Home » Take-or-Pay Hydrogen Offtake: The Volume Number Lenders Size Debt On
Take-or-Pay Hydrogen Offtake: The Volume Number Lenders Size Debt On
10 min read · Jan 2, 2026 · By Alex
A minimum volume clause in a hydrogen offtake obliges your buyer to pay for a defined share of the contracted annual volumes even when it does not take them, and that percentage, not my project narrative, is the number lenders size debt on. The level expected in negotiations sits at 60 to 80 percent against above 90 percent in gas and LNG contracts (August 2025). I set out the take or pay hydrogen offtake clause for the developer at pre-FID structuration stage deciding what minimum volume to concede, across hydrogen, power-to-liquid and e-fuels projects. My position is narrow: the volume number carries the debt, everything else supports it, and I would rather concede a definition than a percentage.
I order the volume clause in four moves: what the clause promises, the level the market expects and the level buyers will actually sign, where I leave flexibility, and how I settle the number against the lender’s own metrics. Each move ends with the consequence I hand a client.
In short
- Volume floor: 60 to 80 percent expected in hydrogen against above 90 percent in gas and LNG (August 2025).
- Buyer resistance: offtakers resist high commitments early, so I split volume across several agreements (2024).
- Lender metrics: minimum take/pay ratio, volume coverage ratio, share of contracted volumes, contract duration and offtaker rating (January 2026).
- Credit support: below BBB- investment grade I add letters of credit, bank guarantees, parent company guarantees or retention monies (2024).
- Local reality: 6 percent of announced Southeast Asian capacity had reached FID (December 2025).
In this article
What the clause promises
Firm take-or-pay commitments are typically a condition for reaching FID (August 2025), and the record behind that condition is thin: 7 Mtpa of purchase agreements were announced between 2021 and 2025 with only 1.6 Mtpa firm (December 2025).
The vocabulary first. The annual contract quantity is the volume the buyer commits to for one year. Take-or-pay obliges the buyer to pay a defined share of it even when it does not take the volumes, while take-and-pay obliges payment only for volumes delivered. A shortfall is the gap between that share and the volume taken; a make-up volume is volume recoverable later against the gap. Force majeure suspends payment for events outside either party’s control. Non-recourse project finance is debt repaid only from project revenue.
What this means for you: put these definitions into the term sheet before price, because every later argument about the percentage depends on which words the parties agreed they mean.
The level the market expects
The Oxford Institute for Energy Studies study of August 2025 reports that volume provisions are expected to prioritise take-or-pay at 60 to 80 percent in low-carbon hydrogen contracts against above 90 percent in gas and LNG, that take-or-pay obliges the buyer to pay a defined portion of the pre-agreed annual contract quantity even when volumes are not physically taken, and that this structure has provided revenue stability and bankability in the energy sector for decades. Alternatives such as capacity-based commitments or hybrid structures are also explored, while under take-and-pay the buyer pays only for delivered volumes, placing almost all volume risk on the seller.
I price that concession rather than absorb it, and I stage the negotiation as set out in the process I follow to secure an offtake agreement.
What this means for you: treat the gap between 60 to 80 percent and above 90 percent as a priced concession, not a template, and ask what the buyer gives back for the volume risk I carry.
What buyers will actually sign
The Green Hydrogen Organisation paper of 2024 records that offtakers are likely to resist high take-or-pay commitments, particularly for early-stage projects, and that a producer may therefore split the risk with several offtake agreements covering smaller volumes, which can raise the share of contracted revenue in a bankability assessment. It also states that take-or-pay gives the seller a steady revenue stream used to obtain project financing and to model cash flows.
Resistance at early stage is not a refusal to contract. Only 10 percent of announced projects have identified a buyer (2024), so the buyer I face is often testing demand as much as price. I bring the anatomy of an offtake agreement to that conversation and split my volume ask into tranches I can defend.
What this means for you: on an early-stage project I would rather sign several agreements covering smaller volumes than one headline deal I cannot place, because the share of contracted revenue is what a bankability assessment reads first.
Where I leave flexibility
Downward flexibility and alternatives to take-or-pay are being explored alongside it (August 2025), so the clause no longer has to be a flat floor. I accept a flexibility band below the annual contract quantity when the make-up mechanics are explicit: the shortfall is measured against a fixed period, nomination windows are set in advance, and recovery of make-up volume is capped inside the contract year.
I concede nothing that weakens the file. Change of law clauses come first, because they keep the contract viable as subsidy regimes, certification schemes and carbon pricing rules evolve, while wide contract reopenings are unlikely to be adopted because they undermine bankability (August 2025). The record is blunt: of the contracted volume, 13 percent is contractually binding, 7 percent pre-contractual and 80 percent memorandums or unspecified (2024).
What this means for you: take the band, the nomination window and the make-up cap in writing, and never trade them for a wider reopening right, because a contract the lender can reopen is a contract the lender will not size.
What a lender counts instead of my prose
The Oxford Institute for Energy Studies review of January 2026 shows that relatively few projects meet today the revenue-certainty conditions required by classic non-recourse project finance. Lenders track the minimum take/pay ratio, the volume coverage ratio, the share of contracted volumes, the annual contracted quantity, the contract duration and the offtaker rating, and in emerging markets and developing economies off-take and market risk followed by political and regulatory uncertainty are the most critical barriers to financing.
Some European projects reached FID with contracts of 5 to 7 years needing an equity contribution of around 50 percent (January 2026): a short contract is paid for in my own cash. Blended finance, subordinated tranches and guarantees absorb first losses without removing the underlying market or offtake risk, so I never count them as volume cover. The detail sits in the mechanics of hydrogen project financing.
What this means for you: I hand the lender the ratios before the narrative, and I size my own equity against the 5 to 7 year short-contract precedent rather than hope for a longer term.
Credit support when the offtaker is weak
Without an investment grade rating of BBB- the parties fall back on letters of credit, bank guarantees, parent company guarantees or retention monies (2024), and where the offtaker is not investment grade, credit enhancements from development finance institutions are envisaged: the World Bank at global level, AfDB, ADB and EBRD at regional level, plus bilateral institutions by country (2024).
I rank that support above a headline percentage. A take-or-pay at the top of 60 to 80 percent from an unrated buyer is worth less than a lower floor standing behind a guaranteed instrument, so I concede points on volume and buy real credit. NEOM reached financial close in May 2023, was oversubscribed more than two times and was financed on a non-recourse basis by 23 banks and investment companies for a total investment of 8.4 billion USD (2024). The options are at development finance institutions for credit support.
What this means for you: I line up the instrument behind any headline number, because an unrated buyer with no letter of credit is a producer risk dressed as a contract.
What this means for a Southeast Asian developer
The IEA briefing of 9 December 2025 records a regional demand of 4 Mt in 2024, with ammonia taking 49 percent against refining at 31 percent and methanol at 20 percent. Announced regional projects equal 12 percent of current demand while only 6 percent of announced capacity has reached FID, and close to 11 Mtpa of potential below 6 USD/kg by 2030 sits mostly in Indonesia. A high cost of capital is cited as the main barrier, against 6.6 billion USD of development finance institution lending between 2021 and 2025.
That profile changes what I concede. Where ammonia leads demand I anchor the volume on a single buyer’s offtake rather than on regional growth, and I read the cost of capital in the Southeast Asia cost outlook before I set the floor.
What this means for you: with only 6 percent of announced regional capacity at FID (December 2025), I underwrite my clause to the buyer in front of me and treat announced regional demand as context, never as cover.
How I set the number
The IEA page of five key questions from 2025 closes the sequence: firm purchase agreements cumulate to less than 2 Mtpa, only 5 percent of the production potential announced for 2030, 9 percent of announced projects worldwide have secured committed investment against 0.5 percent in emerging economies, and the cost of capital can reach 15 percent in emerging economies, three times the level in advanced economies.
Those four numbers are the room I negotiate in: a buyer who knows that 0.5 percent of announced projects in emerging economies hold committed investment will not concede 90 percent, and I would rather arrive with a defensible floor than an aspirational one.
What this means for you: I settle the number in one order with the buyer: credit and contract duration first, the volume I can evidence second, the headline percentage last. The percentage is the output of the other two, not the opening position.
Sources
- Oxford Institute for Energy Studies, Hydrogen Offtake Agreements https://www.oxfordenergy.org/wpcms/wp-content/uploads/2025/08/ET50-Hydrogen-Offtake-Agreements.pdf, August 2025.
- Green Hydrogen Organisation, Key considerations for green hydrogen offtake agreements https://gh2.org/sites/default/files/2024-05/GH2_Considerations%20for%20Hydrogen%20Offtake%20Agreements_2024.pdf, 2024.
- Oxford Institute for Energy Studies, Bankability of Hydrogen Projects: Key Risks, Financing Challenges and Mitigation Solutions https://www.oxfordenergy.org/wpcms/wp-content/uploads/2026/01/ET52-Bankability-of-Hydrogen-Projects.pdf, January 2026.
- IEA, Global Hydrogen Review 2025, Southeast Asia, 9 December 2025 https://iea.blob.core.windows.net/assets/745a259b-9cb7-4e1d-9ba1-a8b63d1eaae8/GHR2025_SEA_Webinar.pdf, 2025.
- IEA, Global Hydrogen Review 2025, Five key questions about hydrogen https://www.iea.org/reports/global-hydrogen-review-2025/five-key-questions-about-hydrogen, 2025.
Frequently asked questions
What is take-or-pay in a hydrogen contract?
It is a commitment by the buyer to pay for a defined portion of the annual contract quantity even when it does not take the volumes. Contracts of this kind are typically included as a condition for reaching FID (August 2025), which is why I treat the clause as a financing input rather than a commercial preference.
How much volume should the clause cover?
There is no published rule, so I work from the record: 60 to 80 percent is what negotiations are expected to produce in low-carbon hydrogen against above 90 percent in gas and LNG (2025). I start from the buyer’s credit, its contract duration and the volume I can evidence, then move the percentage last.
What is the alternative to take-or-pay?
Capacity-based commitments or hybrid structures are being explored alongside the volume floor (2025), and take-and-pay leaves almost all volume risk with the seller, because the buyer pays only for delivered volumes and recovery is harder unless damages are pre-agreed in the contract. I use a hybrid only when the make-up mechanics are explicit.
What happens if the buyer does not take the volume?
The payment obligation still runs unless force majeure applies, which suspends it for events outside either party’s control. Where credit is thin the parties add letters of credit, bank guarantees, parent company guarantees or retention monies, and investment grade starts at BBB- (2024). I negotiate the instrument before the percentage for that reason.
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If you are at pre-FID and the volume number is still open, I run the clause against the lender’s own metrics. My offtake structuring work starts from the credit file rather than the headline percentage, and I come back with the two numbers worth arguing about first.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.