HEFA SAF Explained: What Project Investors Are Actually Financing

10 min read  ·  Nov 2, 2026  ·  By Alex

hefa saf

Any investor sizing a sustainable aviation fuel project in Southeast Asia asks why one conversion route carries almost all of today’s volume? The answer is short: maturity, an accepted qualification date and a blend rule already in the standard. I set out the two limits that decide whether the model holds. HEFA SAF dominates, and it is the approved route at technology readiness level 9 (ICAO ACT-SAF). Hydroprocessed esters and fatty acids run from concept to commercial deployment, qualified in 2011 for blending up to 50 percent. In addition, two limits remain: the jet yield and the waste oil contract (IEA Bioenergy Task 39).

I read a HEFA file the way a lender reads it. Three questions matter: what the standard allows, what the unit produces, and what the contract can carry. The headings below follow that order, and each section closes with the action I would take. The facts come from ICAO, IEA Bioenergy, IATA, IRENA and the World Economic Forum.

In short

  • Maturity: qualified in 2011 at technology readiness level 9, with a blend limit of 50 percent.
  • Process: pretreatment, hydrodeoxygenation, then hydrocracking and hydroisomerization.
  • Feedstock: vegetable oils, animal fats and used cooking oil (kitchen fats collected after frying), with waste and residue supply expected above 40 Mt/a by 2030.
  • Yield: about 15 percent of hydrotreated fats and oils falls in the jet range, meaning the kerosene boiling band.
  • Contract: 70 to 80 percent of annual capacity under offtake, over a tenor of 8 to 14 years.
Facebook
Twitter
LinkedIn

In this article

The short answer: the most mature route with the tightest feedstock

ASTM D7566 Annex A2 approves HEFA-SPK. That annex is the ASTM International specification for aviation turbine fuels containing synthesised hydrocarbons. It qualified in 2011. Refiners blend it with petroleum-based jet fuel up to a 50 percent maximum level. In addition, it stands at technology readiness level 9, proven and commercially deployed (ICAO ACT-SAF). ICAO ACT-SAF calls it the most commercially viable SAF conversion pathway. It is also the route behind the majority of SAF available today. It takes vegetable oils, animal fats and used cooking oil as feedstock (ICAO). Two limits go into my price from day one. One is the share of output that lands in the jet range. The other is the waste oil contract that feeds the unit (IEA Bioenergy Task 39).

What this means for you: maturity is already banked. So my attention sits on the two variables the standard does not fix. One is how much of each tonne becomes jet fuel. Also, who signs for the oils that feed the unit?

What the unit actually does to the feedstock

The HEFA route runs three steps. Pretreatment removes impurities from the feedstock before refining. Hydrodeoxygenation removes oxygen atoms from biogenic fats and oils with hydrogen, creating a pure hydrocarbon n-paraffin with high energy density. Hydrocracking and hydroisomerization then crack and isomerize those pure hydrocarbons. That creates the HEFA-SPK synthetic jet fuel component with the desired properties (ICAO ACT-SAF). Neste makes its HEFA from sustainably sourced, 100 percent waste and residues. Currently it uses only used cooking oil and animal fat waste for SAF production (ICAO ACT-SAF). Waste and residue oils and fats should exceed 40 Mt/a by 2030 (ICAO ACT-SAF). I read the regional feedstock security picture before I read the process design.

What this means for you: I ask for the pretreatment guarantee and the oil supply curve together. The reason is that the second step runs cleanly only when the first one holds.

The lifecycle value that follows the pathway

CORSIA default life cycle values exist for many HEFA feedstocks. In addition, ICAO lists the conversion processes that already have them, including FT, HEFA, SIP and ATJ (ICAO ACT-SAF, ICAO). SAF must have the same chemical qualities as conventional jet fuel. Therefore, engines, aircraft and delivery systems need no redesign. Also, once it demonstrates compliance, refiners blend it with conventional jet fuel and re-test it (ICAO Aviation Benefits). Of the approved conversion processes, eight sit under ASTM D7566. The remaining three follow ASTM D1655 because of co-processing with conventional fossil jet (IRENA). A blend limit exists for a physical reason. Some components of conventional jet fuel, such as sulphur, allow seals to swell in engines and prevent fuel leaks. Also, higher limits should come as manufacturers work towards compatibility with 100 percent SAF by around 2030 (ICAO Aviation Benefits). The sustainability criteria are part of the specification.

What this means for you: I check the default lifecycle value for the specific oil in the model. That figure, not the pathway name, sets the emissions claim attached to every consignment.

What the fuel has to clear in price

SAF production in 2025 reached 1.9 million tonnes, only 0.6 percent of total jet fuel consumption. Also, forecasters project 2.4 million tonnes and 0.8 percent for 2026 (IATA). SAF prices exceed fossil-based jet fuel by a factor of two. In mandated markets the factor reaches five. At current price levels, the SAF premium adds USD 3.6 billion in fuel costs for the industry in 2025 (IATA). Demand for global SAF should reach 17 million tonnes per annum by 2030. That is approximately 4 to 5 percent of total jet fuel consumption (World Economic Forum with Kearney). I treat the price of the fuel as the gap the contract must close.

What this means for you: I write the offtake at the mandated premium. Then I test what happens if that premium narrows as supply grows toward the 17 million tonne target.

The competitor inside the same tank

The HEFA pathway has been fully commercial for some time. However, producers have mainly used it for renewable diesel rather than SAF. Renewable diesel is the road fuel made from the same oils and fats. Also, many new facilities will divert up to 70 percent of total liquid product to SAF (IEA Bioenergy Task 39). The decision to shift to increased SAF production will likely rest on financial considerations, with policy playing a key role. SAF must compete with renewable diesel for road transportation (IEA Bioenergy Task 39).

The supply of waste and lower carbon intensity feedstocks will soon cap output. That covers fats, oils and greases used for renewable diesel and SAF through the HEFA pathway. The reason is that crop-derived lipids carry a higher carbon intensity or other sustainability challenges. Meanwhile, carinata and camelina could add volume, but their commercial availability is currently insignificant (IEA Bioenergy Task 39).

What this means for you: I price the same unit twice, as a jet fuel plant and as a road fuel plant. The reason is that the second quote sits next to mine in the same negotiation.

What a lender tests first on a HEFA file

Investors often require offtake agreements for at least 70 to 80 percent of annual capacity. Those contracts commit a buyer to take the output. In addition, some lenders require reliable offtake on 100 percent of the SAF produced. That cover must run the full loan tenor (World Economic Forum with Kearney). Offtake contracts are often non-binding memoranda of understanding. A project needs binding agreements to reach the final investment decision (FID), the point where the sponsor commits the capital. Also, the offtake needs to cover the tenure of debt financing, for example 8 to 14 years (World Economic Forum with Kearney).

The SAF refinery lifecycle has five critical phases: conceptualization, pre-feasibility, FID, construction and commissioning (World Economic Forum with Kearney). Meanwhile, e-SAF faces a cost base potentially up to 12 times that of conventional jet fuel. That is the comparison a lender runs when asked why the project does not simply go power-to-liquid (IATA). This is where project finance tests the file.

What this means for you: I sign a binding offtake first and fit the debt tenor to it. A memorandum will not carry a loan.

The order I would run the HEFA file in

I start from the feedstock. The route only works with oils and fats that you can contract and trace. Also, waste and lower carbon intensity feedstocks are already the binding constraint (IEA Bioenergy Task 39). Then I fix the jet yield in the model. Only about 15 percent of hydrotreated fats and oils falls within the jet range. Raising that share costs money and loses liquid yield (IEA Bioenergy Task 39). Next I confirm the approval and blend position under ASTM D7566 Annex A2 at 50 percent (ICAO ACT-SAF). Then I write the offtake to cover the debt tenor (World Economic Forum with Kearney). After that I price the route against renewable diesel in the same unit (IEA Bioenergy Task 39).

Finally I walk the five phases to FID (World Economic Forum with Kearney). I apply that sequence in technology maturity and scale-up work.

What this means for you: running these checks in order tells me early what the file carries. That is a yield problem, a contract problem or a policy problem.

How I would run this if it were my file

I treat the feedstock contract and the jet yield as the two lines that decide the credit. Also, I ask for the pretreatment design before I accept the yield assumption. Low-quality waste feedstocks carry numerous contaminants, and that is where on-site and optimized pretreatment has moved (IEA Bioenergy Task 39). I use the built reference as the maturity proof. Neste had 100 kton of SAF total global production capacity in 2019. In addition, it reached 1.5 Mton of total global capability in 2024 through investments in Rotterdam and Singapore. Furthermore, it expects 2.2 Mton in 2026 through further investment in Rotterdam (ICAO ACT-SAF).

The Neste refinery at Tuas in the west of Singapore has operated since 2010. It runs an annual production capacity of 1.3 million tons of renewable and circular solutions. Also, its expansion to add SAF capability was due to start during Q3 2023 (ICAO ACT-SAF). In Southeast Asia the reference list also includes EcoCeres at Tanjung Langsat with 220,000 tonnes planned for 2025. Also, Petronas and Idemitsu at Pengerang plan 650,000 tonnes for 2026. Also, Bangchak at Phra Khanong plans 292,000 tonnes for Q1 2025 (IRENA).

What this means for you: I treat those operating and planned units as the comparables for yield, cost and contract terms. Also, I ask which of them has signed binding offtake before I commit to anything myself.

Sources

Frequently asked questions

It is the most mature route rather than the safest one. HEFA-SPK is the most commercially viable SAF conversion pathway and the one used for producing the majority of SAF available today, at technology readiness level 9, qualified under ASTM D7566 Annex A2 in 2011. The constraint it carries is feedstock: waste and lower carbon intensity oils and greases will soon limit production, and crop-derived lipids carry a higher carbon intensity or other sustainability challenges (ICAO ACT-SAF, IEA Bioenergy Task 39).

Vegetable oils, animal fats and used cooking oil are the approved feedstocks for HEFA-SPK (ICAO). Neste currently only uses used cooking oil and animal fat waste for the production of SAF, and availability of waste and residue oils and fats is expected to exceed 40 Mt/a by 2030 (ICAO ACT-SAF).

Yes. The pathway has been primarily used to produce renewable diesel rather than SAF, and new facilities target SAF by diverting up to 70 percent of the total liquid product, with the decision between the two driven by financial considerations and policy, since SAF competes with renewable diesel for road transportation (IEA Bioenergy Task 39).

HEFA-SPK must be blended with petroleum-based jet fuel up to a 50 percent maximum level, and SAF in general must have the same chemical qualities as conventional jet fuel and be re-tested after blending with conventional jet fuel (ICAO ACT-SAF, ICAO Aviation Benefits).

Not sure your project would survive a credit conversation?

A short call is usually enough to see where your project stands.

If you are at feasibility stage on a HEFA file in Southeast Asia and you want a structured read on feedstock, yield and offtake before the model hardens, investor introductions is where I introduce operators to investors who already understand this pathway and its limits.

I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia

I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.

More about me·Get in touch

Facebook
Twitter
LinkedIn

Related articles