SAF Production Pathways: Which One Is Bankable?

10 min read  ·  Nov 2, 2026  ·  By Alex

saf production pathways

I would answer your question in one line: you pick a production pathway the way you pick a financing structure. Specifically, you weigh proven commercial maturity and a feedstock you can contract. In addition, you weigh a jet yield you can model and an offtake agreement that covers the debt. An offtake agreement is a contract under which a buyer commits to purchase the fuel. That framing comes from the World Economic Forum with Kearney. The umbrella topic is sustainable aviation fuel. Also, the four families on the table are hydroprocessed esters and fatty acids, alcohol-to-jet, gasification with Fischer-Tropsch synthesis, and power-to-liquid. Gasification heats solid feedstock without combustion to make a raw gas called syngas. At pre-feasibility in Southeast Asia you need one answer, not a chemistry lecture. That is the SAF production pathways question, and I settle it before any process drawing exists.

Eleven approved processes and eleven under evaluation look impressive on a slide and mean nothing to a credit committee. I use four tests instead: maturity, feedstock, jet yield, and the offtake that carries the debt. Everything below runs those tests against the published record.

In short

  • Maturity: HEFA-SPK sits at technology readiness level 9, meaning proven and commercially deployed, and supplies most SAF today.
  • Feedstock: I can only model what I can contract, and supply chains decide plant scale.
  • Yield: the jet cut, not the total liquid yield, sets the revenue line.
  • Capital: the four families sit inside an industry capital requirement of 19 to 45 billion US dollars by 2030.
  • Offtake: lenders often want 70 to 80 percent of annual capacity covered for the debt tenure.
Facebook
Twitter
LinkedIn

In this article

The short answer: the pathway is a financing decision

ICAO defines a conversion process in Annex 16 Volume IV. Specifically, it is a technology that converts a feedstock into aviation fuel. As of July 2023, 11 conversion processes for SAF production had been approved and 11 others were under evaluation. Eight of the approved sit under ASTM D7566, the specification for aviation turbine fuels containing synthesised hydrocarbons. Meanwhile, the remaining three follow ASTM D1655 because they involve co-processing with conventional fossil jet (IRENA).

The four families are hydroprocessed esters and fatty acids, alcohol-to-jet, gasification with Fischer-Tropsch synthesis, and power-to-liquid (World Economic Forum with Kearney). I read that list as a financing menu rather than a chemistry menu. Each family carries a different capital profile, feedstock obligation and construction schedule. A lender prices that mix before it opens a process flow diagram.

What this means for you: you are not choosing a reactor. You are choosing the risk a debt provider will hold. Also, the pathway name is the first line of that memo.

What an approval actually certifies

ASTM International currently has 12 SAF production pathways approved, including three for co-processing (ICAO Aviation Benefits). HEFA-SPK, ATJ-SPK and FT-SPK are each approved up to a blend limit of 50 percent. That is the maximum SAF share mixed with conventional jet fuel. Also, SIP and the algae route stop at 10 percent, and co-processing routes at 5 or 10 percent (ICAO).

SAF must have the same chemical qualities and characteristics as conventional jet fuel. Therefore, engines, aircraft and fuel delivery systems do not need redesign (ICAO Aviation Benefits). Also, once it passes laboratory, ground and flight tests, refiners blend it with conventional jet fuel and re-test it. A blend limit exists because components of conventional jet fuel allow seals to swell in engines and prevent fuel leaks. Sulphur is one of them. Meanwhile, ICAO records work ongoing to raise co-processing from 5 percent to 30 percent. In addition, manufacturers target 100 percent SAF compatibility by around 2030.

What this means for you: the approval you cite is a blend ceiling. Therefore, size the plant against 50 percent, 10 percent or 5 percent, not neat SAF.

Feedstock decides before the technology does

The approved HEFA route takes vegetable oils, animal fats and used cooking oils (ICAO). The alcohol route takes ethanol, isobutanol and isobutene from biomass (ICAO). In addition, it takes residual starch, sugar, molasses, agricultural residue and grasses. It also takes biogenic municipal solid waste without plastics or synthetics, bagasse and wood (ICAO ACT-SAF). The Fischer-Tropsch route takes energy crops, lignocellulosic biomass and solid waste (ICAO Aviation Benefits). Availability of waste and residue oils and fats is expected to exceed 40 Mt/a by 2030 (ICAO ACT-SAF).

Gasification technologies can take municipal solid waste and forest and agricultural residues. However, supply chains for these feedstocks are not well-established. Also, the low energy density of forest residues limits the economical transportation distance from a refinery. That distance then limits refinery scale (IEA Bioenergy Task 39). Feedstock availability in Southeast Asia is the first page of any feasibility study.

What this means for you: sign the feedstock before you sign the technology. The reason is that a pathway you cannot feed is a pathway no lender will price.

What each family costs in capital and where the yield comes from

HEFA is the most mature and cost-effective pathway but faces feedstock constraints. Alcohol-to-jet carries higher capital costs from on-site ethanol processing. Gasification Fischer-Tropsch is capital-intensive and needs solid feedstock handling. Power-to-liquid has the highest capital requirement. The reason is that it relies on renewable electricity, electrolysis and CO2 capture (World Economic Forum with Kearney). The industry may require between 19 billion and 45 billion US dollars of capital expenditure by 2030.

On the yield side, only about 15 percent of hydrotreated fats and oils falls within the jet range. In addition, raising it costs more and loses overall liquid yield. Meanwhile, new facilities can divert up to 70 percent of total liquid product to SAF (IEA Bioenergy Task 39). In a conventional Fischer-Tropsch process, the Anderson-Schulz-Flory distribution limits the maximum straight-run jet fraction to about 40 percent. That distribution is the statistical model of chain growth, and extra process units add cost.

What this means for you: model the jet cut rather than the total liquid yield, and price the capital against sustainable aviation fuel price before you compare families.

The maturity test a lender runs first

HEFA-SPK is currently the most commercially viable SAF conversion pathway and the one behind the majority of SAF available today. It sits at technology readiness level 9, proven and commercially deployed. In addition, it qualified under ASTM D7566 Annex A2 in 2011 (ICAO ACT-SAF).

Fischer-Tropsch itself is fully commercial. Gas-to-liquids plants run at 2,500 and 7,500 bbl/day in South Africa and about 14,700 in Malaysia. In addition, Qatar runs about 33,500 and 140,000, Nigeria about 34,000 and Uzbekistan 38,000 (ICAO ACT-SAF). However, the preceding steps are not yet fully commercial. In addition, the integration of the gasification route that yields the syngas feed is still open (IEA Bioenergy Task 39).

Alcohol-to-jet and gasification Fischer-Tropsch are nearing commercial status. Meanwhile, power-to-liquid sits at a lower technology readiness level. The reverse water gas shift reaction still needs to be fully resolved (IEA Bioenergy Task 39). ICAO publishes CORSIA default life cycle emission values for FT, HEFA, SIP and ATJ (ICAO), and technology maturity and scale up is where I build that file.

What this means for you: bring the approval record to the first lender meeting. That is the page read first.

Demand, price and why the mix matters

SAF production in 2025 reached 1.9 million tonnes, only 0.6 percent of total jet fuel consumption. Also, 2026 is projected at 2.4 million tonnes and 0.8 percent (IATA). Demand for global SAF is expected to reach 17 million tonnes per annum by 2030, approximately 4 to 5 percent of total jet fuel consumption, while installed capacity reached 4.4 Mt by end 2024 with 6.9 Mt of expansion planned and an additional 5.8 Mt needing final investment decisions (FID), the moment the board commits capital, by 2026 (World Economic Forum with Kearney).

e-SAF faces a much higher cost base, potentially up to 12 times that of conventional jet fuel, which is why the pathway choice is also a cost-of-compliance choice (IATA). e-SAF project finance runs on a different logic from a bio-based file, and the mix you propose tells a lender which logic applies.

What this means for you: your offtaker is buying a compliance obligation. Therefore, the pathway sets the premium you must defend and the volume a mandate forces on you.

The order I would run the selection in

I would read the offtake obligation first, because it fixes the claim the fuel must carry. Then I would pick the feedstock I can actually contract. In addition, I would test maturity against the published approval record. Next, I would model the jet yield rather than the total liquid yield. Also, I would price the capital against the 19 to 45 billion US dollar range. Finally, I would walk the five critical phases: conceptualization, pre-feasibility, FID, construction and commissioning (World Economic Forum with Kearney). Only then would I write the contract. The reason is that investors often require offtake cover for at least 70 to 80 percent of annual capacity. Also, the agreement needs to cover the tenure of debt financing. For example, that means 8 to 14 years (World Economic Forum with Kearney). How to finance a SAF project follows this same order.

What this means for you: a pathway chosen out of that order becomes a redesign later. Also, redesigns stall FID. The order costs nothing in the lab and saves months at the bank.

How I would run this if it were my file

I would hold HEFA as the base case because it sits at technology readiness level 9 (ICAO ACT-SAF). In addition, I would make the feedstock contract a condition of the feasibility study. It should not wait as a later work package (IEA Bioenergy Task 39). Gasification Fischer-Tropsch goes in a separate risk bucket. In addition, high investment and lengthy construction should slow the ramp-up of commercial volumes (IEA Bioenergy Task 39). I would treat power-to-liquid as a different financing question. It carries the highest capital requirements of the four (World Economic Forum with Kearney).

For Southeast Asia I would check the built reference list first. Neste at Tuas, Singapore, 1,000,000 tonnes operating from Q3 2023. Petronas and Idemitsu at Pengerang, 650,000 tonnes in 2026. EcoCeres at Tanjung Langsat, 220,000 tonnes in 2025; WasteFuel at Manila, 91,000 tonnes of municipal solid waste in 2025 (IRENA). Indonesia released a national road map and action plan for SAF in September 2024. Meanwhile, Malaysia launched its Aviation Decarbonisation Blueprint the same month. That blueprint aims to cut sectoral emissions by up to 46.2 percent (IRENA).

What this means for you: base case, risk bucket and regional comparison on one page. Then the pathway choice stops being an argument.

Sources

Frequently asked questions

HEFA-SPK is currently the most commercially viable SAF conversion pathway and the one used for producing the majority of SAF available today, at technology readiness level 9, qualified under ASTM D7566 Annex A2 in 2011 and blended up to 50 percent (ICAO ACT-SAF). The Fischer-Tropsch process is fully commercial in gas-to-liquids, but the gasification front end and its integration have yet to be fully commercialized for SAF (IEA Bioenergy Task 39).

HEFA-SPK, ATJ-SPK and FT-SPK are approved up to 50 percent, SIP and the algae routes up to 10 percent, and co-processing routes up to 5 or 10 percent, with work ongoing to raise co-processing from 5 percent to 30 percent and to allow 100 percent SAF in aircraft (ICAO, ICAO Aviation Benefits).

The conversion process feeds the lifecycle value that the certifying scheme reports, and ICAO publishes CORSIA default life cycle emission values for FT, HEFA, SIP and ATJ, so the pathway you choose determines the default your auditor can use (ICAO).

The SAF refinery lifecycle has five critical phases, conceptualization, pre-feasibility, FID, construction and commissioning, and investors often require at least 70 to 80 percent of annual capacity to be covered by offtake agreements before they commit, with the offtake covering the tenure of debt financing, for example 8 to 14 years (World Economic Forum with Kearney).

Not sure your project would survive a credit conversation?

A short call is usually enough to see where your project stands.

If you want this shortlist run against your own feedstock, yield and offtake file, investor introductions is where I open the conversation with lenders and equity investors who already know these four families. I bring the maturity record, the jet yield model and the offtake structure, and I only carry files that hold on all three.

I do not provide investment advice or arrange investments. Also, I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia

I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.