How Long Does a Hydrogen Project Take to Reach FID?

10 min read  ·  May 2, 2026  ·  By Alex

hydrogen project timeline fid

Every hydrogen project you read about carries two dates, and only one of them is a decision. The other is an intention that has not met its permits, its buyer or its lenders. Gates that run in parallel rather than in sequence set a hydrogen project timeline. Therefore, the honest calendar belongs to permitting, to offtake and to the capital rather than to the engineering. Also, the one case I can date from public sources is a 20 MW green hydrogen project in the Netherlands that has been under development since 2018 and reached its final investment decision only in May 2026, while worldwide only 9 per cent of announced projects had secured committed investment in the 2025 count. I set everything below against the guide to financing a hydrogen project.

What this article shows

In what follows I order what project lists show and hide, which gates run in parallel, what a decision date really tests, the study that produces the date, the one case I can date, what the capital expects in the meantime and the calendar I then give.

In short

  • The calendar: permits, buyers and capital run in parallel, so the defensible date is the last gate to close.
  • The count: in 2025 only 9 per cent of announced projects had committed investment, against 0.5 per cent in emerging economies.
  • The deadline: 22 Mt of announced potential lose any chance of operating in 2030 if decisions do not come before early 2027.
  • The case: a 20 MW Dutch green hydrogen project under development since 2018 reported its decision on 21 May 2026.
  • The schedule: five gates, one date per gate, one owner per date.
Facebook
Twitter
LinkedIn

In this article

What actually sets the calendar

A final investment decision is the moment the owners commit their money to build, front-end engineering design is the pass that fixes design and cost before that moment, and financial close is the date the loan becomes available to draw. Permitting is the run of approvals from the environmental study to the construction permission. Also, the environmental impact assessment is that study. Those three gates hold separate dates: the buyer contract, the permits and the loan. Also, the engineering starts when the last of them closes. I have never seen a schedule survive three questions about permits, buyers and grid connection (2026). A press release date tells me when the announcement was made. Only the decision date tells me when the owners committed the money.

What this means for you: build the schedule from those three tracks and name the owner of every date. A date without an owner is a hope.

What project lists show and hide

Reading the December 2025 Southeast Asia briefing, I get 4 Mt of hydrogen demand in 2024 across 5 countries with a national strategy, announced projects at 12 per cent of current regional demand and only 6 per cent of announced capacity at a final investment decision. Offtake is thinner than the headline. The market announced 7 Mtpa of offtake between 2021 and 2025, of which only 1.6 Mtpa counted as firm. Export projects lined up 16.5 Mtpa for 2030, of which 4.2 Mtpa had an identified buyer. Capital followed the same pattern: 8 billion USD went into production investment in 2025 against 38 billion USD of public funding advanced and 6.6 billion USD of development lending committed between 2021 and 2025.

Nearly 11 Mtpa of regional potential sits below 6 USD/kg by 2030, mostly in Indonesia, and no certification scheme is yet in place with work under way in three countries. A list of names shows intentions until someone fills the stage column (December 2025).

What this means for you: read the hydrogen developers map for Southeast Asia as a list of intentions, and ask for the stage and firm volume before you quote capacity.

The gates that run in parallel, not in series

The order I use comes from the Oxford bankability paper of January 2026. Lenders require evidence that every environmental and construction permit clears financial close, with a completed environmental impact assessment. They also need all relevant planning permissions and compliance with equipment and safety standards. Two standards matter: ISO 22734 for electrolysers and ASME B31.12 for pipelines. A schedule performance index tracks time against plan. Also, the bank metrics carry the delay in obtaining permits alongside that index and the construction period in months. Complex regulatory frameworks and slow permitting can cause unforeseen delays to overall project timelines. The lengthy development and commercialisation process increases exposure to cost overruns, changing market conditions. Also, policy risks, and longer lead times before commercial operation degrade the project’s financial return and risk profile.

Project-on-project risk is the risk that one asset is ready before the asset it feeds. Also, it arrives when the hydrogen plant operates before its infrastructure is ready. Permits, buyers and infrastructure are three separate calendars that must close on the same week (2026).

What this means for you: run the three calendars in parallel with three owners, because bankability, the degree to which lenders judge a project financeable, is the outcome and not the starting point.

What the decision date really tests

I find the test in the 2026 review’s executive summary. Decisions must come by early 2027, or 22 Mt of announced potential loses its chance of starting operation in 2030. Two-thirds of that potential sits in Europe, North America and Latin America. The announced pipeline stands at 27 Mt for 2030. Meanwhile, projects with strong potential to operate in 2030 fell from 10 Mt to just above 6 Mt overall. Capacity that reached a final investment decision since the previous evaluation added 300 ktpa, but investment momentum slowed in 2025. Demand passed 100 Mt in 2025 while low-carbon production grew 20 per cent to almost 1 Mt. It should pass 1 per cent of world production for the first time in 2026.

The barriers cited are high costs, uncertain demand, slow or complex regulation and insufficient infrastructure. Permitting processes and coordination among authorities act as the levers that reduce lead times. A deadline is not a schedule, it is what happens when the schedule slips (2026).

What this means for you: treat the decision window as a gate with a date, not as a target, and tell shareholders which part of the pipeline still has a chance.

The study that produces the date

The date I can defend comes out of the feasibility and financial model rather than out of a press release. The model writes down the environmental impact assessment, the planning permissions and the construction period in months. It also records the contingency share of contract value and the alignment of commissioning dates across production, transport and offtake. All of it serves as assumptions someone can challenge. Contingency is the money held back for surprises. Also, it sits in the model as a share of contract value rather than as a sentence. The technical review then tests the same file against reference plants, cumulative operating hours and availability rather than against a label: a first-of-a-kind plant is one with no twin to copy, and the label tells a lender nothing about the fleet.

The conclusion I reach in every review is that the model needs one date per gate and one owner per date. A single milestone date hides three gates.

What this means for you: ask for the feasibility and financial model behind the date and check that every assumption carries an owner who can be questioned.

The one case I can date

I date this from the Hydrogen Insight report of May 2026. A 20 MW green hydrogen project in the Netherlands, developed in the Delfzijl chemical park, started in 2018. It reached its final investment decision on 21 May 2026. The European Union had awarded the project a grant of 11 million euros in January 2020. This is the only project whose development span I can date from a source I actually read. Also, it is a reminder that a press release date and a decision date are different objects (May 2026). I cannot say how long any single stage took, because no source I read publishes the permits, the buyer negotiation or the loan as dated events; I can only hold the two dates apart.

What this means for you: quote the two dates and nothing between them, then compare your case with a power-to-liquid project that reached its own decision before you promise a year.

What the capital expects in the meantime

The capital side comes from the 2025 review’s five key questions: only 9 per cent of announced projects worldwide have secured committed investment against 0.5 per cent in emerging economies, and firm offtake agreements add up to less than 2 Mtpa, about 5 per cent of the potential 2030 production of announced projects. An offtaker is a buyer with a duty to buy. Take-or-pay makes that buyer pay whether or not it lifts. Merchant exposure means selling at market prices instead of under contract. The cost of capital can reach 15 per cent in emerging economies, three times the level in advanced economies.

Building every announced project would produce more than 9 Mtpa in Africa, Latin America and Southeast Asia by 2030. That is around 25 per cent of announced world production. Meanwhile, 80 per cent of projects in emerging regions target export markets. The electrolyser stack is only 15 to 20 percent of installed investment. Blended finance takes the first losses but does not remove the offtake risk underneath. The money arrives on a different calendar from the engineers (2025).

What this means for you: put the case for hydrogen investment in Southeast Asia next to your own cost of capital, because the two move on different clocks.

The calendar I give

Gate one is the environmental study and the planning permissions, because every permit must be secured before financial close (2026). Gate two is the buyer. Only 1.6 Mtpa of the 7 Mtpa announced between 2021 and 2025 counted as firm (December 2025). The third gate is the certificate. Southeast Asia had no certification scheme in December 2025, with work under way in three countries. A guarantee of origin records how producers made the molecule. Gate four is the decision window. Announced potential of 22 Mt loses its chance of operating in 2030 unless decisions come before early 2027 (2026). Gate five is the record. Reference plants, cumulative operating hours and availability decide whether the technical file supports the date at all (2026). Those five gates, not a score, decide whether a lender will call the project bankable.

What this means for you: hand shareholders five gates, five dates and five owners, and measure the result with a clear view of bankability rather than one milestone.

Sources

Frequently asked questions

I do not give a single number, because the sources I trust describe gates rather than averages: the one project I can date ran from development in 2018 to a decision reported in May 2026, with a grant awarded in January 2020 along the way.

Permitting and the buyer, since every environmental and construction permit must be secured before financial close while slow permitting can delay the whole timeline, and only 1.6 Mtpa of the 7 Mtpa of offtake announced between 2021 and 2025 was firm. Both are visible in the file before the loan is signed, so neither should arrive as news to a shareholder.

A small minority: in 2025 only 9 per cent of announced projects worldwide had secured committed investment against 0.5 per cent in emerging economies, and only 6 per cent of announced capacity in Southeast Asia had reached a decision in the count published in December 2025. Announced capacity is not financed capacity, and the stage column is the only honest separator between the two.

A schedule with one date per gate and one owner per date, plus the model behind it: the environmental impact assessment, the planning permissions, the construction period in months, the contingency share and the commissioning dates aligned across production, transport and offtake.

Not sure your project would survive a credit conversation?

A short call is usually enough to see where your project stands.

If you want the gates turned into a schedule your shareholders can interrogate, I do that as project finance work. Bring the permits, the buyer contract and the model, and I will tell you which of the three is holding the date.

I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia

I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.