Methanol Project FID Readiness Checklist: What I Check Before Anyone Dates the Decision

10 min read  ·  Jan 2, 2026  ·  By Alex

methanol fid readiness checklist

Before anyone names a date on the final investment decision, the FID, I check three proofs: equity in the vehicle, an offtake, the contract that sells the plant’s output, past the loan, and public cover for the first unit. Around 30 percent of equity sits upfront in the special purpose vehicle, the company built to hold the plant, which GIZ and NIRAS recommended in 2024 as the share that helps secure loan guarantees, financing and investment funds. The offtake must outlive the loan, and the European Investment Bank recorded in May 2024 that buyers stop at two to three years while the construction loan is considerably longer. For the third proof this methanol project fid checklist asks who covers the first-of-a-kind tranche, the first unit of its type ever built: the International Finance Corporation took in December 2023 the right to invest a pro rata share, in proportion to the equity it holds, of the project’s common equity and to lead the financing of at least 50 percent of the project’s debt. The green methanol industry page carries the same picture.

None of the three proofs is a forecast. Each one is a document a lender can open, date and test against the model, and I put all three on paper before anyone proposes a calendar.

In short

  • Equity: about 30 percent upfront in the special purpose vehicle, the share GIZ and NIRAS recommended in 2024 to help secure loan guarantees, financing and investment funds.
  • Offtake: a contract that outlives the loan, because the European Investment Bank recorded in May 2024 that buyers stop at two to three years.
  • Cost: the whole gap in the model, 1.2 to 12 times fossil methanol cost, per BloombergNEF on 18 June 2024.
  • Protection: a bankable long-term offtake, a price floor or a contract for difference, per the Global Biofuels Alliance in January 2026.
  • Public cover: a development finance institution holding equity and leading the debt in the first unit, as Transition Industries and the International Finance Corporation announced in December 2023.
Facebook
Twitter
LinkedIn

In this article

What the checklist actually tests

Three proofs, tested in order, and each one has to be a document rather than an opinion. The Global Biofuels Alliance recorded in January 2026 that all biofuels are policy-anchored assets: mandates, incentives, subsidies and sustainability frameworks supply the revenue visibility that bankability requires. The same source recorded in January 2026 that biofuels account for less than 2 percent of global fuel consumption at nearly 198 Mtpa, that demand should grow 2 to 2.5 times by 2035, and that cumulative investment should reach 420 to 500 billion USD in the base case by 2035. A methanol file sits against that backdrop, so I test whether the revenue story is anchored in an instrument someone has already signed rather than announced. I do not treat a published target as proof; I treat a signed instrument, a dated price and a named buyer as proof.

What this means for you: write the three proofs as dated lines rather than as narrative, and the missing one becomes obvious within a day.

Test one: the equity is already in the vehicle

GIZ and NIRAS recorded in 2024 that a pre-feasibility case recommends a relatively high equity share by the project partners, around 30 percent, available upfront in the special purpose vehicle, to help secure loan guarantees, financing and investment funds. The same source recorded in 2024 that the final percentage is set at later stages against lenders’ requirements, financial models and covenants, the conditions written into the loan, and that the weighted average cost of capital is held at 11 percent in the reference scenario. It recorded in 2024 that the design phase already looks for finance, partners and offtakers, with the vehicle holding the grid, water and transport agreements, the local permissions and the insurance contracts. The Global Biofuels Alliance recorded in January 2026 that lenders and investors require higher equity buffers, the cushion of sponsor money that absorbs early losses, shorter debt tenors and stronger downside protection unless policy-driven revenue risks are mitigated.

The sustainable aviation fuel final investment decision page asks the same question at the same stage.

What this means for you: until the 30 percent is visible in the vehicle, any date is a wish rather than a milestone.

Test two: the offtake reaches past the loan

The European Investment Bank recorded in May 2024, on a consultation of 34 companies selected from a longlist of more than 100, that promoters struggle to secure offtake volumes at prices that reassure lenders. It recorded in May 2024 that buyers hesitate to commit beyond two to three years while the construction loan, and the senior debt behind it, the main project borrowing, runs considerably longer. The same report recorded in May 2024 that buyers are used to trading on standardised spot markets and expect production costs to fall with scale, and that higher inflation, interest rates and electricity prices had already reduced project returns. It also recorded in May 2024 that even with long-term agreements some early-stage buyers such as airlines are not considered sufficiently creditworthy, meaning able in a lender’s view to carry the repayment.

The e-methanol project finance page applies the same test.

What this means for you: an offtake shorter than the loan sells comfort to the sponsor, and the lender reads the loan first.

Test three: the cost gap is in the model

IRENA and the Methanol Institute recorded in 2021 that fossil methanol costs 100 to 250 USD a tonne, against 320 to 770 USD a tonne for bio-methanol with feedstock up to 6 USD per gigajoule and 220 to 560 USD a tonne with process improvements. The same source recorded in 2021 that e-methanol runs at 800 to 1600 USD a tonne with carbon dioxide from bioenergy with carbon capture at 10 to 50 USD a tonne, and 1200 to 2400 USD a tonne with carbon dioxide from direct air capture at 300 to 600 USD a tonne. BloombergNEF and the Climate Technology Coalition recorded on 18 June 2024 that low-carbon methanol production costs run 1.2 to 12 times those of fossil methanol depending on the feedstock, and that above 500 USD a tonne shipping companies may find it cheaper to pay the carbon price on their own emissions until 2030.

The infrastructure project finance page shows where that gap sits in the stack.

What this means for you: the model has to carry the whole range, because the lender will price the top of it.

Test four: the contract that carries the decision

The Global Biofuels Alliance recorded in January 2026 that long-term offtake contracts with creditworthy counterparties fix volume, price and tenor and form the foundation of project bankability. It recorded in January 2026 that lenders and investors hold to tighter terms only where policy-driven revenue risks are mitigated through bankable long-term offtake agreements, price floors, contracts for difference, which pay the gap between a fixed price and the market price, or equivalent public support. The same source recorded in January 2026 that corporate offtakers increasingly take equity linked to long-term purchase agreements, which anchors demand and improves the bankability of capital-intensive projects. I ask who signs, for how long, at what price, and what happens if that price moves.

The page on securing offtake agreements is where that contract is written.

What this means for you: the date moves when counterparty, volume, price and tenor are all named on paper, and not before.

Test five: public cover for the first unit

Transition Industries and the International Finance Corporation announced at COP 28 in December 2023 a joint project development agreement for Pacifico Mexinol near Topolobampo, Sinaloa: a 6,145 MT per day facility expected to produce about 300,000 MT of green methanol from captured carbon and green hydrogen and 1.8 million MT of blue methanol a year. The IFC shares part of the development costs and has the right to invest a pro rata percentage, in proportion to its holding, of the project’s common equity and to lead the financing of at least 50 percent of the project’s debt. The December 2023 announcement expected an FID in 2024 and commercial operations in late 2027, both announced expectations rather than achieved milestones, and quoted the IFC on at least 40 percent of global methanol production coming from coal. The Global Biofuels Alliance recorded in January 2026 that emerging pathways including biomethanol face structural financing gaps, so concessional capital, guarantees and risk-sharing platforms carry a first unit to bankable scale.

The development finance institutions page lists who provides that cover.

What this means for you: for a first unit, public cover is evidence you can show, not a fallback you hope for.

What I would test before I recommend a date

I ask five questions in writing.

Is the equity of around 30 percent already visible in the vehicle, per GIZ and NIRAS in 2024?

Does the offtake outlive the loan, when the European Investment Bank recorded in May 2024 that buyers stop at two to three years?

Is the offtaker creditworthy enough for the lender, when that same May 2024 report found early-stage buyers such as airlines insufficiently so?

Which public instrument covers the first-of-a-kind tranche, when the International Finance Corporation took a pro rata equity right and at least 50 percent of the debt lead in December 2023?

Is announced capacity separated from sold volume: the Methanol Institute recorded in 2025 that 400,000 to 500,000 tons of renewable product were sold in 2024 against 94 million metric tons of total supply, while more than 200 announced projects carrying 45.8 million metric tons of potential capacity by 2030 may see only 20 to 40 percent move forward, which is 7 to 14 million metric tons in the next five years.

What this means for you: five clear answers give you a date to defend, and four give you a delay you can explain.

How I would run the checklist if it were my own file

I keep five dated rows, and each row carries the publisher that printed it.

The equity row carries the 30 percent upfront share and the 11 percent weighted average cost of capital recorded by GIZ and NIRAS in 2024.

The revenue row carries the two to three years buyer horizon recorded by the European Investment Bank in May 2024.

The cost row carries the 1.2 to 12 times multiple and the 500 USD a tonne threshold recorded by BloombergNEF on 18 June 2024, against the 320 to 770 USD a tonne bio-methanol range recorded by IRENA and the Methanol Institute in 2021.

The public row carries the pro rata equity right and the at least 50 percent debt lead announced by Transition Industries and the International Finance Corporation in December 2023.

The volume row carries the 400,000 to 500,000 tons sold against 94 million metric tons of supply, recorded by the Methanol Institute in 2025.

A row without a publisher and a date goes back into the file.

What this means for you: the checklist is finished when every number in it can be traced to the source that printed it.

Sources

Frequently asked questions

It is the set of proofs a lender tests before a date is set: equity already available in the special purpose vehicle, an offtake long enough to outlive the loan, a cost gap the model carries, and public cover for the first unit. The Global Biofuels Alliance recorded in January 2026 that long-term offtake contracts with creditworthy counterparties form the foundation of project bankability, and GIZ and NIRAS recorded in 2024 how the equity share is fixed against lenders’ requirements, financial models and covenants.

Around 30 percent available upfront in the special purpose vehicle is the published recommendation of GIZ and NIRAS in 2024, because that money helps secure loan guarantees, financing and investment funds. The final percentage is set at later stages against lenders’ requirements, financial models and covenants, so the number I check is the one already visible in the vehicle, not the one promised for a later round.

Because it is the repayment source. The European Investment Bank recorded in May 2024 that buyers hesitate beyond two to three years while the construction loan is considerably longer, and that promoters struggle to secure offtake volumes at prices that reassure lenders. The gap between those two horizons is the gap the equity has to cover.

It counts when it carries risk the private side refuses. The International Finance Corporation took in December 2023 the right to invest a pro rata share of the project’s common equity and to lead the financing of at least 50 percent of the project’s debt, and the Global Biofuels Alliance listed in January 2026 concessional capital, guarantees and risk-sharing platforms as what moves emerging pathways to bankable scale.

Not sure your project would survive a credit conversation?

A short call is usually enough to see where your project stands.

If you want a second reading before the file goes to a lender, I run these five rows against your equity, revenue, cost, public and volume evidence and tell you which one is missing. Brief me through the project finance service page.

I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia