Green Methanol Projects in Asia: A Developers Map by Region and Stage
10 min read · Nov 2, 2026 · By Alex
I sort Asia’s methanol build-out by region and by stage. The map holds in three published numbers. I tracked more than 200 renewable and low-carbon methanol projects in February 2025 for a potential 45.8 million tonnes a year by 2030, with China holding half of that pipeline, recorded by the Methanol Institute in 2025. Green methanol projects asia-wide hinge on two further figures: Argus recorded on 16 May 2025 that Southeast Asia methanol capacity rises from 7.5 to 10.8 million tonnes after the Sarawak launch, and MIDA recorded on 23 July 2024 that Malaysia’s Sarawak complex carries 1,750,000 tonnes a year of conventional methanol, while its green methanol plant only broke ground in January 2025. The green methanol explained page frames the molecule those projects would make.
Three different claims sit behind those figures: an announced pipeline, a regional capacity number. In addition, one plant that is already running. I keep them apart because a partner reacts differently to each. In addition, the distance between them is where most early conversations go wrong.
In short
- Pipeline: More than 200 projects and 45.8 million tonnes of announced capacity. Only 20 to 40 percent of them are likely to move.
- Southeast Asia: Demand of 4.1 million tonnes in 2024 rising to 4.8 million tonnes in 2028. Capacity stands at 10.8 million tonnes.
- Sarawak: 1,750,000 metric tonnes a year of conventional methanol running; the green plant only broke ground in January 2025.
- Buyers: Offtake terms of 5 to 15 years, with 500,000 tonnes a year and 100 kt a year signed.
- Stage test: Announced, under construction or operating, then conventional or green, then buyer, then firm volume.
In this article
What the map shows
Start with what each number counts. The 45.8 million tonnes a year is announced capacity, meaning projects declared but not yet built. In addition, the set of them I call the pipeline. The Methanol Institute recorded in 2025 that only 20 to 40 percent of those announced projects may move forward, which would still represent 7 to 14 million tonnes of low-carbon and renewable methanol supply in the next five years. Against that base, total methanol supply in 2024 was 94 million tonnes. In addition, 400,000 to 500,000 tonnes of renewable product was actually sold.
Two definitions then carry the rest of the reading. Green methanol comes from renewable hydrogen and captured carbon dioxide. Conventional methanol is the fossil product that supplies most of today’s market. The line between them decides whether a volume can be counted toward a decarbonisation claim.
What this means for you: I ask for the stage before I ask for the tonnage. Announced capacity is a claim, sold volume is a result, and only one of them appears in a buyer’s books.
Southeast Asia: demand, capacity and one running complex
Argus recorded on 16 May 2025 that regional demand is about 4.1 million tonnes in 2024. That rises to 4.8 million tonnes in 2028, that Southeast Asia capacity rises to 10.8 million tonnes from 7.5 million tonnes after the Sarawak launch, that biodiesel drove demand growth and accounted for 45 percent of regional demand in 2024, and that shipowners are cited as the drivers of announced capacity while 11 projects in China holding more than 3 million tonnes a year of capacity have been paused.
MIDA recorded on 23 July 2024 that Sarawak Petchem’s complex at Tanjung Kidurong in Bintulu has an annual production capacity of 1,750,000 metric tonnes, that Sarawak Petchem is Malaysia’s second-largest methanol producer after PETRONAS Chemical, and that with its commissioning Malaysia became the leading methanol producer in the Asia Pacific region. The Southeast Asia green methanol page covers that regional market.
What this means for you: I treat the 10.8 million tonnes as regional capacity rather than green supply. In addition, I ask which running plant is certified for marine fuel before I count any of it toward a charter.
What the neighbouring map shares
Published 2025 milestones record about 4 million tonnes of low-carbon, blue, bio-methanol and e-methanol facilities operational or under construction as of February 2025. In addition, they show China holding half of the global bio-methanol and e-methanol project pipeline, expected to be the main supplier of renewable methanol from 2025 to 2027. Read alongside Clarksons Research, the same data count 50 methanol dual-fuel vessels in service . At the start of 2025, 350 methanol-capable ships were on order and nearly 700 methanol-ready ships. Therefore, more than 1,000 vessels classed for methanol will enter service over the next five years.
The neighbouring map matters because supply announced in one country. In addition, demand booked in another have to be read with the same method: stage first, then chemistry, then contract. The hydrogen developers map for the region uses the same reading method.
What this means for you: I read the order book as a demand signal rather than a supply plan. A ship delivered in 2027 still needs a signed volume of green methanol behind it.
Who signs for the molecules
An offtake agreement binds a buyer to a stated volume for a stated period. State of Green recorded on 26 June 2025 that in November 2023 Maersk signed a green methanol offtake with Goldwind for 500,000 tonnes a year from 2026, covering its first 12 methanol-powered container ships; that in October 2024 it signed a long-term bio-methanol offtake with LONGi Green Energy Technology from agricultural residues and forest by-products; that together they cover more than 50 percent of the green methanol Maersk needs for its dual-fuel fleet in 2027; and that it targets up to 600,000 tonnes a year from 2026 with at least 65 percent lifecycle greenhouse gas reduction.
Maritime Propulsion recorded on 3 November 2026 that Maersk operates about 20 methanol-capable container ships. It reached its target of 19 in 2026, that Hapag-Lloyd ordered eight dual-fuel methanol ships of 4,500 TEU in December 2025 for delivery in 2028 and 2029, and that methanol ship deliveries were 59 in 2025 and 38 in the first half of 2026. The marine fuel offtake page sets out what those buyers are contracting.
What this means for you: a target of 600,000 tonnes a year. In addition, a signed 500,000 tonnes a year sit in different columns of my file.
What pulls the demand
Invest India recorded on 5 November 2026 . Offtake agreements typically run 5 to 15 years and are often signed years before first delivery, that publicly announced Indian agreements cover up to 1.2 million tonnes a year of renewable ammonia and 100,000 tonnes a year of green methanol, that Uniper and AM Green announced up to 500,000 tonnes a year in January 2026 with first deliveries from 2028, that Hintco and AM Green signed for 10 years at a minimum value of 585 million euros with deliveries from 2029, and that Hintco and ACME signed for 10 years and 100 kt a year of green methanol in 2026.
The same source records an IEA figure cited there. Only one fifth of the 1.7 Mtpa of new low-carbon hydrogen supply in 2025 was firm. The low-carbon fuel mandates page covers the rules behind that demand.
What this means for you: I check the term against the first delivery date. An agreement of 10 years starting in 2029 tells me nothing about whether fuel is available in the near term.
How a developer enters a new region
The Star recorded on 20 January 2025 that the ground-breaking ceremony for the Sarawak Petchem green methanol plant at Tanjung Kidurong took place in the week before publication, that the company chairman said the plant would use water electrolysis, meaning electricity used to split water into hydrogen, powered by renewable energy with captured carbon dioxide as feedstock, and that green methanol could be used as a sustainable marine fuel. At the same event 20,000 tonnes of methanol left for China in two vessels from the Sarawak complex.
The same report records that about 7 billion RM was invested in that complex, that it Samsung Engineering built it with an annual capacity of 1.75 million tonnes, and that Sarawak expected to partner Japanese investors in a joint venture producing ammonia and hydrogen, with a memorandum of understanding due in May. The market entry page sets out the sequence for a new region.
What this means for you: I read the 20,000 tonnes as conventional product leaving a running plant. In addition, I keep the ground-breaking in a separate row from the complex that produced it.
What I would check before I call a project real
I ask five questions in writing before I treat any project as real. I record the answer with its date beside it.
First, has it reached a final investment decision, the point where the owners commit the capital. In addition, is it announced, under construction or operating? The 2025 milestones record about 4 million tonnes operational or under construction as of February 2025. Second, is it green methanol or conventional methanol? The July 2024 release records 1,750,000 tonnes a year of conventional capacity. Third, is there a buyer? The June 2025 record shows the Goldwind agreement of 500,000 tonnes a year. Fourth, is the offtake firm rather than aspirational? The November 2026 note records that only one fifth of the 1.7 Mtpa of new low-carbon hydrogen supply in 2025 was firm. Fifth, is the plant actually built? The January 2025 report records only a ground-breaking.
What this means for you: a project that fails any of these five lines stays in the announced column of my own file, whatever the press release says.
How I would keep the map
I keep four dated rows in one table, and I enter every claim on the day I read it.
The pipeline row carries more than 200 projects and 45.8 million tonnes announced in the 2025 milestones, against the 400,000 to 500,000 tonnes sold in 2024. Also, the region row carries 4.1 million tonnes rising to 4.8 million tonnes and 10.8 million tonnes of capacity from the 16 May 2025 regional data. The anchor row carries 500,000 tonnes a year from State of Green in June 2025 and 100 kt a year from Invest India on 5 November 2026. In addition, the stage row carries the January 2025 ground-breaking from The Star.
A row without a date is a rumour in my file. Therefore, I never leave one blank, and I never move a volume from announced to operating without a dated record behind it.
What this means for you: every row carries its publisher and its date. Therefore, I can see within one line whether a claim has moved since I last read it, and which column it belongs in.
Sources
- Methanol Institute, 2025.
- Argus, 16 May 2025.
- MIDA, 23 July 2024.
- The Star, 20 January 2025.
- Invest India, 5 November 2026.
- Maritime Propulsion, 3 November 2026.
- State of Green, 26 June 2025.
Frequently asked questions
Where are green methanol projects being built in Asia?
In three published places. China holds half of the global bio-methanol and e-methanol project pipeline and is expected to be the main supplier of renewable methanol from 2025 to 2027. Southeast Asia capacity rose to 10.8 million tonnes from 7.5 million tonnes after the Sarawak launch. India has publicly announced agreements covering up to 100,000 tonnes a year of green methanol. Those three readings come from the 2025 milestones, the 16 May 2025 regional data and the 5 November 2026 note.
How much announced capacity is real supply?
Very little of it. The 2025 milestones record that only 20 to 40 percent of more than 200 announced projects may move forward, which would still be 7 to 14 million tonnes over the next five years. Against that, 400,000 to 500,000 tonnes of renewable methanol were actually sold in 2024, out of a total supply of 94 million tonnes.
Which developers have signed long-term buyers?
The 26 June 2025 record shows the Goldwind agreement of 500,000 tonnes a year from 2026 and the LONGi bio-methanol agreement signed in October 2024 from agricultural residues and forest by-products. The 5 November 2026 note records the Hintco and ACME agreement of 100 kt a year over 10 years.
Should I count Sarawak's methanol as green methanol?
No. The July 2024 release records that the Sarawak complex produces 1,750,000 metric tonnes a year of conventional methanol and made Sarawak Petchem Malaysia’s second-largest producer after PETRONAS Chemical. The January 2025 report records that the green methanol plant at Tanjung Kidurong was only breaking ground at that date.
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If you want to place your own project against this picture, I work with developers. In addition, buyers on the strategic partnerships that move a volume from announced to signed, starting from the same five checks I use on every file.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.