SAF Projects in Southeast Asia: Pipeline and Developers Map

10 min read  ·  Nov 2, 2026  ·  By Alex

saf projects southeast asia

What I found first is a single line in a table marked Operating rather than Planned. One plant runs in Southeast Asia today: Neste at Tuas in Singapore, with 1,000,000 tonnes a year of sustainable aviation fuel. In addition, every other regional entry on the IRENA table is marked planned. So the status of a plant comes before any capacity figure in my reading. When I screen SAF projects Southeast Asia, I am asking three things: who is building what, at what scale. In addition, what is actually running today.

I work from open sources published between December 2024 and February 2026 and from the project record itself rather than from announcements. The regional map is dense on paper and thin in operation, and that gap is the whole investment question.

In short

  • Operating: Neste at Tuas in Singapore, 1,000,000 tonnes a year, feedstock UCO and animal fats, start Q3 2023 (IRENA).
  • Planned: Pertamina, NEXTCHEM, EcoCeres, PETRONAS and Idemitsu, Vandelay Venture, LOKEN Malaysia, FatHopes Energy with Lootah Biofuels, WasteFuel, Bangchak, PTT, SAF One and Nihon Toyo (IRENA).
  • Feedstock: HEFA, the pathway carrying 80 to 90 percent of current global SAF output, mostly on waste oils (White & Case).
  • Offtake: The contracts under which a buyer takes the fuel, which lenders commonly want covering 70 to 80 percent of annual capacity (World Economic Forum with Kearney).
  • Screen: Status first, then countable feedstock, then binding offtake, then certification, then capital.
Facebook
Twitter
LinkedIn

In this article

The short answer: one plant runs, the rest is a plan

The IRENA table of planned and operating SAF production plants in Southeast Asia lists Neste at Tuas in Singapore on UCO, used cooking oil, and animal fats, start Q3 2023, 1,000,000 tonnes, status Operating (IRENA). Every other entry on that table is marked Planned, from Pertamina in Java to SAF One in Viet Nam. Nothing else on that regional list has started up on the same table. In addition, I carry that qualifier into every downstream number I read. The status of a plant, by which I mean that operating or planned label, therefore precedes any capacity figure. This is because a planned number tells me what someone intends to build, not what a buyer can lift. I read the map as a status column, not as a capacity column. In addition, I never add the planned rows together to make a regional total.

What this means for you: one operating line. In addition, a queue of planned lines is the entire Southeast Asia picture on the IRENA table. In addition, I would price the queue at zero until its status changes.

The map, country by country

Indonesia carries Pertamina at Cilacap in Java on UCO and palm kernel oil for 2026, plus NEXTCHEM at Sei Mangkei on UCO. In addition, POME, palm oil mill effluent, 60,000 tonnes planned (IRENA). Malaysia is the densest row (IRENA): EcoCeres at Tanjung Langsat in Johor Bahru, 220,000 tonnes planned for 2025; PETRONAS. In addition, Idemitsu at Pengerang in Johor, 650,000 tonnes planned for 2026. Vandelay Venture at Kota Kinabalu in Sabah, 250,000 tonnes planned for 2025. LOKEN Malaysia on UCO and biomass oils, planned for 2025 with no figure published. In addition, FatHopes Energy with Lootah Biofuels on waste oil, 200,000 tonnes planned. The Philippines has WasteFuel at Manila on municipal solid waste, the waste a city collects, 91,000 tonnes planned for 2025.

Thailand has Bangchak at Phra Khanong on UCO, 292,000 tonnes planned for Q1 2025, plus PTT. In addition, Viet Nam has SAF One and Nihon Toyo (IRENA). I keep the country map open while I read these rows.

What this means for you: most planned capacity sits in Malaysia and Indonesia. Therefore, a delay in either country moves any regional total you might try to build.

What those plants will run on

HEFA, hydroprocessed esters and fatty acids, is the most technologically mature pathway and processes agricultural products, waste oils or fats. It carries 80 to 90 percent of current global SAF output (White & Case). Indonesia accounts for 58 percent and Malaysia 25 percent of global palm oil production, which is the feedstock advantage and the compliance problem at the same time. This is because key markets such as the European Union exclude palm oil based SAF from counting towards regulatory SAF mandates and targets (White & Case). The treatment of POME, PFAD and other palm residues is less clear under those rules (White & Case).

IRENA’s study focuses on HEFA-SPK, FT-SPK and ATJ-SPK, and the one Fischer-Tropsch plant announced in the region is WasteFuel in the Philippines (IRENA). I cross-check every row against the feedstock availability review before I credit a feedstock claim.

What this means for you: a HEFA plant on palm inputs here inherits a buyer list that excludes the European Union. Therefore, the offtake search has to start outside it.

Who is actually building, and with what support

Neste’s Singapore Expansion construction started at the beginning of 2019 and operations started in April 2023 on an investment of EUR 1.6 billion. This takes the refinery, operating, to 2.6 million tons of annual production capacity including up to 1 million tons of SAF (Neste). EcoCeres has a 350,000 tonne SAF plant in Johor, operating since it was commissioned in October 2025 (White & Case). In addition, PETRONAS is developing a 650,000 tonne plant in Johor, planned to start operations by 2030 inside the Pengerang Integrated Complex (White & Case). Malaysia supported that PETRONAS project through an offtake agreement signed in 2023. Under it, Malaysian Aviation Group is to take delivery of over 230,000 tonnes of SAF beginning in 2027 (White & Case).

Indonesia’s Cilacap refinery was the first in Southeast Asia to produce ISCC-certified SAF. In addition, PETRONAS has also produced ISCC-certified SAF delivered to Kuala Lumpur International Airport through an existing multi-product pipeline (White & Case).

What this means for you: the assets I can actually verify are the ones with a certification trail and a named buyer. In addition, that pairing, not the tonnage, is what I underwrite.

What the market pays for the fuel

SAF prices exceed fossil-based jet fuel by a factor of two, and by up to a factor of five in mandated markets. That is the margin a planned plant is bidding against (IATA). SAF output reached 1.9 Mt globally in 2025, only 0.6 percent of total jet fuel consumption, and 2026 is projected at 2.4 Mt and 0.8 percent (IATA). IATA also reports that airlines paid a premium of USD 2.9 billion for the 1.9 Mt of SAF available in 2025, of which USD 1.4 billion reflects the standard SAF price premium over conventional fuel (IATA). The global SAF industry was valued at USD 1.8 billion in 2024 and USD 2.3 billion in 2025 (White & Case). I keep the SAF price explainer next to the plant list when I test that spread.

What this means for you: a planned plant is bidding into a spread that already costs the industry billions a year, so I test the price assumption before I test the construction schedule.

What separates a listed project from a funded one

Demand certainty is what turns a listed plant into a financed one. In addition, the argument is on the record. Policy support through mandates or incentives creates the demand certainty that drives investment, while the expansion of the Neste Singapore refinery, now operating, to produce 1 Mt of SAF is quoted at about EUR 1.65 billion (presentation by Neste at the ICAO Regional Seminar on Environment, 7 to 8 August 2024). The same presentation reports about 43 SAF production facilities planned in Asia Pacific against only five operational in the region in 2024 (Argus SAF Capacity Map 2024), and about USD 3,200 billion of investment needed by 2050 to meet global SAF demand (ICAO seminar).

Investors often require at least 70 to 80 percent of annual capacity covered by offtake. In addition, some lenders require 100 percent of the SAF produced covered for the loan tenor of 8 to 14 years (World Economic Forum with Kearney). Those thresholds set a floor on capacity utilisation, by which I mean the share of a plant’s annual capacity that is actually sold. Offtake contracts are often non-binding memoranda of understanding. In addition, a final investment decision, the point where a board commits capital, needs binding agreements (World Economic Forum with Kearney). For the sequence I use the project finance walkthrough.

What this means for you: I separate the announced column from the financed column with one question. Who is contractually obliged to buy, and for how long.

The order I would screen these projects in

I read the status column first, then the feedstock the plant’s market can actually count, then the offtake behind it, then the certification that makes the volume sellable, then the capital stack. On policy I check what has become binding. Singapore has a SAF levy for all passenger and cargo flights departing the country from 1 October 2026, supporting a 1 percent SAF target by the end of 2026. Indonesia has proposed a 1 percent blend by 2027; South Korea has a 1 percent blending mandate from 2027 (Airbus). Japan has set the ambition of 10 percent SAF usage by 2030. In addition, Australia has committed AUD 1.1 billion in production incentives for low-carbon liquid fuels (Airbus).

On capital I keep the sector scale in view. The industry may require between 19 billion and 45 billion US dollars of capital expenditure by 2030 (World Economic Forum with Kearney). For the diligence sequence I use the FID walkthrough.

What this means for you: I score a project on binding policy in its own jurisdiction before I score its technology. This is because a mandate is the only thing in this market that reliably creates a buyer.

How I would run this if it were my money

I would refuse to value planned capacity at operating capacity. This is because the regional table is one operating entry against a long list of planned ones (IRENA). I would check the neighbourhood of the plant, since the European Union excludes palm oil based SAF from its mandates. That narrows the buyer list for a HEFA plant on palm inputs (White & Case). I would check whether the offtake exists, since binding agreements are what a project needs to reach final investment decision. In addition, investors commonly ask for 70 to 80 percent of capacity covered (World Economic Forum with Kearney). I would check the certification route early, because the Cilacap.

In addition, Kuala Lumpur deliveries show that certification is a market access condition, not a badge (White & Case). Only after those four checks would I open the capital stack and the schedule.

What this means for you: operating status, countable feedstock, binding offtake and certification are my four checks. In addition, a project that fails any one of them stays on the planned list in my model.

Sources

Frequently asked questions

The IRENA table marks one entry as Operating, Neste at Tuas in Singapore with 1,000,000 tonnes of annual production, and separately the presentation by Neste at the ICAO Regional Seminar on Environment reports five operational facilities in the whole of Asia Pacific in 2024 against about 43 planned (IRENA, ICAO seminar). I read those two counts as different geographies: one is Southeast Asia on the IRENA list, the other is the wider Asia Pacific region in 2024.

On the IRENA table the largest single planned figure in Southeast Asia is PETRONAS and Idemitsu at Pengerang in Johor, Malaysia, at 650,000 tonnes for 2026, followed by Neste’s operating 1,000,000 tonnes in Singapore, and White & Case separately describes PETRONAS’ 650,000 tonne Johor plant for 2030 (IRENA, White & Case).

Not as a rule: the status column reads planned for almost every entry, and the published record shows support arriving through specific instruments instead, such as Malaysia’s 2023 offtake agreement under which Malaysian Aviation Group is to take delivery of over 230,000 tonnes of SAF beginning in 2027 (White & Case).

Predominantly waste oils and residues on the HEFA pathway, which represents 80 to 90 percent of current global SAF output: UCO and palm kernel oil in Indonesia, UCO and POME in Malaysia, municipal solid waste for the announced FT plant in the Philippines, and animal fats alongside UCO in Singapore (White & Case, IRENA).

Not sure your project would survive a credit conversation?

A short call is usually enough to see where your project stands.

If you want to test a specific row on this map against a buyer, a feedstock position or a financing route, I run that screen as a project finance engagement. In addition, I also make investor introductions where the project and the mandate genuinely fit. One page of verified status, feedstock and offtake is worth more to me than a stack of planned tonnes.

I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia

I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.

More about me·Get in touch

Facebook
Twitter
LinkedIn

Related articles