We Connect Asia

WtE

Waste-to-Energy FID Readiness: The 8 Checks I Run Before I Call the FID

10 min read  ·  Dec 28, 2025  ·  By Alex

wte fid readiness checklist

I keep one short checklist before a developer in the waste-to-energy industry asks whether the project is ready to commit capital. FID, the final investment decision, is the moment the owners commit the capital. Also, I call a waste-to-energy project ready for it when eight checks clear. Also, my waste to energy fid checklist clears only when several conditions hold. In addition, the plant has the waste committed in writing at the volume it needs. Moreover, both revenue lines carry signatures or a fixed price. For example, the team measures calorific value, the heat released per tonne, across the seasons. Permits and state commitments sit on paper. Specifically, the model survives the lender’s downside. In fact, every risk has a named holder. Therefore, the five core documents exist, and the procurement calendar carries a published award date.

Also, the 2014 study from Indonesia required about 15 percent return from the two revenue lines together. Local authorities offered about 9-10 USD a tonne, while the industry needed about 25-30 USD.

I run the eight checks in a fixed order because each one rests on the one before it. Revenue comes first because no model survives without it. Then come the waste, the paper, the downside case, the risk holders, the documents, and finally the calendar.

In short

  • Revenue: both income lines are signed or fixed before any model is run.
  • Waste: we measure volumes and heating quality across the seasons, not from one sample.
  • Permits: construction, environmental and power purchase paperwork carry published deadlines and a named payer.
  • Model: the downside case still pays when one plant underdelivers.
  • Documents: five items on file, with a published award date on the procurement calendar.
Facebook
Twitter
LinkedIn

In this article

What I mean when I say a project is ready

I use one definition of readiness: nothing material still moves when the project goes to approval today. The Ramboll interview of January 2025 describes a bankable solution built from the early pre-feasibility stage. Also, it needs three things together, a proven technical solution, an optimal risk allocation. Also, the payment mechanism must be clear. It covers the gate fee for each tonne and the feed-in tariff for each unit of electricity.

Both public and private money have to join, and private investment must develop the projects. Contract form matters. Governments in the region pick Design, Build, Own, Operate and Transfer. That form keeps one entity in front of them. Split packages are harder to finance because investors prefer one counterparty. The public sector has to guarantee the waste stream.

What this means for you: I do not build a model until those three elements sit in writing. A project that misses one of them has not reached readiness; it is only a plan.

Check one: the revenue, signed before the model

I will not build a revenue model on an assumption. The 2014 Carbon Trust and IESR study of Indonesia names two revenue lines, the tipping fee and the sale of electricity under a feed-in tariff. It reports that developers struggled to assemble a package giving an internal rate of return of about 15 percent, the level both the industry. Also, the state treated as acceptable.

Local authorities offered about 9-10 USD per tonne, while the industry stated a need of 25-30 USD. One tender in 2012 ran for about 4 years on a 20-year contract. The tender expected a tipping fee as low as 9.76 USD a tonne, worth 316 billion roupies, 26 million USD. Illegal dumping lets operators dump waste very cheaply and erodes the fee a plant can charge. Researchers built the study on 22 interviews between November 2013 and March 2014.

What this means for you: I ask for both lines signed, or fixed by a published instrument, before I run the project finance case, because a gap of 9-10 against 25-30 cannot be closed by arithmetic.

Check two: the waste, measured not assumed

Volume and quality decide whether a plant makes economic sense. The Infrastructure Asia overview of waste management in Asia puts 500 tonnes per day at the point where an incineration plant starts to work economically. It says installations as small as 50 tonnes per day are harder to finance. Its rule of thumb for grate combustion is about 6 MJ/kg, the calorific value of the delivered waste. Municipal solid waste in the region often sits below it. Refuse-derived fuel, waste processed into a graded solid fuel, needs at least 14 MJ/kg for a cement plant buyer.

In a public-private partnership the private developer must be sure of daily deliveries. Developers will not carry that risk with the capital at stake. Singapore’s fifth plant tender in 2001 drew a single bid. The authority asked the developer to carry finance, design, operational and demand risk. The 2005 re-tender adopted take-or-pay. Under it, the government buys 100 percent of the incineration capacity or pays a penalty. Authorities awarded it in 2005, and it started in 2009 at 800 tonnes a day and about 22 MW.

What this means for you: I want the waste measured before the process design is fixed, because the design only works inside the measured range.

Check three: permits and state commitments on paper

Paper speed is a check, not a formality. The August 2026 HFW briefing on Indonesia’s new regulation sets out Perpres 109/2025, signed on 10 October 2025. National eligibility requires 1,000 tonnes of waste a day throughout operations. A simplified tariff of 0.20 USD/kWh applies to a 30-year power purchase agreement. The state electricity company must sign it within 10 working days of the pre-construction permits. The tariff allows no negotiation and no escalation. Environmental licences issue within two months of a complete file, and the rule grants them if the authority stays silent.

BPI Danantara coordinates the work and expects financing in part from about IDR 50 trillion of Patriot Bond. A first public-private partnership reached commercial close in July 2026, before ground breaking. Commercial close means signed contracts and available funding. The plant runs at about 2,131 tonnes a day and 40.79 MW. About 200 entities had expressed interest and 85 qualified. Two earlier commercial plants ran under Perpres 35/2018, which named twelve cities. Also, they produced different results. That is why an economical project, a reliable waste supply and a proper risk allocation still matter.

What this means for you: I date every permit and signature on one calendar and test it against an independent technical review before any capital is committed.

Check four: the model survives the downside

A structure can pay the lender even when one plant underperforms, and that is what I look for. The October 2015 Asian Development Bank case story groups individual projects into one transaction to reach the bank’s minimum loan size and cut transaction costs. A single holding company borrows and pays even if one project defaults, under the full and irrevocable guarantee of the sponsor. A loan of 100 million USD sat beside a loan of 100 million USD from international banks.

Three clauses carried the risk. The concession was exclusive for at least 25 years. The contract guaranteed the contractor against municipal failure to deliver the minimum waste. A tipping fee formed the third clause. On average one third of revenue came from tipping fees and two thirds from the tariff. The portfolio added 6,200 tons of capacity, 132 MW and 630 GWh a year. Work started in May 2009 and finished in December 2013. One 36 MW plant running on 2,000 tons produced 190 GWh.

What this means for you: I ask for the downside case with the full financial model beside it, and I check that one weak plant does not break the payment chain.

Check five: every risk has a named holder

Every risk needs a name beside it before I sign anything. The barriers recorded in the 2014 study fall into a few groups. Financing costs ran high because the market looks risky, and the local technology had not proved itself. Public policy history was inconsistent, and procurement procedures stayed opaque. Developers doubted the solidity of contracts with the state electricity company and local governments. No guarantee mechanism covered waste-to-energy at that point.

The 2026 briefing adds three open points. The parties have not settled contract and operating terms. Acceptance criteria, fuel specifications and trial runs remain open. Risk allocation for construction and operations should follow the feedstock and technology risks. Importing profiles from other markets does not work. The January 2025 interview asks for a waste characterisation study. It must cover at least one year across the wet and dry seasons.

What this means for you: I write that schedule myself when no one else has, and I place it beside the bankability test the lender will apply first.

Check six: the five documents I ask for first

I ask for five items, in this order. First, the waste supply commitment carries the authority’s signature. The 1,000 tonnes a day commitment of October 2025 is the clearest current example. Second, the payment mechanism needs a named payer, a price and a duration. The at least 25 years exclusivity of the 2015 structure is the standard I compare against. Third, the risk allocation schedule showing who carries quality, availability and demand. Fourth, the procurement calendar with a published award date. Fifth, the environmental and community record with monitoring commitments.

I keep the list short on purpose. Each item is a document a lender can read without a phone call. Each one traces back to a published instrument rather than a presentation. None of them depends on a forecast.

What this means for you: I stop the review whenever one of the five fails to appear. The 500 tonnes per day economic floor means nothing without a signature behind the tonnage.

How I would run the readiness review

  • 2014: local authorities offered about 9-10 USD a tonne against a stated need of about 25-30 USD. The return threshold stood at about 15 percent.
  • 2015: a loan of 100 million USD beside a loan of 100 million USD. One third of revenue came from tipping fees against two thirds from the tariff.
  • October 2025: 0.20 USD/kWh for 30 years. The power purchase agreement requires a signature within 10 working days of the permits.
  • 2026: commercial close before ground breaking in July at about 2,131 tonnes a day.

I read those four rows together rather than one at a time. They show what a lender will test in the same order I test it. None of them is a forecast.

What this means for you: I run the review as four dated questions. One: is the revenue enough? Two: is the waste measured? Three: is the calendar public? Four: does the downside still pay? I book the FID meeting only when all four answers are yes.

Sources

Frequently asked questions

It is the moment the owners commit the capital and the process stops being reversible, which is why the revenue lines, the waste commitment and the permits have to be signed first. Until then the plan can still change without penalty. In the 2014 study the two revenue lines together had to reach about 15 percent before the package was acceptable to either side.

The waste supply commitment, because everything else rests on it. The 2015 structure made the contract guarantee the contractor against municipal failure to deliver the minimum waste, with an exclusive concession of at least 25 years, and the tipping fee sat beside it as the third clause. I would not start the model without that signature.

Revenue that does not clear and waste that is not measured. Local authorities offered about 9-10 USD a tonne against a stated need of about 25-30 USD, and plants below about 500 tonnes per day are harder to make economic. When the two miss each other, the project stops in the same place every time.

In the records I read, one tender ran about 4 years on a 20-year contract, while a regulation signed on 10 October 2025 compresses the power purchase signature to 10 working days and the environmental licences to two months. The calendar moves with the framework, not with the developer.

Not sure your project would survive a credit conversation?

A short call is usually enough to see where your project stands.

If you are pre-FID and want a second pair of eyes on the checklist, project finance support is where I start. I read your documents against the eight checks and hand back a dated list of what is still open.

My work covers neither investment advice nor investment arrangement. I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia

I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.

More about me·Get in touch

Facebook
Twitter
LinkedIn

Related articles