Home » SAF Policy Change Risk: Can a Rule Change After FID?
SAF Policy Change Risk: Can a Rule Change After FID?
10 min read · Nov 2, 2026 · By Alex
Yes, a rule for sustainable aviation fuel (SAF) can change after a project reaches final investment decision, the point where a board commits capital. I see three moments when it happens: before a rule exists when a proposal has not yet become law, while a rule in force is reopened by a review. A scheduled reopening of the text, or a call for evidence. Also, a published invitation to comment, and inside the eligibility criteria, the list of what counts. In all three, the protection a lender holds is the date. In addition, the wording of what it signed rather than any promise of stability.
That is the SAF policy change risk I am asked to settle before anyone signs. In addition, I settle it by reading published instruments rather than intentions. The wider frame sits in SAF policy risk.
I read two published records more carefully than any forecast. An EU regulation with a scheduled review, and a UK mandate whose detailed rules were written before the market had to live with them. Both are dated instruments with movable parts, and neither is a fixed backdrop for a model.
In short
- Three moments: a proposal before law, a reopening while in force, a criteria change underneath.
- Not yet law: Indonesia and Malaysia publish targets that have not fully crystallized into regulation.
- Scheduled review: the EU quota path and its fine formula are both tested in 2027.
- Moving criteria: the UK HEFA cap starts in 2027 and EU eligibility lists narrow on their own dates.
- My protection: the date and the wording of what the lender signed.
In this article
What a policy change means here
A policy change in this market takes three shapes. In addition, I keep them apart because each one hits a different part of a finance plan: before a rule exists. A published proposal is not yet an obligation; while a rule is in force, a government can reopen it through a review or a call for evidence; under a rule, the eligibility criteria. In addition, the caps that decide what counts can move without the headline target moving at all.
IATA argues for sequencing of production incentives and investment frameworks that provide certainty and reduce risk before any mandates are imposed (IATA, 6 June 2026). IATA also states that any SAF mandates should apply only where the necessary market conditions, production capacity, infrastructure readiness. In addition, supportive policy measures are sufficiently in place (IATA, June 2026).
Sequencing is not a preference here, it is the difference between a plant that can raise finance. In addition, a plant asked to hedge a rule that does not exist yet.
What this means for you: name the shape before you price it. A proposal needs timing risk, a reopening needs a review date. In addition, a criteria change needs a retest of what the model still counts. I do not hold them as one risk, because the cure for each is different.
The first moment: before the rule exists
The mandate landscape in Asia is mostly proposals at this stage. Indonesia’s SAF Industry Development Roadmap proposes a 1% blending requirement for international flights from two major airports, 1% by 2027, 2.5% by 2030 and 50% by 2060, and Malaysia’s Aviation Decarbonisation Blueprint envisions 1% from 2027 for outbound international flights from Kuala Lumpur International Airport rising to 47% by 2050. Neither of these proposals has fully crystallized into law, limiting investor certainty (White & Case).
Singapore has imposed a 1% blending requirement on all outbound flights by 2027. South Korea has proposed a similar mandate. India is considering a similar but non-binding target, and in Japan no mandate exists yet although signalling suggests a possible 10% SAF blend by 2030 (White & Case).
The regional reading is that several Southeast Asian nations have introduced SAF blending roadmaps beginning around 2027, and that 2025 is the year the region moved from aspiration to action on SAF policy (Sustainable Aviation Futures).
What this means for you: I price a proposal as timing risk rather than credit risk. That is because it can still be revised, dropped or delayed before a lender ever sees a default. In addition, I do not carry it into the model until it becomes law.
The second moment: a rule in force being reopened
The ReFuelEU Aviation core quota rises from 2% in 2025 to 70% in 2050. In addition, the synthetic sub-quota rises from an average 1.2% across 2030 and 2031 to 35% in 2050 (Orrick, 28 October 2026). The regulation has no buyout, a payment that replaces compliance: a shortfall triggers a fine. In addition, the missing volume must still arrive in the following year in addition to that year’s applicable quota.
The minimum fine is at least twice the relevant price gap multiplied by the noncompliant volume; on EASA’s 2024 reference prices of 2,085 euros per tonne for SAF and 734 euros per tonne for conventional fuel, a 10,000-tonne shortfall would trigger a minimum fine of approximately 27 million euros (Orrick, 28 October 2026).
Also, the 2027 review will test whether the EU can hold firm on a framework adopted before the current cost and geopolitical realities, or whether it introduces a safety valve of its own (Orrick, 28 October 2026).
The UK instrument sits alongside it: the SAF Mandate came into force on 1 January 2025 with a main obligation from 2025, a power-to-liquid obligation from 2028. In addition, a HEFA cap from 2027 (GOV.UK, 16 June 2026).
What this means for you: I date the reopening as carefully as the target. That is because a lender who knows when the rule can be reopened can price it, and one who does not will meet it first inside the penalty.
The third moment: criteria and caps moving under the project
The caps under a mandate move on their own timetable, and I track them apart from the headline percentage. Also, the UK HEFA cap takes effect in 2027. In addition, decreases HEFA’s allowed contribution as a proportion of total SAF supply annually; from 2027 to 2040 that share falls even as the absolute amount of HEFA that can count towards compliance is likely to increase as the mandate rises (GOV.UK, 16 June 2026).
In the EU, industrial CO2 from power stations phases out of eligibility in 2036 and phases out fully in 2041, so a project depending on an industrial point source needs a transition plan rather than a present-day eligibility opinion (Orrick, 28 October 2026).
Pooling ends too: through the end of 2034 a supplier can satisfy the quotas as a weighted average across the EU airports it serves, but from 2035 each airport must meet them alone. Germany’s implementing legislation sets an obligation payment of 17,000 euros per tonne for synthetic aviation fuel shortfalls with no cap linked to company size. Revenue or ability to pay. In addition, failure to make good a shortfall is an administrative offence carrying fines of up to 50,000 euros (Orrick, 28 October 2026).
What this means for you: I re-read the criteria list rather than the target at every milestone. A percentage that holds while the allowed feedstock narrows is still a change, and I log it with its own date and its own cure.
What has to stay true for the fuel to count
To qualify under international sustainability frameworks, SAF must meet stringent sustainability. In addition, lifecycle emissions-reduction criteria such as those set by ICAO under CORSIA, and international frameworks. In addition, certification schemes require traceability and independent verification throughout the supply chain (IATA, June 2026).
That list is written by someone else, and it can be rewritten while my contract still quotes the old percentage.
In the EU, certification runs under schemes recognised for RED purposes with chain-of-custody evidence reconcilable to the Union Database. In addition, misleading information on SAF origin carries the same fine as missing the quota (Orrick, 28 October 2026).
IATA asks governments to support the development and recognition of global SAF book-and-claim systems consistent with the purchase-based claiming approach allowed under CORSIA. In addition, to enable a global market supported by harmonized standards that create enduring rules (IATA, 6 June 2026).
What this means for you. A change in criteria is the quiet version of a policy change, because the headline percentage survives while the fuel under contract stops counting, so I verify the certificate chain before I compare the price.
What the delay actually costs
Delay has a measurable cost, and it lands on the capital plan. Continual calls for evidence and consultations are only feeding uncertainty regarding the mandate and policy landscape, serving to further delay investment and plants reaching final investment decision (Climate Catalyst, July 2026).
The UK Department for Transport states that it will not propose changes unless there is a strong rationale and that such changes maintain policy stability and investor confidence in the UK SAF industry. In addition, it is not proposing any changes to the overall SAF Mandate targets (GOV.UK, 16 June 2026).
Industry feedback in the same call for evidence warns that, once the HEFA cap. In addition, the power-to-liquid obligation come into force, availability of advanced non-HEFA. In addition, power-to-liquid SAF risks being lower than previously anticipated, and that insufficient global supply would leave fuel suppliers with the buyout as their only compliance option. That does not deliver the carbon savings the mandate is designed to deliver (GOV.UK, 16 June 2026).
None of the larger eSAF facilities in the EU have reached final investment decision. In addition, several projects must commit by the end of 2026 if the 2030 synthetic sub-quota is to be met without imports or penalties (Orrick, 28 October 2026).
What this means for you: I put the delay itself on the cost line. That is because every month of unanswered consultation moves the date on which a plant can commit, and that date is what my model depends on.
Where I draw the line
The first thing I do with a rule is take its date. Three fields go into my schedule: the obligation itself, the eligibility list that decides what counts. In addition, the next moment the instrument can be reopened. They sit on separate lines because a lender who reads only the first will believe a target is stable when the second has already moved underneath it.
A target that survives a review while the eligibility list changes is a change, and I log it as one. I treat a consultation as a scheduled event with a closing date, not as a rumour. That is because the UK call for evidence was published on 16 June 2026 and closed while the mandate was already binding. I never average a pre-review number with a post-review number, and I never carry a proposal into the model before it becomes law.
What this means for you: ask for the reopening date before you ask for the target. A rule I can date is a risk I can price. In addition, a rule I cannot date is one I carry without knowing it.
How I would write it into the credit file
I attach a policy schedule to the model with a line for each jurisdiction I depend on, the date the rule was adopted. The date of the next scheduled review, the body that can change it. In addition, the cure period if the criteria move. Two examples show why that schedule earns its space: on the EU side I enter the 2027 review as a dated event. In addition, the fine formula as a cost line. Therefore, a shortfall is priced rather than discovered; on the UK side I enter the HEFA cap start of 2027. In addition, the buyout as the ceiling on compliance cost.
I ask for a clause that reopens pricing if eligibility changes, and I ask for the eligibility list to be attached to the contract rather than referenced by date. My last line is the counterparty that signed. That is because a rule that changes and a buyer that stays are two different risks. In addition, only one of them is in my contract.
What this means for you: hand the lender a schedule with dates on it rather than a narrative about stability. The document that holds after the rule moves is the one that already says what happens when it moves.
Sources
- IATA, June 2026.
- Also, IATA, 6 June 2026.
- White & Case, consulted 15 November 2026.
- Sustainable Aviation Futures, 2025.
- Orrick, 28 October 2026.
- GOV.UK Department for Transport, 16 June 2026.
- Climate Catalyst, July 2026.
Frequently asked questions
Can a SAF mandate change after a project reaches final investment decision?
Yes, and it happens in three ways: before a proposal becomes law, through a review or a call for evidence while the rule is in force, and through changes to eligibility criteria and caps. I track each one separately, because the published record shows a roadmap that is not yet law, a regulation carrying a scheduled review, and a cap with its own start date (IATA; White & Case; GOV.UK).
What is the EU review in 2027?
It is the moment when the framework adopted before the current cost and geopolitical realities is tested, to see whether the EU holds firm on it or whether it introduces a safety valve of its own (Orrick, 28 October 2026). For a lender it is the date on which both the quota path and the fine formula can be revisited, so I carry it as a dated event rather than as background.
Why does a call for evidence matter to a lender?
Because it is a published, dated step that can alter obligations already binding. The UK call for evidence was published on 16 June 2026 while the SAF Mandate was already in force, and continual calls for evidence and consultations are only feeding uncertainty regarding the mandate and policy landscape, serving to further delay investment and plants reaching final investment decision (GOV.UK, 16 June 2026; Climate Catalyst, July 2026).
How do I protect a project against a policy change?
By dating every rule, attaching the eligibility list to the contract rather than a date, pricing a reopen if eligibility changes, and keeping the counterparty’s signature separate from the rule’s text (Orrick; GOV.UK). I also run the file twice, once on the current criteria and once on the transition dates, so the lender sees the difference before signing rather than after the rule moves.
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If you want the policy schedule, the reopen clause and the double run written into a file you can hand to a lender. I build exactly that through contracting and risk management. Send me the jurisdictions you depend on and the dates you are carrying. In addition, I will show you which of them can move.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial. In addition, financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.