In addition, that payment is what lets the seller cover fixed costs. IATA also advises that any contract should include strong transparency provisions regarding fluctuating costs.
Price comes second, since the choice between cost-of-production, cost-plus. In addition, an index decides who absorbs feedstock movement, and IATA notes that cost-plus is becoming more popular with suppliers because the risk profile favours the seller.
Change in law is third, force majeure fourth, both attaching to a settled volume and price. Also, credit support is negotiated last and sized first.
What this means for you: I hold this order because each clause rests on the one before it. In addition, a price agreed before volume is settled will be reopened anyway.
How I would run this if it were my file
If this were my file I would put a single page in front of the committee. One line per risk and one named owner.
Change in law: the cost of compliance with tightened SAF regulatory requirements, passed to the offtaker under the offtake contract. That is the Dentons position. Force majeure: rewritten as an allocation of operational risk, with named triggers, cure steps and notice periods, following the Mayo Law point that clauses which read well often allocate nothing. Credit support: named and sized, with the obligor, the instrument. In addition, the draw trigger stated, as Bracewell and Mayo Law both frame it. Coverage: set against the 70 to 80 percent of annual capacity investors often require, and 100 percent across the debt tenor where the lender requires it, per the World Economic Forum. Price: on a named index from a price reporting agency such as Argus or Platts, per IATA.
What this means for you: that single page is the SAF offtake risk allocation exercise in one view, and if any line has no owner the credit committee will find it before I do.
Sources
\n
- \n
- Dentons, 15 April 2025
- Bracewell, 10 September 2026
- Mayo Law, 15 November 2026
- Global Trade Funding, 13 March 2022
- World Economic Forum, February 2025
- IATA, 12 May 2024
- IATA, 9 December 2025
\n
\n
\n
\n
\n
\n
\n
Frequently asked questions
Who should carry change in law risk in a SAF offtake contract?
The offtaker is the intended carrier. Dentons reports that projects can expect the change in law risk to feature prominently in lender due diligence, and that ideally the costs of compliance with tightened SAF regulatory requirements are passed to the offtaker under the offtake contract. I therefore draft the transfer explicitly rather than leaving it to a general hardship clause, and I check that it sits with the termination rights and conditions precedent package rather than alone.
Is a force majeure clause enough to protect the project?
It is present in most offtake agreements and lets either party modify or cancel the agreement if something beyond anyone’s control puts undue hardship on either party. But Mayo Law notes that such clauses often read well without allocating actual operational risks, so the schedule of named triggers, cure steps, notice periods and escalation paths is what carries the protection in practice.
What credit support do lenders expect from an offtaker?
A credit review looks for who the actual obligor is and what support exists: a guarantee, a letter of credit, a security package or a reserve account, plus what happens on downgrade or distress. Bracewell treats performance assurance, meaning who posts collateral, how much, in what form and when a party can draw on it, as a central negotiated issue. A beautifully drafted contract with a weak buyer is often not bankable.
How much of the plant output must be contracted?
The World Economic Forum reports that investors often require at least 70 to 80 percent of annual capacity to be covered by offtake agreements, and that some lenders require 100 percent of the SAF produced to have reliable offtake covering the full loan tenor. Contractually binding agreements are also needed for the project to reach FID, with a tenure such as 8 to 14 years. The exact coverage figure follows from the lender, not from the project.
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If you are at pre-FID and want this risk map tested against a real credit paper, my investor introductions work is where I put the file in front of the counterparties who will actually read it.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.