Home » Policy Risk for Maritime Fuel Projects: The Dates That Move and the Clauses That Survive
Policy Risk for Maritime Fuel Projects: The Dates That Move and the Clauses That Survive
10 min read · Nov 2, 2026 · By Alex
Two shipping fuel rules I model have already moved a date, and neither move cancelled anything. The IMO Net-Zero Framework got approval at MEPC 83 in April 2025 for adoption in October 2025. The formal committee vote that would place the text in MARPOL Annex VI, and on 17 October 2025 the extraordinary session was adjourned for 12 months. On the European side, the incorporation of FuelEU Maritime into the EEA, the European Economic Area agreement, was delayed by a notification of 18 December 2025. norwegian and Icelandic ports are treated as third-country ports. Two regimes, two slips: I build the file so that a date can move without the project dying. That is maritime fuel policy risk in practice, and the sustainable maritime fuels page is where I keep the working notes.
A lender at pre-FID stage does not need a political forecast from me. I need to know how much regulatory uncertainty the model can carry, and which clause absorbs the shock when a calendar moves. The answer is structural, not predictive.
In short
- The date that moved: the global framework got approval in April 2025, and its adoption session slipped for 12 months on 17 October 2025.
- The scope that holds: both regimes turn on 5,000 gross tonnes, so scope is the stable part of the model.
- The demand signal: 275 orders for alternative fuelled vessels in 2025, down 47 percent, with alternatives at 38 percent of gross tonnage.
- The cost already billed: the EU ETS phase-in moved from 40 percent of verified 2024 emissions to 100 percent from 2026.
- The clause that survives: five tests before I sign, each naming a party, a date and a price formula.
In this article
What policy risk is in a maritime fuel file
Policy risk, as I use the term in a maritime fuel file, is the chance that a published rule changes one of its settings between signing and operation, and that the change lands on the project instead of on the regulator. Furthermore, I do not forecast politics. Instead, I price four settings.
The first is the date of entry into force, the moment an amended instrument starts to bind its parties. Specifically, The second is scope: which tonnage the rule reaches and which voyages it counts. Specifically, The third is stringency, how demanding the standard is and how fast it tightens. Moreover, The fourth is the price of non compliance, what a shortfall costs once it must be covered.
Any one of the four can move while the other three hold, and the file has to survive each combination.
What this means for you: I put four separate assumptions in the model, one for each setting, each with its own date. Also, its own sensitivity, so that a slip shows up as a line item rather than as a surprise.
The global rule and the year it lost
The framework sits behind the Net-Zero Framework explained. In addition, The press briefing of 17 October 2025 records that the extraordinary session of 14 to 17 October 2025 was adjourned and will be reconvened in 12 months, while the intersessional working group on greenhouse gas emissions still met from 20 to 24 October 2025 to continue the implementation guidelines. Consequently, Approved at MEPC 83 in April 2025 as a new chapter 5 of the draft revised Annex VI. Furthermore, The framework carries two elements: a global fuel standard and a global greenhouse gas pricing mechanism.
The FAQ gives the mechanics. In addition, Adoption needs a two thirds majority of Parties present and voting, and MARPOL Annex VI has 108 Parties. By contrast, Tacit acceptance, the procedure by which an amendment stands accepted unless someone formally objects, deems the text accepted after a minimum of ten months unless objection comes from less than one third of the Parties or from Parties representing 50 percent of world tonnage; entry into force follows six months later.
Scope is tonnage: ships above 5,000 gross tonnes, more than 85 percent of international shipping emissions, are covered, ships below 5,000 gross tonnes are not. Also, a discussion runs on ships between 400 and 5,000 gross tonnes. Meanwhile, The framework is reviewed every five years.
What this means for you: I run two dates, one if the vote lands in 2026 and one if it slips again. Also, i check which of the two the model can carry.
The European rule and its own slip
The caps sit inside the FuelEU Maritime rules. However, The FuelEU page of the European Commission records that Regulation (EU) 2023/1805 has applied fully since 1 January 2025, except articles 8 and 9 since August 2024, and that it caps the annual average greenhouse gas intensity of the energy used by ships above 5,000 gross tonnes calling at European ports, whatever their flag, against the 2020 average: 2 percent in 2025, 6 percent in 2030, 14.5 percent in 2035, 31 percent in 2040, 62 percent in 2045 and 80 percent in 2050. Moreover, The same page records that ships above 5,000 gross tonnes are 55 percent of all ships and 90 percent of the sector’s carbon dioxide emissions.
Greenhouse gas intensity is the greenhouse gas emitted per unit of energy used, measured well-to-wake, from production through to combustion.
The slip sits on the European side as well. Moreover, A notification of 18 December 2025 delayed the incorporation of FuelEU Maritime into the EEA agreement. Therefore, norwegian and Icelandic ports have been treated as third-country ports since 1 January 2025. Regulation (EU) 2026/394 of 23 February 2026 governs access to the FuelEU database. Also, a study published in July 2026 examined carbon leakage and competitiveness.
What this means for you: I model the port list rather than the flag list. Also, i re-check that list whenever a notification moves a port in or out of scope.
The demand that depends on those rules
Orderbooks react first. The annual figures from DNV record 275 orders for alternative fuelled vessels in 2025, down 47 percent, inside a newbuilding market that fell to 2,403 orders from 4,405 in 2024, with the alternative share of gross tonnage held at 38 percent. LNG led with 188 orders, 31 percent of total gross tonnage. Methanol fell to 61 orders from 149 in 2024, while ammonia and LPG saw limited uptake. In the container segment the tonnage split runs about 58 percent LNG, 36 percent conventional and 6 percent methanol, and 22 LNG bunkering vessels joined the orderbook next to vessels able to supply methanol and biofuels.
The same source reads the slowdown as a year shaped by regulatory uncertainty, with owners concentrating on segments where infrastructure, regulatory certainty and commercial viability align. A mandate works on this market in one direction: it converts a voluntary orderbook into a compliance schedule, and the mandates that bind demand set that schedule, not the appeal of a fuel, so the schedule sets the order date.
What this means for you: I do not read order counts as demand. I read them against the compliance calendar and ask which deadline forced the order, and whether that deadline still exists.
The cost layer already billed
Some of this risk is already an invoice, and the maritime fuel bankability page shows how a lender reads that invoice. The European Commission report of 18 March 2025 records that the extension of the EU ETS, the emissions trading system, to maritime transport applies since January 2024 to cargo and passenger ships above 5,000 gross tonnes, and from 2027 to offshore ships above 5,000 gross tonnes. Its phase-in, the schedule by which surrendered allowances rise, runs at 40 percent of verified 2024 emissions, 70 percent of 2025 emissions and 100 percent from 2026, when methane and nitrous oxide also come into scope.
Scope reaches 100 percent of emissions on voyages between EU ports and at berth in them, and 50 percent of emissions on voyages between an EU port and a port outside the jurisdiction. The report puts the average increase in total shipping costs at 3.7 percent in 2024 where no efficiency measure is taken, and records surcharges of 1 percent to 5 percent on deep sea container services and 3 percent to 11 percent on European ferry lines in that year. It also carries a clause requiring a fresh report every two years.
What this means for you: I put the surrender obligation in the operating budget from day one, with the phase-in dates written into the tariff model instead of assumed away.
Where the risk lands in the contract
A rule change reaches a project through three channels, and I draft each one separately, starting from the offtake and pass-through clauses I review. The cost pass-through clause decides which party absorbs a new levy and from which date. The compliance obligation clause names the party that buys and surrenders the units. Also, the date by which it must do so. The change in law clause carries its own pricing formula. Therefore, a new obligation is priced by a stated method rather than by argument.
The guide from Global Maritime Forum records that the Net-Zero Fund remains the least developed part of the guidelines, and that discussions have fragmented, with some countries proposing to reopen the legal text agreed at MEPC 83. In the draft text, a compliance balance is the position held when banked or transferred surplus units offset a deficit. Also, a remedial unit is one bought through a contribution to that fund. A fund whose rules are unfinished is a price that cannot be fixed yet.
What this means for you: I will not sign a pass-through clause that points at a future fund with no formula, and I ask for the party, the date and the method in the same sentence.
The five clauses I would test before I sign
By this point I am reading signatures rather than forecasts, and five tests decide whether I take the paper. A rule change hurts only where a contract is silent.
- Which party: the party for whom the ship is counted under the standard, named in one line: registered owner, charterer or operator.
- Target date: whether the standard’s date is a condition precedent, which blocks a draw until it is met, or a covenant I test each year.
- Slip formula: what happens to the price if adoption slips another year, written as a formula rather than as a reopening.
- Verification: whether the fuel’s certified greenhouse gas intensity can be checked by an independent scheme recognised by the committee.
- Fund change: who pays the compliance units if the fund rules change after financial close, the date on which the financing documents are signed and the conditions to draw are met.
What this means for you: I ask for all five in the term sheet, because a clause that is missing at signing will not appear when the pressure arrives.
The watchlist I keep, with dates
I keep four rows, each with a date and a name against it. Nothing here is a forecast: each row is a published date attached to a published body.
- Adoption of the global framework: the reconvened extraordinary session, held 12 months after 17 October 2025, so during 2026; owner, the Marine Environment Protection Committee.
- Implementation guidelines: ISWG-GHG 21 in April 2026, followed closely by MEPC 84; owner, the intersessional working group.
- European phase-in dates: 2025, 2030, 2035, 2040, 2045 and 2050; owner, the operator calling at European ports.
- Review clauses: five years for the global framework, two years for the European cost report; owner, my own calendar.
A slip in the first row moves the second row with it, and the demand case moves behind both.
What this means for you: every row carries an owner I can reach. Also, a date I can diarise, and the file updates the moment one of them moves.
Sources
- International Maritime Organization, IMO net-zero shipping talks to resume in 2026, 17 October 2025.
- International Maritime Organization, The IMO Net-Zero Framework, FAQs, consulted 16 November 2026.
- Global Maritime Forum, A guide to the IMO Net-Zero Framework, consulted 16 November 2026.
- European Commission, Decarbonising maritime transport, FuelEU Maritime, consulted 16 November 2026.
- European Commission, Monitoring of the implementation of the ETS extension to maritime transport, COM(2025) 110 final, 18 March 2025.
- DNV, LNG-fuelled container ships sustain alternative fuel share of global orderbook, consulted 17 November 2026.
Frequently asked questions
Has the IMO Net-Zero Framework been adopted?
No. It was approved at MEPC 83 in April 2025, and the extraordinary session convened from 14 to 17 October 2025 was adjourned for 12 months. The text sits as a new chapter 5 of the draft revised Annex VI: approved, not adopted.
When would the global fuel standard apply to a ship?
Under tacit acceptance, the amendment is deemed accepted at the end of a minimum of ten months unless a formal objection comes from less than one third of the Parties or from Parties representing 50 percent of world tonnage, and entry into force follows six months later. The published scenarios run from adoption later in 2026, with entry into force in 2028 and application in 2029, to a prolonged blockage.
Why does the FuelEU starting date matter outside Europe?
Because FuelEU Maritime applies to ships above 5,000 gross tonnes calling at European ports whatever their flag, and because its incorporation into the EEA agreement was delayed by the notification of 18 December 2025, so a voyage to a Norwegian or Icelandic port has been treated as a voyage to a third country since 1 January 2025.
How do I price a rule that might move again?
By separating the four things that can move and putting each one in a clause with a date: scope, stringency, price and entry into force, with a formula for the case where adoption slips a second time.
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If your file is at pre-FID and you want the four settings stress-tested against your own dates, my contracting and risk management work covers clause drafting, pass-through formulas and watchlist upkeep. I work from your draft documents rather than from a template.
Consequently, I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.