The Waste-to-Energy Market in Southeast Asia: Where the Projects Actually Are

10 min read  ·  Dec 5, 2025  ·  By Alex

waste to energy market southeast asia

Five Southeast Asian countries sit at different stages of waste-to-energy development, in which municipal solid waste, the everyday waste a city collects, is treated to recover energy instead of only buried. Indonesia generated 35.8 million tonnes of municipal solid waste in 2022 and counted 12 waste-to-energy facilities in 2025; Singapore treats about 80 percent of its municipal solid waste in waste-to-energy plants in the 2025 figures; Thailand had about 210 MW of installed capacity, meaning plants built and running, from municipal solid waste in 2018. The gap between them is not mainly about technology. It is about tonnes collected, plants that run, and a payer that carries the treatment cost: that is how I read the waste to energy market southeast asia before I take a mandate.

In this piece I set out what I count as the market, where the waste grows, what an operating plant delivers, what a market needs before it finances, where Indonesia stands, and what public policy puts in place. Each of those comes from one dated record and from nothing else.

In short

  • Market: Five countries with 700 million people in 2025, and one city-state already treating about 80 percent of its municipal solid waste.
  • Growth: 2.56 billion tonnes of waste in 2022, heading for 3.86 billion tonnes by 2050.
  • Delivery: A financed fleet in 2015 added 6,200 tons of capacity, 132 MW and 630 GWh a year.
  • Entry: In 2013 the floor was 100,000 tonnes a year at 7 MJ/kg before a plant is financeable.
  • Indonesia: In 2014, 64 million tonnes a year with 9-10 USD asked against 25-30 USD needed.
Facebook
Twitter
LinkedIn

In this article

What I count as the market

My baseline is the ISWA regional brief of July 2025, covering five countries with more than 700 million people: in 2022 Indonesia generated 35.8 million tonnes of municipal solid waste at 0.67 kg per person, Malaysia generates nearly 14 million tonnes a year, Thailand about 25.7 million tonnes a year, and the Philippines moved from 9.07 million tonnes in 2000 to 16.63 million tonnes in 2020.

In that 2025 picture, about 80 percent of Singapore’s municipal solid waste is treated in waste-to-energy plants, and those plants produced 1,502,487 MWh from incineration in 2023. Volume is not the same thing as delivery: in 2022, 47.64 percent of Indonesia’s waste went to sanitary or controlled landfill and 37.38 percent escaped into the environment.

What this means for you: I size a market by tonnes generated, tonnes collected and capacity in operation, because those three decide whether a mandate has anything to feed. Targets and announcements I leave out of the count.

Where the waste is growing fastest

The growth curve comes from the World Bank’s What a Waste 3.0 report of March 2026, which records 2.56 billion tonnes of waste produced in 2022, a figure the 2018 edition did not expect before 2030, and projects 3.86 billion tonnes by 2050 under business as usual, drawing on data from 217 countries and 262 cities.

A collection rate, meaning the share of waste that a service actually picks up, tells me whether that volume can be reached: in March 2026 it stood as low as 31 percent in Sub-Saharan Africa and 67 percent in South Asia. The same March 2026 data put the sector at about 18 million urban waste workers.

For Southeast Asia I then narrow the frame to the circular waste and energy industry, because a tonnage only becomes feedstock once a service reaches it and a contract delivers it.

What this means for you: I do not ask whether waste is growing. I ask whether a service reaches it, because growth I cannot collect into is growth in a dumpsite, not in a plant.

What an operating plant delivers

The template I compare against is the Asian Development Bank case story published in October 2015: a portfolio of six plants that added 6,200 tons of municipal solid waste processing capacity, 132 MW of power and 630 GWh a year, with one plant at Jinan producing 190 GWh from 36 MW while running on 2,000 tons of waste.

The concession, meaning a long-term grant of exclusive rights to receive and treat a city’s waste, was exclusive for not less than 25 years in that 2015 model. In the same market in 2015, 67 plants were processing 11 million tons of municipal solid waste a year.

Before I model a fleet of that kind I walk through a guide to waste-to-energy plants to see what sits behind each figure, from grate to ash handling.

What this means for you: I want a reference fleet I can measure against, in tons, MW and GWh a year, because a single plant with no fleet behind it tells me nothing about scale.

What a market needs before it can be financed

The entry conditions I use are the ISWA guidelines of August 2013: a mature and well operated waste management system, disposal already in controlled landfills, at least 100,000 tonnes a year of combustible waste, an average lower calorific value of at least 7 MJ/kg never falling below 6 MJ/kg, a community able and willing to pay, and planning stable for more than 15 years.

Refuse-derived fuel, meaning waste processed into a solid fuel with a steadier calorific value, is what many plants burn instead of raw municipal solid waste. In 2013 more than 1,200 waste-to-energy plants operated across more than 40 countries.

Capital and operating costs stay high in that setting, and a rise in treatment cost can push waste toward uncontrolled dumping, which is why I run every case through my Southeast Asia project finance framework before I call a market ready.

What this means for you: If one condition fails, the plant is not financeable yet, however good the technology looks. I check all six before I spend a week building a model.

Where Indonesia stands

The reference point is the 2014 Carbon Trust and IESR study of Indonesia, which records about 64 million tonnes of urban solid waste a year with more than two thirds disposed on around 380 open landfill sites, a waste sector accounting for 25 percent of national greenhouse gas emissions in 2005, and local authorities prepared to pay roughly 9-10 USD per tonne against an industry stated need of about 25-30 USD for incineration.

Two revenue lines carry the plant: the tipping fee, meaning the charge for accepting a load of solid waste, and electricity sold under a Feed-in Tariff, meaning a fixed price guaranteed for power delivered to the grid. In that 2014 analysis the two together had to reach an internal rate of return of about 15 percent.

Procurement in one city took about 4 years in that period, and around 1.2 million waste pickers depended on the system in 2014. I read the offtake agreements for waste-to-energy and biogas before I price anything.

What this means for you: I look for who pays each line and which instrument fixes it, because a gap of that size between what is asked and what is needed is the first thing a lender tests.

What public policy is putting in place

Indonesia’s presidential decree of 2017 sets a 30 percent reduction at source and a 70 percent handling target for 2025, and a decree of 2018 accelerates energy recovery in 12 major cities.

Malaysia’s solid waste law has been in force since September 2011 and covers seven states, with 165 landfills operating in 2025 against a 40 percent recycling target for that year.

Singapore’s master plan targets 70 percent recycling and a 30 percent cut in waste generation by 2025, backed by a green bond and medium-term note programme of 3 billion Singapore dollars adopted in August 2021.

Thailand’s roadmap aims at 100 percent recycled plastic by 2030, and about 210 MW of waste-to-energy capacity was installed there in 2018. I map each of these to the grants and incentives a project can actually claim.

What this means for you: I read policy as a set of dates and numbers I can hold a counterparty to, not as a promise. A target with no funding behind it does not enter my case.

What I would test before I back a market entry

I write five checks on one page before I look at a term sheet. First, the tonnage actually collected and delivered in the market, not the tonnage generated. Second, the share of that tonnage controlled in engineered landfills, since open dumping competes on price. Third, capacity in operation against capacity announced, and the two are never added together, because announced capacity is not capacity and a sum of the two is a number no lender will use.

Fourth, the payer behind the tipping fee and the electricity price, and which instrument fixes each of them. Fifth, where the plant sits against the waste hierarchy, meaning prevention first, then reuse and recycling, then recovery, then disposal, as national policy states it. I ask for the document behind each answer rather than a summary.

What this means for you: A market passes these five tests or it does not, and I would rather lose a mandate than argue with the third one six months later.

How I would write the market case in a credit paper

I put four dated rows on the first page of any credit paper and nothing above them.

  • Volume, 2022: 35.8 million tonnes of municipal solid waste in Indonesia.
  • Collection, March 2026: rates as low as 31 percent in Sub-Saharan Africa and 67 percent in South Asia.
  • Fleet, 2015: 6,200 tons of added capacity, 132 MW and 630 GWh a year.
  • Price, 2014: 9-10 USD asked against 25-30 USD needed.

Bankable, for me, means a case a lender will accept on those four rows without a story around them, and every row carries a date so a reader can see when the ground was measured. Nothing in that paper is a target or an announcement: each row is a measured figure from a published record, and I would rather cut a row than soften one.

What this means for you: I would rather hand over four dated rows that hold than a deck of forecasts. If a row cannot be sourced to a year, it does not go in.

Sources

Frequently asked questions

I measure it in waste volumes and in plants that run: 35.8 million tonnes of municipal solid waste in Indonesia in 2022, about 25.7 million tonnes a year in Thailand, nearly 14 million tonnes a year in Malaysia, and 16.63 million tonnes in the Philippines in 2020 projected to 20.45 million tonnes by 2045. Those are the tonnes I would contract against, not a regional average.

The one that already treats most of its municipal solid waste in plants: about 80 percent in the city-state, where incineration produced 1,502,487 MWh and a new line of 2,900 tonnes per day started construction in May 2020. Everywhere else in the region most waste still ends up in open dumpsites.

A waste stream that fails the entry conditions, a payer that will not carry the treatment cost, and a procurement that drifts: at least 100,000 tonnes a year at an average 7 MJ/kg, a fee of about USD 9-10 asked against about USD 25-30 needed in one market, and a tender that took about 4 years in 2014. Any one of the three is enough to stop a close on its own.

It depends on the two revenue lines rather than on the technology: one third from tipping fees and two thirds from the electricity price in the 2015 concession model, with an internal rate of return of about 15 percent required before capital is committed. A plant that clears only one of the two lines does not get built.

Not sure your project would survive a credit conversation?

A short call is usually enough to see where your project stands.

If you are at concept stage and want a clear read on which of these markets deserves your next two weeks, my strategic partnerships work is where I take that on, one market at a time and against the same four dated rows.

I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia