Development Capital vs Project Equity in SAF Projects
6 min read · Sep 3, 2025 · By Alex
This page belongs to the equity guide for sustainable aviation fuel in Southeast Asia. Development capital pays for the work before construction finance exists. Project equity pays to build the plant. Developers often ask me which one to raise first, and the answer depends on one thing: can you already show a project that lenders and infrastructure funds would call bankable?
In short
- Development capital funds the pre-construction work: engineering, permitting, legal work and the development team. One specialist provider puts it at roughly 5 to 10 percent of total project cost.
- Project equity arrives later, in large cheques, from investors who want a project close to FID and tolerate little risk.
- Banks generally do not lend for early development work, so the first money usually comes from the sponsor, a joint venture partner or a rare specialist fund.
- Early money is repaid through reimbursement, a development fee, a stake in the project or all three, and it usually comes with control rights.
In this article
Two different jobs
The two types of capital do not compete. They fund different stages. Development capital pays for the work that turns an idea into a project that can be financed. Project equity, with debt alongside it, pays for the plant itself. Each has its own investors, its own risk appetite and its own price.
What this means for you: decide first where your project stands. The answer tells you which investors to approach.
What development capital pays for
According to Tuatara Development Capital, a provider writing about its own market, development capital covers the development team’s overheads, site acquisition or options, front-end engineering, permitting and technical consultants, legal work on the commercial agreements, and preparation for debt and tax equity. It is spent before a final investment decision.
The same source estimates development spending at about 5 to 10 percent of total project cost, with sums in the millions or tens of millions of dollars. On a USD 100 million SAF plant, that means roughly USD 5 to 10 million at risk before construction finance is possible. It is also binary: the author notes that some projects end in a total loss.
What this means for you: build a development budget, with milestones, before you speak to any investor.
Who provides it
Not many. Tuatara describes development capital as mostly unavailable because it is not a recognised investment class, and explains why other investors stay away. Venture capital funds the creation of new intellectual property, and project development is execution. Private equity looks for established cash flows, and a plant that is not built has no EBITDA. Infrastructure equity writes cheques of hundreds of millions and cannot absorb a total loss.
Haynes Boone, writing about renewable projects in 2024, describes the usual alternative: a joint venture partner, often a utility or a financial investor, who releases funds phase by phase as development milestones are met. The money comes as shareholder loans or preference shares in the joint venture company. Banks, it notes, generally do not lend for early development work because the outcome is uncertain.
What this means for you: your realistic sources are your own capital, a strategic or financial joint venture partner, and a few specialist funds.
How early money is repaid
A 2009 panel of US renewable energy investors, reported by Chadbourne, gives a useful picture of the mechanics, even though it is old and concerns another technology. One investor makes a loan that converts into equity in the project company when construction finance closes, with triggers that let it take control if milestones are missed. The developer is paid in three ways: reimbursement of development spending, a development fee at construction closing, and a carried interest that pays out after the investor has recovered its capital plus a preferred return.
The panel’s illustration: a developer that invested USD 2 million might receive a fee of USD 4 to 6 million on top of the USD 2 million reimbursement. Treat these figures as an illustration of the structure, not as SAF market terms.
What this means for you: negotiate the conversion, the fee and the control triggers before you sign, because they decide who owns the project at FID.
What project equity is
Project equity is the risk capital that sits beneath the debt once the project is ready to build. Tuatara notes that equity needs above USD 400 million narrow the pool of infrastructure investors, and that projects needing more than USD 500 million of unrated debt often depend on government loan guarantees. Haynes Boone adds that leverage can range from under 50 percent to over 80 percent depending on the technology and the contractual protections.
These investors look for contracted cash flow: a signed offtake, secured feedstock, a proven technology and an EPC contract. Without them, the project is still a development project.
What this means for you: do not approach infrastructure funds with a concept. Approach them with a project that has the contracts they underwrite.
Which one fits your stage
The split follows the stage of the project. It is a tendency, not a rule: there are no hard and fast rules, and some financial investors provide both early and construction funding.
| Question | Development capital | Project equity |
|---|---|---|
| What it pays for | Engineering, permits, legal work, development team | Building the plant, alongside debt |
| When | Before FID | Around FID and construction |
| Typical size | Millions to tens of millions of dollars | Tens to hundreds of millions of dollars |
| Risk taken | High, a total loss is possible | Lower, needs contracts in place |
| Who provides it | Sponsor, joint venture partner, a few specialist funds | Infrastructure and private equity funds, strategic investors |
| What the investor asks for | Control, milestones, a stake or fee at FID | Signed offtake and feedstock, bankable technology |
What an early investor will ask of you
Early investors expect substantial control. Board appointments and decisions on exit are among the usual requests. They also want a clear path to FID, because they are paid when the project reaches financial close. IRENA observed in 2025 that well-structured renewable projects can reach financial close in 6 to 15 months, yet many remain stuck for years because development funding is missing, and that developers then rely on their own equity or on grants.
I see the same gap among SAF developers in Southeast Asia: a technical study and a mandate on paper, but no development budget and no list of milestones.
What this means for you: bring a budget, a milestone list, a view on who should own what at FID, and a clear position on what you will not give up.
Common mistakes I see repeated
- Asking an infrastructure fund to pay for development work it cannot underwrite.
- Raising development capital without a milestone plan, so the investor cannot tell when the project has earned its next tranche.
- Giving away control at the first cheque without agreeing what happens at FID.
- Treating the development fee and the reimbursement as one number.
Sources
- Biofuels Digest, Bridging the development capital gap
- Haynes Boone, Funding renewable energy project developments (May 2024)
- Chadbourne, Finding development capital (February 2010, panel held in 2009)
- IRENA, Early-stage project financing (April 2025)
Frequently asked questions
What is development capital in a SAF project?
The money that pays for the work before construction finance exists: engineering, permitting, legal work and the development team. One specialist provider estimates it at about 5 to 10 percent of total project cost.
Do banks lend for SAF project development?
Generally not. Haynes Boone notes that banks do not usually lend for early-stage development because the outcome is uncertain. Banks arrive when the project is ready to build.
How is development capital repaid?
Usually through reimbursement of the spending, a development fee and a stake in the project at financial close. A 2009 investor panel described a loan that converts into equity at that point. Terms vary and are negotiated.
Can one investor provide both development and project equity?
Yes. Haynes Boone notes there are no hard and fast rules and that some financial investors fund both stages. The investor will then expect control and a clear path to FID.
Preparing an equity conversation for a SAF project?
A short call is usually enough to see where your project stands.
I can help you work out whether you need development capital or project equity first, and who should hear your story. See how I work on investor introductions.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.