How to Structure a SAF Joint Venture
7 min read · Sep 5, 2025 · By Alex
This page is part of the equity guide for sustainable aviation fuel in Southeast Asia. A SAF joint venture is a shared company that holds the project, and the structure you agree on decides who controls it, who pays for it and who can leave. Settle five things before you sign: the share split, the board and reserved matters, how the budget is funded, what protects a minority partner, and the exit.
In short
- A joint venture lets partners bring different things: capital, a site, technology, feedstock or offtake.
- Real SAF joint ventures in Southeast Asia show very different splits, from 5 to 15 percent for a minority partner to a 51 percent majority.
- Governance has to survive a deadlock and a hard decision: whether to take FID.
- Funding obligations should be tied to an approved budget, with clear consequences if a partner does not pay.
- A minority partner should ask for a board seat or observer, vetoes on key decisions, anti-dilution and tag-along rights.
In this article
Why partners form a SAF joint venture
A SAF project needs more than money. It needs technology, feedstock, offtake, a site and a balance sheet, and one developer rarely has all of them. Haynes Boone notes that joint ventures suit early development, when the certainty needed for a bankable project does not yet exist. The Pengerang biorefinery in Malaysia shows the logic: Petronas hosts it in its Pengerang Integrated Complex, Eni brings the Ecofining technology developed with Honeywell UOP, and Euglena of Japan joined as a minority partner.
What this means for you: write down what each partner brings before you discuss shares. The split should follow the contributions.
Share split and control: three real examples
The World Bank’s joint venture checklist starts with a simple question: a 50:50 deadlock structure, or one partner with a majority? Three SAF projects in the region answer it differently.
- Pengerang, Malaysia: Petronas and Eni are the major shareholders. Euglena invests USD 65 to 195 million for 5 to 15 percent, with an option to move to 15 percent within nine months of closing. The board has two directors from each of Petronas and Enilive and one from Euglena. Equity and shareholder loans go in phases and pro rata.
- BSGF, Thailand: Bangchak, Thanachok Oil Light and BBGI hold 51, 29 and 20 percent of a joint venture for the country’s first used cooking oil SAF plant.
A minority stake with a board seat is a real position. A majority stake carries control and the obligation to fund.
What this means for you: decide who holds the casting vote and what happens when the board splits.
Governance and the FID decision
Freshfields, writing about green hydrogen joint ventures, makes a point that applies to SAF: rules that are too rigid cause repeated deadlock, and rules that are too loose leave direction and funding unclear. It also flags an early choice, whether one governance regime covers the whole life of the project or the early development rules are replaced at FID.
FID itself needs a clause. The parties should define what must be in place first, such as permits, key contracts and secured funding. They should also decide whether a minority partner can be outvoted into a positive FID, and what happens if it votes against or cannot fund its share.
What this means for you: write the conditions for FID into the agreement now, not after the study is finished.
Funding, budgets and cash calls
Equity commitments are usually tied to a development, construction or operating budget that is updated as the project moves. Freshfields lists the questions to settle: the vote needed to approve the budget, whether partners can be bound to extra funding, and what happens if one refuses. Dilution is one possible consequence. The cash call process should be simple enough to pay suppliers on time.
The same firm observes that developers are used to funding early work alone, and that a weak offtake market can keep founding partners paying for longer than planned.
What this means for you: agree a funding plan with milestones, and decide in advance what happens to a partner that does not pay.
What protects a minority partner
Financier Worldwide lists the protections a minority investor in a project joint venture should look for:
- a board seat, or an observer with full rights to attend and receive papers;
- information rights beyond the statutory minimum;
- reserved matters that need the minority’s approval, such as new debt, asset sales or budget changes;
- anti-dilution, so later equity is not issued at a lower price;
- pre-emption on transfers, such as a right of first refusal or first offer;
- lock-up of the controlling partner for three to five years;
- tag-along, to sell on the same terms when the majority sells.
The same article adds that offtakers may prefer to join as minority investors where the offtake is commoditised.
What this means for you: if you are the developer, expect these requests and decide which ones you accept.
Related-party contracts
In a joint venture along the value chain, partners often also sell to the project: EPC, operation and maintenance, feedstock or offtake. These related-party contracts create conflicts, and treating them as reserved matters may not be enough if the conflicted partner can still influence the vote. Conflict provisions can adjust who votes and the quorum.
What this means for you: list every contract a partner will have with the joint venture, and decide who negotiates each one on the project’s side.
Questions to settle before you sign
This is the checklist I use when I read a joint venture term sheet. The questions come from the sources below, and the answers depend on your project.
| Topic | The question |
|---|---|
| Contributions | What does each partner bring, and how is it valued? |
| Split and control | Who holds the majority, and who has the casting vote? |
| Board | Who appoints directors, and what is the quorum? |
| Reserved matters | Which decisions need a partner’s approval: debt, budget, asset sales? |
| Funding | What is the budget, who funds pre-FID work, what if a partner does not pay? |
| FID | What must be in place, and can a minority be outvoted? |
| Related parties | Which partners sell to the project, and who negotiates for it? |
| Exit | Lock-up period, pre-emption, tag-along, deadlock procedure? |
On exit, founding partners are typically locked in until a major milestone such as the start of commercial operations, and that developers often want to sell down later and recycle the money into new projects.
Common mistakes I see repeated
- Agreeing the share split before listing what each partner brings.
- Leaving the FID decision out of the agreement, so a disagreement stops the project.
- Funding obligations that are not tied to an approved budget.
- Letting a partner that also supplies the project negotiate its own contract.
- Forgetting the exit: no lock-up, no pre-emption, no deadlock procedure.
Sources
- Freshfields, Joint venture considerations for green hydrogen projects
- Financier Worldwide, Minority investor protections in project joint ventures
- World Bank PPP Knowledge Lab, Joint venture checklist
- Haynes Boone, Funding renewable energy project developments (May 2024)
- S&P Global, Euglena, Petronas and Eni greenlight a biofuel plant in Malaysia (26 July 2024)
- Bangchak, BSGF, Thailand’s first SAF from used cooking oil
Frequently asked questions
Why form a joint venture for a SAF project?
To combine what one developer rarely has alone: capital, a site, technology, feedstock and offtake. Haynes Boone notes that joint ventures suit early development, before a project is bankable.
What equity split do SAF joint ventures use?
It varies. At Pengerang in Malaysia, Euglena invests for 5 to 15 percent beside two major shareholders. At BSGF in Thailand, three partners hold 51, 29 and 20 percent.
What should a minority partner ask for?
A board seat or observer, information rights, vetoes on key decisions, anti-dilution, pre-emption on transfers, a lock-up for the controlling partner and tag-along rights.
What happens if a partner cannot fund its share?
It depends on the agreement. Freshfields lists the options to settle in advance, including dilution. Tie funding obligations to an approved budget and agree a simple cash call process.
Negotiating a SAF joint venture?
A short call is usually enough to see where your project stands.
I can help you map the partners you need and prepare the first conversations. See how I work on strategic partnerships.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.