Commercial Banks and Private Credit for SAF Projects

8 min read  ·  Feb 14, 2026  ·  By Alex

saf commercial bank debt

Yes, commercial banks and private credit do lend to sustainable aviation fuel (SAF) projects, but they are selective rather than absent. A lender is looking for contracted offtake that runs the full tenure of the debt, a feedstock position that survives competition, a construction package where risk sits with capable counterparties, and a policy backdrop it can underwrite. The broader context sits in how to finance a SAF project. The practical difference between a declined loan and an approved one is documentation, not ambition.

This article covers what lenders are saying right now, how they test the two equal pillars of offtake and feedstock, how they structure and de-risk a credit, what they expect around construction, demand and policy, and what I tell pre-FID developers in Southeast Asia to assemble.

In short

  • Banks are present, but selective. Capital is available, but it is deployed only to projects with credible demand visibility, supportive policy frameworks, defensible feedstock strategies and realistic cost trajectories.
  • Offtake tenure matters as much as price. Lenders want a contract covering the debt tenor, for example 8 to 14 years, usually at a fixed price with a risk-sharing mechanism.
  • Feedstock contracts are read as hard as offtake. Short contracts and sub-investment grade suppliers are the most common reasons a credit file stalls.
  • Construction risk has to move. Partial wraps from EPC contractors, warranties from equipment makers and insurance are how a credit committee is passed.
  • Documentation beats ambition. The gap between a decline and an approval is the quality of the paper, not the strength of the story.
Facebook
Twitter
LinkedIn

In this article

Commercial banks are selective, not absent

I keep hearing that SAF is simply unfinanceable, and I do not recognise that description of the market. Standard Chartered states plainly that debt financing is available but typically requires de-risked structures: contracted offtake, policy support, blended finance or balance-sheet backing. It also notes that capital is available but selectively deployed, with lenders prioritising projects that show credible demand visibility, supportive policy frameworks, defensible feedstock strategies and realistic cost trajectories.

The caution has a real basis. The World Economic Forum reports that traditional financing sources, such as commercial banks, often see these projects as high risk because of their novelty, extended timelines and reliance on emerging technologies, and that first-of-a-kind facilities can take up to eight years from inception to becoming operational.

Against that, SkyNRG’s DSL-01 facility in Delfzijl reached financial close and started construction after a seven-year development period, becoming the first commercial-scale SAF plant to secure non-recourse project financing, backed by a group of 12 lenders with ING appointed as facility agent.

What this means for you: the credit committee is not deciding whether SAF is a good idea. It is deciding whether your specific project can be documented to a standard that survives its internal risk framework.

Offtake is the pillar lenders test first

I treat offtake as one of two equal pillars, and lenders test it early. The World Economic Forum notes that an offtake contract needs to cover the tenure of debt financing, for example 8 to 14 years, and that lenders generally expect a fixed offtake price set in the contract while the SAF market is nascent, with offtake agreements often carrying a risk-sharing mechanism between producers and off-takers.

The concentration risk is visible. Only three airline groups, Air France-KLM, DHL and IAG, consumed over 1% of SAF in their fuel mix as of 2023, while more than 80% of 2030 demand is driven by 15 airlines. In the SkyNRG transaction, KLM is the primary off-taker and signed a fully cost-plus offtake agreement for 75% of the SAF volumes produced, against a KLM target of 10% SAF usage by 2030, which is 4% higher than the EU mandate. The regulatory floor behind that demand is covered in my note on low carbon fuel mandates.

What this means for you: I would rather show a lender a narrower offtake with a credible tenor, a fixed price and a sensible risk-sharing clause than a larger volume signed on assumptions the committee will dismantle.

Feedstock is the pillar that decides most credits

Feedstock security is one of the largest risks for new projects, and competition for waste feedstocks, including used cooking oil, intensifies across renewable diesel and SAF. HEFA is the most mature and lowest-cost route, which is exactly why the waste pool is contested. For a Southeast Asian HEFA project, the competing claim on the same collected oil is a question I expect in every lender meeting.

RMI’s framing is more than two years old, but its point still governs credit files: investors are weary of short feedstock contracts, which create recontracting risk, and of sub-investment grade suppliers, and feedstock contracts need to be as airtight, maybe even more solid, than offtake. I look for tenure that matches the debt, price mechanics that do not break in a spike, collection and traceability evidence, and suppliers whose own credit standing will not become the project’s problem.

What this means for you: I would rather rebuild the feedstock contract before diligence begins than discover during it that the offtake is sound and the feedstock behind it is not.

How lenders actually de-risk the credit

RMI sets out three financing archetypes: a government loan with a government guarantee, a commercial loan with a government guarantee, and a commercial loan with no government guarantee. It also notes that a US Department of Energy Loan Programs Office review can take 6 to 12 months with approval uncertain, which is the practical reason public routes are rarely a substitute for a bankable commercial file.

For the commercial route, banks’ credit committees are passed by marrying partial-wraps from EPCs, warranties from OEMs and insurance. The wider toolkit described by the World Economic Forum includes 10 financial levers, among them guarantees and insurance instruments to enhance the credit profile, multilateral development bank support, long-term offtake, a tolling model, and green bonds, with no tolling agreements concluded in SAF at the time of writing.

Equity sets the floor: RMI reports that a private equity-backed energy transition fund may want around 15% levered equity internal rate of return for operating projects and over 20% if there is development risk, while venture capitalists may want north of 40% for pre-offtake projects.

What this means for you: I map every point of remaining risk to a named counterparty, an insurance policy or a contract clause before I let a term sheet be written.

Construction and completion risk

Standard Chartered names capital delivery risk directly: the construction, commissioning and operational risks of large industrial developments. Lenders read this section harder than the brochure section, because it is where first-of-a-kind projects fail in practice.

In the SkyNRG deal the package is concrete: Technip Energies is the EPC contractor, the HEFA pathway uses Topsoe’s HydroFlex technology, construction has started after a seven-year development period, and start-up is expected mid-2028. Deutsche Bank confirms the same production start timing. The plant is designed for 100,000 tonnes of SAF per year plus 35,000 tonnes of sustainable by-products, comprising bio-based propane, butane and naphtha, with an expected lifecycle greenhouse gas reduction rising from around 80% to more than 90%.

What this means for you: I want the lender to see a fixed scope, a contractor with a defined completion obligation, equipment warranties and insurance before it sees my production curve.

Demand, policy and the wider funding stack

The World Economic Forum expects demand for SAF to reach 17 million tonnes per annum by 2030, about 4-5% of total jet fuel consumption. Installed SAF capacity globally likely reached 4.4 Mt by end 2024, with 6.9 Mt of capacity expansion planned, yet reaching 2030 demand would require an additional 5.8 Mt of capacity needing FID by 2026, and the industry may require between 19 billion USD and 45 billion USD in CapEx by 2030. SkyNRG’s market outlook puts projected global demand around two million tonnes in 2026, rising to over 15 million tonnes by 2030, after 2024 supplied volumes doubled from the previous year.

That gap is why the stack matters. I look at development finance institutions for guarantees and credit enhancement, and at the feedstock position through my note on SAF feedstock availability in Southeast Asia where the pathway is not HEFA.

What this means for you: I size debt against demand I can evidence today, and I treat policy as a structuring input rather than as the assumption that carries the case.

What I tell developers to assemble before FID

I ask for five things in this order: an offtake draft with tenor, price mechanism and risk-sharing terms; a feedstock contract set with tenure and supplier credit standing addressed; an EPC agreement with completion and liquidated damages positions; an insurance and warranty schedule; and a policy memo that states which mandate or incentive the revenue actually depends on. Then I ask for the equity story behind it, because the offtake agreement has to close alongside the debt, not after it.

From there the sequence to FID is a matter of sequencing the same documents, as set out in how to reach FID on a SAF project.

What this means for you: I would rather spend pre-FID months making one set of documents internally consistent than spend diligence weeks defending contradictions between them.

The Southeast Asia picture

Standard Chartered observes that SAF still trades at a significant premium to conventional jet fuel and that price is the binding constraint. RMI’s conclusion, which is more than two years old, still holds: finance for clean jet fuel will not flow as it does for clean electricity, because there is no 20-year investment grade offtake, more demand for feedstock than supply, and uncertainty on which technology will win. It also frames the scale of the task, with SAF needing to grow from 0.1% of global jet fuel to 10% by 2030, implying 300 SAF plants globally.

Southeast Asia sits inside that arithmetic with a specific advantage and a specific problem. The advantage is proximity to waste oil collection and to growing aviation demand. The problem is that every new HEFA line in the region is bidding for the same used cooking oil and waste tallow, while renewable diesel buyers are bidding too.

What this means for you: I build the Southeast Asian case on a feedstock position I can defend against a competing buyer, and an offtake I can defend against a lender’s own stress case.

Sources

Frequently asked questions

They lend against a pre-FID project once the documentation supports it. The offtake, feedstock, EPC and insurance package has to be in a form a credit committee can test. Lenders are selective rather than absent, and they typically want contracted offtake, policy support, blended finance or balance-sheet backing to de-risk the structure.

It should cover the tenure of debt financing, for example 8 to 14 years. Lenders generally expect a fixed offtake price while the market is nascent, with a risk-sharing mechanism between producer and off-taker.

It is a real concern. HEFA is the most mature and lowest-cost route, and competition for waste feedstocks intensifies across renewable diesel and SAF. Feedstock security is one of the largest risks for new projects, so I treat the feedstock contract as at least as important as the offtake.

Usually documentation: a short feedstock contract, an offtake whose tenor is shorter than the debt, unallocated construction risk, or a policy assumption that cannot be evidenced. In my experience the gap between a declined loan and an approved one is documentation, not ambition.

Want your debt package read before the credit committee?

A short call is usually enough to see where your project stands.

If you are building a SAF project in Southeast Asia and want a clear read on whether your offtake, feedstock position and construction package will survive a bank credit committee, let’s talk through it. I offer project finance support for teams heading into diligence and FID.

I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia

I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.

More about me·Get in touch

Facebook
Twitter
LinkedIn

Related articles