From 1 January 2027, flights leaving South Korea must use jet fuel blended with 1% sustainable aviation fuel. The blend will rise to 3% to 5% by 2030 and to 7% to 10% by 2035. From 2027, refiners, petroleum exporters and importers carry the duty to put the blend into the fuel supplied. From 2028, airlines must refuel at least 90% of annual volumes. Penalties reach 150% of the average transaction price times the shortfall, but authorities wait a year before enforcement. Meanwhile, the ratios beyond 2027 remain open, and the government will decide them in 2026 and 2029. My standing notes on the mandates I track across the region place this one in that group. This is a south korea saf policy with a firm start date and several dials still moving.
Two ministries, one alliance and a dated ramp do not by themselves tell a lender whether the volumes will land. I read the roadmap as a published schedule with named obligors, real flexibility and ratios that are still open. Below is how I take it into a finance file.
What the South Korea SAF policy requires at a glance
In short
- Duty: 1% SAF blending on international departures from 1 January 2027, rising to 3% to 5% by 2030 and 7% to 10% by 2035.
- Obligor: fuel suppliers, meaning refining companies and petroleum exporters and importers, from 2027; airlines refuel at least 90% of annual volumes blended from 2028.
- Penalty: up to 150% of the average transaction price multiplied by the shortfall, with enforcement deferred for a year.
- Flexibility: up to 20% of the annual obligation carried over, meaning it can be met within the following three years.
- Open: the ratios after 2027 are to be decided in 2026 and 2029.
In this article
What South Korea actually adopted
MOLIT and MOTIE jointly announced the Sustainable Aviation Fuel Blending Mandate Roadmap on Friday 19 September 2025. They also launched the SAF Alliance, with representatives of the aviation and refining sectors and related agencies present. The two ministries announced the SAF Expansion Strategy in August 2024. It was the first coordinated national framework for SAF deployment. Korean airlines set routes, operating periods and blending ratios through purchase contracts with domestic refiners. The MOLIT note sets the announcement against ICAO’s November 2023 target. ICAO aims to cut international aviation carbon emissions by 5% by 2030 through SAF. This target sits inside the wider goal of net zero by 2050. The note also sets it against EU and UK blending mandates that made 2025 the start of SAF obligations. The alliance aims to keep ministries, industry and agencies aligned as the ratios firm up.
What this means for you: the start date sits on a roadmap from two ministries. The roadmap has an alliance that includes the sectors involved and a strategy already in force since 2024. Therefore, I treat the commitment as documented rather than assumed.
The dates and ratios published so far
Mandatory blending starts at 1% in 2027. The blend will rise to 3% to 5% by 2030 and reach 7% to 10% by 2035. The government will set the specific ratios in 2026 and 2029. Its decision will weigh domestic production capacity, international obligations and global market conditions. The airline refuelling requirement applies from 2028. Airlines must blend at least 90% of annual jet fuel volumes for international departures. A compliance management system will run during 2026 and 2027. Officials will pilot it in the first half of 2028. I count each calendar year of measurement as one compliance period. Quality standards for bio-aviation fuels are due in the first half of 2026. Specifically, after 2030, the government will consider weighting fuels from feedstocks with higher carbon reduction rates. I read this schedule next to the Southeast Asia SAF picture, where neighbours sit at different stages.
What this means for you: 1% in 2027 is the number I can underwrite today. The 3% to 5% and 7% to 10% steps are dates for decisions. Therefore, I can date the confirmation rather than the volume.
Who carries the obligation, and how CORSIA is wired in
From 2027 the blending obligation sits with fuel suppliers. This duty sits on refining companies, petroleum exporters and importers. Each year, they must prove compliance through the SAF share they supply for flights leaving South Korea. The airline duty is separate. From 2028, airlines must refuel at least 90% of annual volumes with SAF blended at the departure airport. Korea will recognise as SAF any aviation fuel that achieves the carbon reduction levels required under ICAO standards. ICAO standards also cover lower carbon aviation fuels. These are fossil-based fuels that cut life-cycle emissions by at least 10% against the ICAO baseline. Subordinate regulations under the Act on the Management of Carbon Emissions from International Aviation are meant to ensure that SAF use is reflected in an airline’s CORSIA obligations.
CORSIA requires operators on routes between participating states to cover emissions above a baseline, and 130 states were participating as of 1 January 2026, including Vietnam from that date.
What this means for you: the volume obligation sits with the fuel supplier from 2027, so I match my offtake to a supplier’s annual blend share rather than to an airline’s stated intent.
What the fuel costs and who absorbs the gap
SAF costs several times more than conventional aviation fuel. In fact, SAF still counts for less than 1% of global aviation fuel use. Feedstocks cost more, production technologies are still developing, and upfront investment needs are high. Moreover, physical and market infrastructure is also missing. That gap is why the roadmap mixes the obligation with incentives. Airlines that refuel and operate above the blending requirement receive increased points from 1 to 3.5 in the allocation of international air traffic rights. Airport operators granted fee reductions worth W500 million from Incheon International Airport Corporation in 2025 and 2026. Korea Airport Corporation added W100 million, for a total of W600 million. Instead, the government says it will consider direct subsidies to airlines. Airlines reward passenger contributions at booking with lounge access, preferred seating or SAF-related souvenirs. I track the spread itself at the SAF price page.
What this means for you: the incentive side is real but modest next to the production gap, so I price the fuel differential into my margin and treat the airport fee reductions as support rather than as revenue.
What a finance plan has to survive
The obligation reaches fuel suppliers before it reaches airlines. Therefore, a project selling into Korea needs a counterparty on the refining side, not only an airline statement of intent. Airlines already hold the existing demand in purchase contracts. They set routes, operating periods and blending ratios through those contracts with domestic refiners. Nine domestic airlines already fly selected short-haul routes with a 1% blend. Korean Air extended a 1% blend to Kobe and Osaka in September. The move followed a year-long trial on Incheon to Haneda. The trial used cooking oil from HD Hyundai Oilbank and GS Caltex. IATA’s sequencing warning still applies. Introduce mandates only where market conditions, production capacity, infrastructure and policy support are in place. In the way I approach financing a SAF project, I ask for the instrument, the obligor and the enforcement date before the debt tenor starts.
What this means for you: I want a named refiner across the table and a date I can point at before I size anything.
Where the risk sits today
Enforcement of penalties is deferred for a year, and fines for the refuelling obligation are deferred by a year as well, to give industry time to adjust. Up to 20% of the annual blending obligation can carry over into the following three years. An adjustment system can lower blending ratios under unavoidable circumstances. New airlines stay exempt during their first three years of commercial operations. In addition, the government may grant exemptions for safety concerns or natural disasters. The penalty formula is up to 150% of the average transaction price multiplied by the shortfall in fuel uptake for the year. Beyond 2027, the ratios remain open. Moreover, industry engagement shows refiners backing the mandate on condition that policymakers provide financial incentives. I keep those points in the policy risk note I hold for this market.
What this means for you: a plan that counts 2030 volumes as contracted revenue is counting a ratio and an enforcement date that are both still open.
What I would ask before signing
I ask four questions in writing. First, which entity carries the obligation on my volume, the supplier or the airline. Also, I keep a record against the article of the scheme that says so. Second, I need to know which fiscal year the ratio I am modelling belongs to. The answer may be the confirmed 2027 level or a ratio still open for 2026 or 2029. Third, I need to know what happens to the shortfall when enforcement waits a year. Also, I read the carry-over rule next to it rather than in isolation. Fourth, I ask what share of the offtake purchase contracts with domestic refiners already cover. In fact, that is where the demand already sits. I keep the deferred enforcement and the confirmed start date side by side, each with its source.
What this means for you: written answers to those four questions turn this south korea saf policy from a published roadmap into a position I can price, and every answer carries the date I read it.
How I would model it if it were my file
I put four rows on separate lines and I date every entry:
- Obligation: 1% in 2027 on departing international flights, obligor named as the fuel supplier.
- Ramp: 3% to 5% by 2030 and 7% to 10% by 2035, each flagged as to be confirmed.
- Airline: the 90% refuelling share from 2028, with the pilot scheduled in the first half of 2028.
- Flexibility: the 20% carry-over over three years, the deferred penalty and the three-year exemption for new entrants.
I run the model twice, once with the ramp confirmed on schedule and once with a slip of one cycle, and I show the lender the difference in one line. My last row is the contracted volume, because that is the only row a lender will count.
What this means for you: two runs and one contracted row beat any headline ratio on underwritability. Therefore, that is the page I put in front of the credit team.
Sources
- MOLIT, 23 September 2025.
- GreenAir News, 6 October 2025.
- InfluenceMap, consulted 16 November 2026.
- IATA, June 2026.
- ICAO, November 2026.
- IATA, consulted 16 November 2026.
- ICAO, June 2025.
Frequently asked questions
What is South Korea's SAF blending mandate?
A SAF Blending Mandate Roadmap announced jointly by MOLIT and MOTIE on 19 September 2025 makes SAF blending compulsory for international flights departing South Korea, starting at 1% in 2027 and rising to 3% to 5% by 2030 and 7% to 10% by 2035, supported by a SAF Alliance of ministries, industry and agencies (MOLIT; GreenAir News).
When does the 1% SAF blending requirement start?
The mandatory blending ratio starts at 1% in 2027, and from 2028 international flights must refuel at least 90% of their annual volumes as SAF blended at the departure airport, with the compliance management system built during 2026 and 2027 and piloted in the first half of 2028 (GreenAir News; InfluenceMap).
Who carries the obligation, airlines or fuel suppliers?
From 2027 the blending obligation sits with fuel suppliers, meaning refining companies and petroleum exporters and importers, while the refuelling share applies to international airlines from 2028 (GreenAir News).
Does the South Korean mandate make a project bankable?
It creates a dated demand signal with penalties capped at 150% of the average transaction price multiplied by the shortfall, but enforcement is deferred, up to 20% of the obligation can be carried over for three years, and the ratios after 2027 are still to be confirmed in 2026 and 2029, so a finance plan still needs signed purchase contracts before treating the ramp as contracted revenue (GreenAir News; InfluenceMap).
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If you are putting a Korean volume into a term sheet, I would rather review the structure before the numbers harden: offtake agreements is where I start that conversation, working from the published obligor, the confirmed 2027 ratio and the deferred enforcement dates.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.