Home » Singapore SAF Levy: What It Means for SAF Projects in Southeast Asia
Singapore SAF Levy: What It Means for SAF Projects in Southeast Asia
10 min read · Nov 2, 2026 · By Alex
The Southeast Asia SAF question I am asked most often is whether the charge on departing Singapore flights buys anything from your project. It does not. The charge is a levy, meaning a fixed charge imposed by law, collected centrally into a statutory fund, a pot created by law. That fund procures sustainable aviation fuel, meaning jet fuel made from waste and residues, and environmental attributes on aggregated demand. An environmental attribute is the certificate proving the fuel is sustainable, and aggregation means buying for the whole market at once rather than for one airline. Singapore fixes the SAF levy by geographical band and cabin class. A band is the destination group a route sits in, and the start date has already moved once. A lender must therefore underwrite a procurement policy rather than an offtake contract.
I read the mechanism as a demand instrument rather than as a contract. One design choice drives everything that follows. The state centralises the money, so the volume any single plant can claim depends on how the fund buys rather than on what an airline owes.
In short
- What it is: A statutory charge on departing Singapore flights, collected into a fund that buys SAF centrally.
- Who pays: The aircraft operator remits, and may pass the amount to the passenger on the ticket.
- What it costs: Economy passengers pay S$1.00 to S$10.40 by band, four times that in premium.
- What it buys: Fuel against a 1% target for 2026, with a goal of 3 to 5% by 2030.
- What a lender sees: A procurement duty on a published rate, not a contracted revenue line for a plant.
In this article
What the levy actually is
The charge rests on the Civil Aviation Authority of Singapore Act 2009 and the Civil Aviation Authority of Singapore (Sustainable Aviation Fuel Levy) Order 2026. That legislation took effect on 1 October 2026. The levy applies to qualifying passenger and general and business aviation flights departing Singapore from 1 January 2027, for tickets or services sold from 1 October 2026. In addition, the cargo levy applies to services sold from 1 October 2027 for flights departing Singapore from 1 January 2028.
It is a mandatory charge on qualifying flights departing Changi Airport or Seletar Airport to an immediate destination outside Singapore. Domestic flights within Singapore are out of scope. The aircraft operator is legally responsible for paying it. It also may pass it on to the passenger, with the amount specified on the ticket.
The state collects the levy centrally and funds the purchase of SAF and related environmental attributes through a statutory SAF Fund. SAFCo manages collection and procurement.
What this means for you. No airline owes your project a purchase, it owes the state a published rate, and the state then buys fuel wherever its process decides to buy it.
What it costs and who remits it
CAAS set the quantum from the volume of SAF needed to meet the 1% SAF target for 2026, plus the projected price premium over conventional jet fuel and the certification, blending and delivery costs, the same costing logic behind SAF mandates elsewhere.
The scheme groups destinations into four geographical bands, from Southeast Asia in band I to the Americas in band IV. Economy passengers pay S$1.00 in band I up to S$10.40 in band IV. In addition, the premium cabin is four times that, so S$4.00 to S$41.60.
Earlier estimates of around S$3.00, S$6.00 and S$16.00 for an economy passenger direct to Bangkok, Tokyo and London landed at S$1.00, S$2.80 and S$6.40. Prevailing SAF costs were lower.
General and business aviation pays S$40 to S$6,500 per qualifying flight by wingspan category and band, cargo pays S$0.01 to S$0.15 per kilogram. In addition, a temporary 30% reduction applies to qualifying passenger flights departing between 1 January and 31 March 2027. The ground handling agent collects from the operator and assists the post-flight declaration. Also, records stay on file for five years. Late payment adds daily interest 4.5 percentage points above the three-month compounded benchmark rate in Singapore. A reporting failure without reasonable excuse may attract a fine of up to S$2,000.
What this means for you. CAAS sets that number as a policy parameter from a projection. The state can re-price it without any producer seeing a new contract.
What the money buys
Singapore set a 1% SAF uplift target for 2026, with the goal of raising it to 3 to 5% by 2030, subject to global developments and the wider availability of sustainable aviation fuel. The levy is the funding route for that target.
Procurement runs centrally, using the levies to aggregate demand and reap economies of scale. Businesses and organisations will be invited to purchase fuel through the same mechanism.
The regulator argues it is critical to provide fuel producers with a demand signal to give them the confidence to make further investments in SAF production. It also explains that the market for the supply of SAF is still nascent. In addition, the price of SAF can be volatile, so a fixed levy gives cost certainty to airlines and travellers.
The blueprint behind the policy acknowledges a simple gap. Most SAF from the Neste refinery in the Tuas industrial zone, with capacity to produce up to 1 million tonnes of SAF per year, goes to higher-demand markets. In fact, regional demand is lower.
What this means for you. The fund buys on aggregated demand, so your plant competes for a state procurement decision rather than for an airline’s route-level obligation.
Why the design matters across Southeast Asia
Several Southeast Asian nations including Indonesia, Malaysia and Thailand have introduced SAF blending roadmaps beginning around 2027. Singapore stands out with a confirmed near-term goal of 1% SAF by 2026, potentially rising to 3 to 5% by 2030.
Since 2024, multiple APAC governments have moved from tentative goals to concrete blending targets and mandates. In 2025 the region moved from aspiration to action on SAF policy. Europe’s SAF blending mandate under ReFuelEU Aviation kicked in on 1 January 2025 starting at 2%.
SAF produced in Asia has tended to flow to Europe, where mandates create a price premium. That raises concerns about local shortages or higher costs if the region lags behind in policy. IATA reports that most SAF supply in 2025 goes to Europe. It warns that Europe’s approach has driven SAF prices to five times that of conventional jet fuel.
What this means for you. The regional order of mandates matters because it sets which jurisdiction pays first. In addition, a levy that starts early claims demand before its neighbours do.
What the March 2026 deferral changed
On 25 March 2026 the government deferred the implementation of the SAF levy. The reason was the impact of the ongoing conflict in the Middle East on airlines and passengers.
The levy now applies to tickets and services sold from 1 October 2026 for flights departing from 1 January 2027. It no longer follows the earlier announcement of tickets sold from 1 April 2026 for flights departing from 1 October 2026. CAAS states the levy will apply for all origin-destination passengers, origin-destination cargo shipments, and general and business aviation flights departing Singapore.
The published target and the published rate did not move; the calendar moved. The fuel procured still has to meet internationally recognised sustainability and lifecycle criteria such as those set by ICAO under CORSIA.
The cargo leg moved separately, to services sold from 1 October 2027 for flights departing from 1 January 2028.
What this means for you. It also run the model on two dates, because a deferral moves the sales date. In addition, the departure date without changing the rate you were handed.
What a lender wants to see
IATA states that governments should introduce SAF mandates only where market conditions, production capacity, infrastructure readiness and supportive policy are in place. The aim is to avoid unintended economic impacts. Supply constraints or disproportionate cost burdens on the aviation sector and consumers. It calls for stronger policy support: effective sequencing of production incentives and investment frameworks that provide certainty and reduce risk before any government imposes a mandate.
That is the test I apply to policy risk in any jurisdiction.
Global SAF production should reach around 2.4 million tonnes in 2026, representing just 0.8% of aviation fuel use, at a cost to airlines of $4.3 billion.
SAF currently represents less than 1% of global aviation fuel use. It also costs several times more than conventional aviation fuel. The reasons are more expensive feedstocks, still developing production technologies, thin physical and market infrastructure, and high upfront investment.
What this means for you. I therefore read a levy as a demand signal with a procurement duty attached, not as a contracted revenue line.
Where the levy stops short for a project
Aircraft operators are not required to purchase or use sustainable aviation fuel for each chargeable flight. The state collects the levy centrally and funds the purchase of SAF and related environmental attributes through the statutory SAF Fund.
That design decouples an airline’s compliance from a specific plant’s output: the airline remits a published rate, and the volume actually bought depends on how the procurement chain runs.
The published instruments name no producer and fix no volume for any single plant. The design is deliberate, it gives airlines cost certainty while leaving the state free to choose supplier, volume and timing.
CAAS sets the rate itself from a projected premium. Therefore, a project that waits for the levy to reveal a price is waiting for a policy parameter rather than for a counterparty’s signature.
What this means for you. I treat the levy as one line in the demand column and I keep it out of the contracted revenue column until a procurement contract names my facility.
How I would model it if it were my file
I write four lines: the statutory rate by band, the collection calendar, the volume the fund has committed to buy, and the date of the next published review.
I take the rate from the published table rather than from a press estimate. The same route was re-priced once.
I mark the deferral as a dated event with two dates, the sales date and the departure date, and I run the model at both.
I test the result against a demand that is policy-made. Global SAF production is heading for around 2.4 million tonnes in 2026. SAF still accounts for less than 1% of global aviation fuel use.
My last line is the one a procurement contract would have to name, because that is the only line a lender will count.
What this means for you. The file is only as strong as its fourth line. In addition, that line has to come from a signed procurement contract rather than from the levy schedule.
Sources
- IATA, June 2026.
- IATA, 6 June 2026.
- Sustainable Aviation Futures, 2025.
- CAAS, 10 November 2025.
- CAAS, 25 March 2026.
- FCC Aviation, 2 November 2026.
- GreenAir News, 22 February 2024.
Frequently asked questions
What is the Singapore SAF levy?
It is a mandatory charge established under the Civil Aviation Authority of Singapore Act 2009 and the Civil Aviation Authority of Singapore (Sustainable Aviation Fuel Levy) Order 2026, collected centrally and used to fund the purchase of SAF and related environmental attributes through a statutory SAF Fund. The legislation took effect on 1 October 2026, and the levy reaches qualifying flights departing Changi Airport or Seletar Airport to an immediate destination outside Singapore.
Who pays the levy, the airline or the passenger?
The aircraft operator is legally responsible, and the operator may pass the charge on to the passenger, in which case the amount must be specified on the ticket. The ground handling agent collects from the operator and assists the post-flight declaration, and for business and general aviation the licensed ground handling agent handles declaration and payment through IATA, SAFCo’s appointed levy collection service provider.
How much does the levy cost per passenger?
Passenger rates run from S$1.00 to S$10.40 in the economy cabin by geographical band, with the premium cabin at four times that rate up to S$41.60, and a temporary 30% reduction applies to qualifying flights departing between 1 January and 31 March 2027. General and business aviation flights pay S$40 to S$6,500 per qualifying flight by wingspan category and band, and cargo pays S$0.01 to S$0.15 per kilogram.
Does the levy make a Southeast Asian SAF project bankable?
Only as far as the fund buys. The levy is a published rate collected into a fund, so it signals demand and gives cost certainty to airlines and travellers, while a lender still needs a procurement contract that names the project. A project gains a revenue line only when that contract exists.
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
Where a project needs a contracted line instead of a demand signal. The instrument is an offtake agreement, and offtake agreements are what a lender reads first. Before the numbers go into a model, I frame that document.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.