Power Supply Contracts for PtL Projects: What Lenders Will Sign

10 min read  ·  Feb 2, 2026  ·  By Alex

ptl power supply contracts

What a lender will sign is a power supply firm enough to hold a load factor. This means the share of hours the plant runs at rated output. At 50 USD per MWh in the December 2023 study of e-fuels, the power price alone contributes 25 to 35 USD per gigajoule of fuel. That holds before any investment or consumable. The levelised cost is the investment spread over the fuel actually made. It starts climbing very quickly once the electrolyser drops below a 40 percent load factor. That unit splits water into hydrogen with electricity. Both figures are dated to the same study. The contract, not the equipment brochure, decides whether those numbers hold.

This is why I treat a PtL power purchase agreement as the primary credit document of a power-to-liquid plant. That contract is where the plant buys its electricity, and the plant itself converts renewable electricity and captured CO2 into a liquid fuel. The wider route sits in the power-to-liquid explainer.

How I test a PtL power purchase agreement

I test four things here. Is the supply firm enough to hold the hours, and what floor does the power price put on the fuel? A third test is whether the electricity can be counted in the molecule. The last question is which of those facts travel into the financing. Each one is settled in the contract, before the plant is built.

In short

  • Firmness: I buy hours rather than price spikes, because below 40 percent load factor the levelised cost climbs very quickly, in December 2023 modelling.
  • Cost floor: At 50 USD per MWh the power price alone adds 25 to 35 USD per gigajoule of fuel, in December 2023.
  • Blend: The worked example minimises cost at a 40 to 50 percent solar share with 6 percent annual curtailment, in December 2023.
  • Equipment: Minimum load is 10 percent for modern atmospheric alkaline, in February 2026, so the plant can turn down with the supply.
  • Capital: The cost of capital can reach 15 percent in emerging economies, in 2025, three times the level of advanced economies.
Facebook
Twitter
LinkedIn

In this article

What the contract has to prove

A lender reads one question first: does the power supply hold the hours the plant needs? At 50 USD per MWh in December 2023 the power price alone contributes 25 to 35 USD per gigajoule of fuel before any investment or consumable. Below a 40 percent load factor, the levelised cost starts climbing very quickly. Those two numbers, and the contract that protects them, are the entire test.

The vocabulary I work from:

  • A power purchase agreement is the contract under which the plant buys electricity.
  • The load factor is the share of hours the plant runs at rated output.
  • The levelised cost spreads the investment over the fuel actually made.
  • An electrolyser is the unit that splits water into hydrogen using electricity.
  • Curtailment is power that is available but not taken.
  • Full load hours are the yearly equivalent hours at rated output.
  • A hybrid supply mixes grid power, the plant’s own renewables and storage.

What this means for you: I do not start from the equipment brochure or the tariff leaflet. I start from the supply document, because every figure above only holds if the hours behind it are contracted.

The floor the contract sets

The 2023 e-fuels report sets the floor. At 50 USD per MWh the power price alone contributes 25 to 35 USD per gigajoule of fuel. In oil terms that is 1,000 to 1,500 USD per tonne of oil equivalent. That holds before any investment or consumable, in December 2023. The annual availability of those hours drives the load factor. It also decides how much of the plant investment sits in every gigajoule. Therefore, assuming a constant average price, the levelised cost starts increasing very quickly once the load factor drops below 40 percent, in December 2023.

The worked example minimises cost at a 40 to 50 percent share of solar photovoltaic capacity. Annual curtailment falls to 6 percent, against 18 percent on solar alone and 23 percent on wind alone, in December 2023. The modelled assumptions pair 30 and 50 USD per MWh with 800 and 2,000 USD per kilowatt of electrolyser. They also hold a 5 percent cost of capital over a 25 year economic life. Operating cost beyond electricity runs at 1.5 percent of capital for electrolysis and 3 percent for synthesis each year, in the same December 2023 model.

What this means for you: these are the scenarios the feasibility and financial model has to carry, and I reject any model that assumes more hours than the contract delivers.

The load behind the contract

The World Bank survey of February 2026 starts from a simple premise. Electricity is the most significant operating cost and its price is highly site dependent. Therefore, the technology choice has to follow the local energy profile. Operational flexibility lets the plant take low cost power. Therefore, developers use hybrid designs and battery storage. Also, a grid connected project on power purchase agreements faces a different choice from a project running its own renewable assets.

  • Efficiency: 51 to 56 kWh per kilogram for alkaline against 53 to 56 for PEM and 35 to 42 for solid oxide, in February 2026.
  • Durability and minimum load: 60,000 to 90,000 hours for alkaline against 40,000 to 60,000 for PEM. Minimum load is 10 percent for modern atmospheric alkaline, 30 percent for pressurised alkaline, 10 percent for PEM and 50 percent for solid oxide, in February 2026.
  • Modules: typically 5 MW to 100 MW, with utility scale plants cycling stacks individually so units can stop when power is expensive, in February 2026.

What this means for you: I check the green hydrogen route behind the plant before I check the tariff, because the electrolyser that suits the local energy profile is the one these hours will actually support.

What the power price does to the financing

The five key questions section of the 2025 review prices the capital. It can reach 15 percent in emerging economies, three times the level of advanced economies. Only 0.5 percent of announced projects there have secured committed investment, against 9 percent worldwide, in 2025. The stack itself is only 15 to 20 percent of the installed investment, in 2025. Therefore, a power contract that fails shows up across the whole balance sheet rather than in the equipment line.

IRENA’s cost reduction study from 2020 moves four variables together. Electricity falls from 53 to 20 USD per MWh, full load hours rise from 3,200 to 4,200 and the cost of capital falls from 10 to 6 percent. Efficiency rises from 65 to 76 percent, in 2020. On that study’s own figures green hydrogen remains two to three times more expensive to produce than blue hydrogen, in 2020.

What this means for you: the power price enters hydrogen project finance in Southeast Asia as a cost of capital problem, so I settle the supply contract before I discuss financing terms.

Reading the contract with the fuel's rules

I read the electricity contract and the classification of the fuel together, never one without the other. The same hours that decide the load factor also decide whether the power can be counted in the molecule. A supply that looks cheap on paper can still leave a fuel that cannot claim the electricity it consumed.

A power purchase agreement that satisfies my model but fails the certification rules leaves a fuel with no market. The buyer takes delivery of the fuel under an offtake agreement. That buyer will test the origin of every unit of power claimed. I therefore draft the supply terms and the fuel claims in the same document set. Also, I check the certification requirements against the RFNBO classification rules before the model is finished.

What this means for you: I treat eligibility as a condition of signing the power contract, not as a later paperwork exercise. A fuel that fails the rules has no buyer, whatever the electricity price was.

What I will not accept as a firm power supply

Four exclusions, applied in this order.

  • Hours: Cheap hours are not a load factor, because below 40 percent the levelised cost climbs steeply, in December 2023. The worked example answers with a 40 to 50 percent solar share and storage, in December 2023.
  • Delivery: An announced renewable capacity is not delivered power. The same study puts annual curtailment at 18 percent on solar alone and 23 percent on wind alone, against 6 percent in the blended case, in December 2023.
  • Equipment: A headline electrolyser price is not an installed price, because the stack is only 15 to 20 percent of the installed investment, in 2025.
  • Tariff: A low tariff without the hours is not a cost. The target range is 3,200 to 4,200 full load hours, and the price path runs from 53 to 20 USD per MWh, in 2020.

What this means for you: I reject these four before I open the model. Each one asks a lender to fund an assumption instead of a contract, and the gap surfaces later as an unsupportable load factor.

What this changes for a Southeast Asian project

The 2026 review from the International Energy Agency frames the surrounding conditions. Global demand sits above 100 Mt in 2025 and low emissions production rose 20 percent in 2025 to almost 1 Mt. The announced pipeline falls to 27 Mt by 2030. The barriers are high costs, uncertain demand, complex regulation and missing infrastructure. Its infrastructure recommendation points at industrial and port clusters where production and users sit together.

The demand test is harder. Firm purchase agreements cumulate to less than 2 Mtpa, only 5 percent of what announced projects could produce by 2030, in 2025. In a region where a final investment decision. This means the formal commitment of capital waits on buyers as much as on lenders. That ratio is the first thing I check.

What this means for you: the power contract has to be priced against the buyer who ultimately pays the power bill, so I read it alongside the sustainable aviation fuel market before I set any price assumption, and I will not let a favourable tariff hide a missing buyer.

The four lines I would put in front of a lender

  • Line one, the price: at 50 USD per MWh the power price contributes 25 to 35 USD per gigajoule of fuel, in December 2023.
  • Line two, the hours: the levelised cost rises below 40 percent load factor, in December 2023. The target range is 3,200 to 4,200 full load hours at 53 to 20 USD per MWh, in 2020.
  • Line three, the equipment behind the load: 51 to 56 against 53 to 56 kWh per kilogram and 60,000 to 90,000 against 40,000 to 60,000 hours. Minimum load is 10 percent for modern atmospheric alkaline, in February 2026.
  • Line four, the capital: 15 percent, three times advanced economies, and less than 2 Mtpa of firm purchase agreements at 5 percent of announced 2030 production, in 2025.

What this means for you: I put these four lines on one page, each dated to its source. A power contract is only as good as the hours and the price it has to deliver. Both are settled before the plant is built.

Sources

Frequently asked questions

A supply that holds the load factor. Electricity is the most significant operating cost and its price is highly site dependent, operational flexibility lets the plant take low cost power, and grid connected projects on power purchase agreements face a different choice from projects running their own renewable assets. I add one test of my own: the hours have to be contracted, not merely available.

At 50 USD per MWh the power price alone contributes 25 to 35 USD per gigajoule of fuel, or 1,000 to 1,500 USD per tonne of oil equivalent, before any investment or consumable, in December 2023. That is the floor, and every other cost line sits on top of it.

Because the investment is spread over the fuel actually made. With a constant average price the levelised cost starts increasing very quickly once the load factor drops below 40 percent, in December 2023, against a target range of 3,200 to 4,200 full load hours, in 2020. The tariff can be attractive and the fuel still expensive.

Counting cheap hours as a load factor. Annual curtailment runs 18 percent on solar alone and 23 percent on wind alone, against 6 percent in the blended case that also minimises cost at a 40 to 50 percent solar share, in December 2023. A tariff quoted for a few good hours is not a delivered cost.

Not sure your project would survive a credit conversation?

A short call is usually enough to see where your project stands.

If you want a second reader on the supply side of the file, I offer contracting and risk management support on the contract itself: firmness, hours, curtailment treatment and how the whole package travels into the financing model. I work document by document with the sponsor and the lenders around the table.

I do not provide investment advice or arrange investments. In addition, I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia

I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.