My starting point in a sustainable aviation fuel file is the repayment schedule, not the fuel market. The offtake agreement is the contract under which a buyer commits to take the plant’s output. It needs to cover the tenure of debt financing, for example 8 to 14 years. At least 70 to 80 percent of annual capacity should sit under contract. Also, some lenders requiring 100 percent of the SAF produced for the full loan tenor. The buyer side offers shorter: buyers discuss supply 3 to 5 years out for a tenure of 5 to 10 years. In addition, airlines hedge only two to three years, so I negotiate the gap.

That is why I read saf offtake tenor lender requirements off the debt first. In addition, the wider route into the subject runs through how to secure SAF offtake agreements.

This note stays narrow: tenor and coverage on a pre-FID SAF project, read from the lender’s side of the table. I take the published figures as given and test every clause I negotiate against them.

In short

  • Debt first: The offtake contract needs to cover the tenure of debt financing, for example 8 to 14 years.
  • Coverage: Investors often require at least 70 to 80 percent of annual capacity covered by offtake agreements.
  • Buyer offer: buyers discuss long-term supply 3 to 5 years out with a tenure of 5 to 10 years.
  • Hedge ceiling: Airlines do not typically forward-hedge their fuel requirements beyond two to three years.
  • Bridge: I close the gap with several offtakers, an aggregator of sufficient creditworthiness, or a shorter drawdown profile.
Facebook
Twitter
LinkedIn

In this article

Tenor is read from the debt, not from the market

Tenor is how long the loan runs before repayment, and loan tenor is the number I start from. The published definition is simple: the offtake contract needs to cover the tenure of debt financing, for example 8 to 14 years (World Economic Forum, February 2025). Also, the same source sets the coverage bar. Investors often require offtake agreements to cover at least 70 to 80 percent of annual capacity. In addition, some lenders require 100 percent of the SAF produced to have reliable offtake covering the full loan tenor. I read offtake coverage as the share of output a committed buyer has agreed to take.

On the seller side, offtake agreements provide fixed or contractually adjusted prices for as long as ten years or more into the future. The tenor I negotiate is therefore a reading of the repayment schedule, not a habit of the fuel market.

What this means for you: I write loan tenor and required coverage into the model first, then look for a contract that matches both.

What the lenders write down

To be financeable, an offtake agreement must provide stable, predictable revenue over the life of the debt and involve a creditworthy offtaker. It must also mitigate the project’s material operating and market risks. Also, it must avoid provisions that block lenders from exercising remedies if the project defaults (Bracewell, 10 September 2026). I take a creditworthy offtaker to mean a buyer whose balance sheet, guarantee or letter of credit can carry the payment obligation across the whole tenor. In power projects the term can range from approximately 5 to 25 years depending on the project and financing requirements. Therefore, the range follows the financing, not the product.

Every project finance lender scrutinizes offtake agreements because lenders rely on them to provide the financial assurances needed to validate the cash flow forecasts that form the basis for loan repayment. Drafting standards for the wider category sit at offtake agreement structures.

What this means for you: I treat those four tests as the floor of my credit paper, and I answer the tenor question there before I open a negotiation.

What the buyer side offers

Typically the airline negotiates a long-term offtake agreement with a SAF producer investing in a new or additional production facility. The supply refers to 3 to 5 years out. Also, a longer tenure of 5 to 10 years (IATA, 12 May 2024). Near-term contracts run the other way: one-off or annual deals priced off a conventional aviation fuel index or a SAF index, built for a fuel budget rather than a debt schedule. With long-term sales contracts the offtaker agrees to take the contractually agreed-upon quantities. Prices then rest on market prices at delivery or an agreed formula or index. Certain contractual floor prices still apply (Global Trade Funding, 13 March 2022).

The difference between a 5 to 10 year tenure and an 8 to 14 year loan is the number I carry into every tenor discussion. Price formation context is set out at sustainable aviation fuel price.

What this means for you: I do not ask the buyer to match the loan on day one. I plan how to fill the difference between those two horizons.

The two-to-three-year wall

Airlines, the end-users of SAF, do not typically forward-hedge their fuel requirements beyond two to three years. This makes a long-term, fixed-price offtake agreement that project finance lenders typically require difficult to secure for a SAF project. Even a 10 year airline purchase commitment would leave a large, uncontracted tail for a long-term debt tenor of perhaps 20 to 25 years. An uncontracted tail is the part of future production that no buyer has committed to take. In addition, it is where a tenor proposal usually dies. The published bridge is to interpose an intermediary, an aggregator of sufficient creditworthiness, between the SAF producer selling long term.

Also, the end-customer buying short or mid-term, and larger projects may enter several offtake arrangements with different buyers to spread the credit risk. Reaching a final investment decision is covered at the SAF project timeline and FID.

What this means for you: before I quote a tenor, I size the tail and name who will stand behind it, because that is the question the credit paper asks first.

Policy holds the horizon open

In Europe, under ReFuelEU Aviation, airlines pay up to five times more than the price of conventional jet fuel. They also pay double the market price of SAF, without guarantee of supply or consistent documentation. In addition, the UK SAF mandate has triggered price spikes leaving airlines to absorb the burden. The demand my tenor rests on comes from policy. In 2025 SAF output should reach 1.9 million tonnes, double the 1 Mt produced in 2024. That volume represents only 0.6% of total jet fuel consumption, increasing to 0.8% the following year, with production projected to reach 2.4 Mt in 2026. Mandates are what let me ask a buyer for a longer commitment, because the obligation survives the hedge cycle.

However, the mandate also carries the price risk I have to place inside the contract. The mandate landscape itself sits at low carbon fuel mandates.

What this means for you: I can argue for a longer tenor where a mandate keeps demand in place. However, I write the price consequences of that mandate into the contract rather than into the forecast.

What makes a tenor credible

The offtaker’s financial quality can matter as much as the promised volume. A practical credit review asks who the actual obligor is. It asks what support exists: a guarantee, letter of credit, security package or reserve account. It also asks what happens on downgrade or distress, and whether the lender can capture revenue (Mayo Law, consulted 15 November 2026). Also, a well-drafted agreement distinguishes between signing date, effective date, commercial operation date and delivery start date. The parties must open conditions precedent such as financing closing, permits, board approval and completion testing before the contract becomes fully operative. Performance assurance, also called credit support or security, is a central negotiated issue.

The parties must determine who posts collateral, how much, in what form, and when they can draw on it. I accept a long tenor only when the contract records those elements. This happens because a tenor without an obligor behind it is a forecast. Bankability tests sit at bankability.

What this means for you: I sign a long tenor only once the obligor, the security. Also, the gates are on paper, not before.

Where a tenor breaks

Lenders will be reluctant to take significant merchant exposure for a new sector. In addition, any limited merchant offtake strategy will need detailed marketing analysis and considered implications for debt-sizing (Dentons). Merchant financings remain possible but far less common. In these deals a project sells output directly into the market without a locked-up contract. Revenue volatility has historically burned lenders. In addition, some financings permit a limited merchant tail that remains the exception rather than the rule. Termination rights need symmetry: one-sided termination for convenience is often a financing problem because it makes projected revenue less reliable. Most offtake agreements also carry a force majeure clause that allows either party to modify or cancel the agreement if something beyond anyone’s control puts undue hardship on either party.

The same tension applies to broad rejection rights and to force majeure clauses that read well but do not allocate actual operational risks.

What this means for you: I check merchant exposure, termination symmetry and excuse clauses before I argue about price. This happens because each of them shortens the tenor a lender will fund.

How I would run this if it were my file

I write four lines: debt tenor, coverage percentage, buyer tenure on offer, and the size of the uncontracted tail. Then I test them against the published floor: at least 70 to 80 percent of annual capacity covered. The contract must also cover the tenure of debt financing, for example 8 to 14 years (World Economic Forum, February 2025). Also, Then I ask what the buyer will actually sign. Buyers discuss supply 3 to 5 years out for a 5 to 10 year tenure. Hedging stops at two to three years. Then I price the gap: several offtakers, an aggregator of sufficient creditworthiness, or a shorter drawdown profile.

If the four lines do not match, I do not adjust the debt model, I adjust the contract structure. My tenor is then a number with a repayment schedule behind it.

What this means for you: run the same four lines on your file before you pick a number. Let the repayment schedule choose the tenor rather than the other way round.

Sources

Frequently asked questions

The contract needs to cover the tenure of debt financing, for example 8 to 14 years (World Economic Forum, February 2025), while the offtake on the buyer side is often discussed for a supply of 3 to 5 years and a tenure of 5 to 10 years (IATA, 12 May 2024). The practical answer is therefore the debt schedule plus the coverage the lender requires, and I start from the repayment profile rather than from what the product seems to fetch.

Investors often require at least 70 to 80 percent of annual capacity to be covered by offtake agreements, and some lenders require 100 percent of the SAF produced to have reliable offtake covering the full loan tenor (World Economic Forum, February 2025). So 70 to 80 percent is a floor many investors apply, not a universal answer, and I check which test my lender applies before I size the debt.

Airlines do not typically forward-hedge their fuel requirements beyond two to three years, and even a 10 year airline purchase commitment would leave a large, uncontracted tail for a long-term debt tenor of perhaps 20 to 25 years (Dentons, 15 April 2025). The hedge cycle is shorter than the loan, so a single airline cannot carry the whole tenor on its own.

The published answers are an intermediary of sufficient creditworthiness between the producer and the end-customer, several offtake arrangements with different buyers to spread credit risk, or a shorter tenor paired with marketing analysis and explicit implications for debt-sizing (Dentons, 15 April 2025). I choose among those before I reopen price.

Not sure your project would survive a credit conversation?

A short call is usually enough to see where your project stands.

If my reading of your tenor and coverage differs from the one in your credit paper, that difference is the whole conversation: investor introductions is where I put a prepared file in front of people who ask exactly these questions.

I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia

I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.