We Connect Asia

SAF

Green Loans and Sustainability-Linked Debt for SAF Projects

10 min read  ·  Oct 2, 2026  ·  By Alex

saf green loans sustainability linked

Two labels, one question: does either make my SAF project more bankable? My answer, from files I have worked through at FID stage in Southeast Asia: a green loan changes what you can prove about a defined use of funds, a sustainability-linked loan changes what your margin does when you miss a target, and neither replaces an offtake agreement or a secured feedstock supply. I start every file at how to finance a SAF project, then pick the structure the evidence can carry.

Most developers at FID stage hear “green finance” as one product. It is at least two, with different evidence, owners and failure modes.

In short

  • Green loan: proceeds are ring-fenced for eligible green projects and tracked to those categories; the rate is fixed at issuance.
  • Sustainability-linked loan: proceeds go to general corporate purposes and the margin moves with your ESG performance, up or down.
  • Cheaper terms are a supply-side effect: banks across Southeast Asia are building green loan portfolios, which sits in your favour.
  • Targets have to clear regulation: since February 2023 an SPT must go beyond what the law already requires.
  • Neither instrument fixes a gap: no label sizes your debt if the offtake or the feedstock supply is missing.
Facebook
Twitter
LinkedIn

In this article

Two instruments, one question

The Loan Market Association material I work from, written with Norton Rose Fulbright in June 2023, splits debt into two families: use of proceeds loans finance standalone green projects, while sustainability-linked loans support a borrower improving performance through predetermined targets and the proceeds may fund any business activity. That publication is older than two years, so I read it as a description of the instrument rather than current pricing.

In aviation the split went one way: the green loan has been used for a small number of aviation deals while the sustainability-linked loan became the favoured instrument, flexible, borrower-focused and free of the greenwashing risk in calling today’s aircraft green.

For a SAF producer the difference is narrower than the marketing suggests: a green loan attaches to a named spend inside your project, such as feedstock purchases or a pre-FID study, while a sustainability-linked loan attaches to a company-wide metric and ignores which asset the cash touches.

What this means for you: if your case rests on one project with a defensible spend, lead with the green loan; if it rests on company-wide performance you can measure and verify, lead with the sustainability-linked loan. Build neither before the offtake and feedstock legs are drafted.

What a green loan asks of a SAF producer

The defining characteristic of a green loan is the purpose of the capital, not your sustainability profile: funds must finance eligible green projects, and that use must be tracked.

The framework comes first. Neste built its own green finance framework aligned with the Green Bond Principles of the International Capital Market Association and Asia Pacific Loan Market Association principles, went through a third-party review and publishes annual reports on the financed projects. It has issued four green bonds in four years totalling 2.1 billion euro, most recently 600 million euro at 3.875% in November 2023, expanding capacity in Singapore, Rotterdam and Martinez, California.

Taxonomy is the second gate: SAF producers need a green financing taxonomy, the framework defining what counts as environmentally sustainable economic activity. The EU and China cover SAF use, SAF sits in scope of the IDFC Common Principles for Climate Mitigation Finance Tracking, while the Climate Bonds Initiative taxonomy does not recognise aviation and bioenergy as sustainable. Issuers commit to reporting SAF volume and lifecycle emissions.

A regional precedent: Cathay United Bank’s Singapore branch closed a green trade loan with Apeiron Bioenergy, announced 19 February, entirely for its procurement of used cooking oil for SAF production, under the Green Loan Principles of the Asia Pacific Loan Market Association. Apeiron runs 10 countries from Singapore and has supplied over 600 million litres of used cooking oil since 2017, an estimated 1.8 million metric tons of GHG savings.

What this means for you: write the green finance framework and the allocation policy before you send the model, and show a use-of-proceeds ledger a lender can audit against project categories.

What a sustainability-linked loan asks instead

Nothing is ring-fenced: the proceeds go to general corporate purposes, and the loan’s economics vary with whether you achieve ambitious, material and quantifiable sustainability performance targets. Targets met, the rate falls; targets missed, a margin adjustment applies.

Five components carry the structure: selection of KPIs, calibration of SPTs, loan characteristics, reporting and verification. The KPI must be relevant to your core business, measurable and externally verifiable, backed by an audited baseline and ambitious enough that missing it is a real outcome: weak targets trigger reviews.

Verification sits at the end and governs everything before it: borrowers must obtain independent, external verification of performance against each SPT before any margin adjustment, because marking your own homework would call the product’s integrity into question. Budget for that third party from the start.

What this means for you: if you cannot name an independent verifier and produce an audited baseline today, you do not have an SLL file yet; start with the green loan and build the system in parallel.

Choosing the KPI and calibrating the target

The aviation market’s KPIs are a short list: fleet renewal, the share of an airline’s fleet running on sustainable aviation fuel, and CO2 emissions per passenger kilometre. Consistency is poor, which is why two initiatives exist: ACAF, where financial institutions disclose annually whether the aircraft, airlines and lessors they finance align with 1.5C targets, and IMPACT, which proposes milestone scoring.

The calibration rules are stricter than most term sheets suggest. SPTs must stay relevant and ambitious for the life of the loan, represent a material improvement in the KPI and go beyond business as usual; since February 2023 they must also go beyond what regulation requires. That last test is where many files fail.

This is exactly where the SAF mandates question bites: a mandate sets a legal floor, and an SPT that merely repeats it fails the test. An undated Green Finance Institute page gives that floor: countries including the UK, the US and EU member states have set net zero aviation targets by 2050, and the UK will soon require airlines to use 10% SAF by 2030 and 75% by 2050.

The SLLP recommends SPTs be set each year for each KPI, with exceptions where a strong rationale is given. For a producer the equivalent KPIs sit on the plant’s emissions intensity and the fuel’s lifecycle intensity, which drags certification data into the loan agreement and makes reporting cadence an operating task.

What this means for you: pick one KPI you can measure monthly and one target visibly above the mandate, then write the annual recalculation into the term sheet before pricing.

What the market has actually paid for

Start with the carrier side, where the documented pricing sits: Etihad in 2021, US$1.2 billion, with KPIs on CO2 emissions intensity of its passenger fleet; JetBlue in 2020, 550 million USD, linked to its sustainability rating; British Airways in 2021, 1 billion pounds, supported by UK Export Finance.

Then the bond market. Air France-KLM issued a sustainability-linked bond for 1 billion euro in January 2023, linked to reducing scope 1 and scope 3 emissions by 2025, with SAF use as one of four levers and a 10% decrease in well-to-wake emission intensity per revenue tonne kilometre against 2019.

Two tranches: 500 million euro for 3.3 years at a 7.25% coupon and 500 million euro for 5.3 years at an 8.125% coupon, 2.6 times oversubscribed.

Read that as appetite, not as your price: every figure above was paid by a carrier with routes and a balance sheet, not by a producer under construction.

What this means for you: quote these precedents to show that SPT-linked structures clear the market, then drop them from your own pricing expectations and let your model stand on its own economics.

Where producers have actually raised green money

In power-to-liquid, Twelve raised up to 645 million USD, of which 400 million USD in project equity led by TPG Rise Climate and 200 million USD in Series C financing; Fundamental Renewables issued a 25 million USD construction loan and SMBC a 20 million USD green loan.

The gap is upstream: the Green Finance Institute page, undated, states that UK SAF plant developers find it difficult to access finance because of price, technology and feedstock risks. SAF demand is expected to reach 17 million tonnes per annum by 2030, about 4% to 5% of total jet fuel, requiring a further 5.8 million tonnes of capacity reaching FID by 2026.

Feedstock decides which instrument you can use. HEFA is the most mature and cost-effective pathway and is expected to dominate SAF production to 2030, but it faces feedstock constraints, and used cooking oil is competed for by biodiesel, renewable diesel and SAF producers.

Keep feedstock and offtake as two equal pillars: a green loan covers the feedstock leg, since the use of proceeds can be tied directly to those purchases, while an offtake contract covers the revenue leg. Neither replaces the other.

What this means for you: if your feedstock supply is secured and your revenue side is not, spend your effort on the offtake first, because no green label will close that hole.

Which one changes bankability, and when

My decision rule is mechanical: a defined asset with a defined spend, such as used cooking oil purchases or a pre-FID study, fits the green loan, because the use of proceeds is auditable and the framework gives lenders a reporting handle they know. An operating company with company-wide emissions wanting its margin to reflect performance fits the sustainability-linked loan, because the rate is tied to ESG KPIs on general corporate purposes.

There is one more asymmetry on the demand side: a sustainability-linked structure tied to SAF uptake de-risks offtake agreements, and mandates create contracted volume in the same direction. Patient money from development finance institutions often arrives with green portfolio targets, which a framework-backed file answers more easily.

One warning I repeat in every session: neither instrument cures a missing offtake or an unsecured feedstock supply. Lenders underwrite cash flows and contracts; the wrapper only decides how fast the credit committee moves and which internal portfolio bucket you land in.

What this means for you: run both applications in parallel only if you can staff both evidence packs; otherwise pick the green loan, because it is the one your existing contracts can already satisfy.

What I assemble before I approach a lender

For a green loan the file starts with a financing framework mapped to a named taxonomy, a third-party review, an allocation policy, a reporting cadence and a use-of-proceeds ledger tying every draw to an eligible category. For a sustainability-linked loan it starts with KPI definitions, an audited baseline, annual SPTs with the margin mechanics in numbers, and the verification contract identified.

Alongside that I put the evidence pack and the financial model, with feedstock contracts and offtake terms treated as equals rather than annexes: the lender’s question is always which proves the cash flow.

Three pieces of my own sequence sit behind this article: the feasibility and financial model covers the gating work before any lender call, low carbon fuels investment covers the sponsor money under the debt, and power-to-liquid explained covers the route itself.

What this means for you: build the framework, the baseline and the ledger as one document set and send it with the model, because the file that arrives complete gets priced while the file that arrives in three emails gets deferred.

Sources

Frequently asked questions

The green loan ties the cash to a project: proceeds must finance eligible green projects, the rate is fixed at issuance, and use of proceeds is tracked. The sustainability-linked loan ties pricing to performance: proceeds fund general corporate purposes, margins follow ESG KPIs, and you need a verified baseline plus credible targets.

Often, but for a reason unrelated to your project’s quality: margins may be lower, tenors longer and covenants more flexible because banks across Southeast Asia are under pressure to grow their green loan portfolios. Terms still depend on your credit and contracts, so do not model an unquoted discount.

Usually not comfortably: you need an audited baseline, relevant and externally verifiable KPIs, annual SPTs and an independent verifier engaged before any margin adjustment, and pre-FID companies often lack the reporting history that makes those credible. Start with a green loan for a defined spend and build the measurement system in parallel; the SLL becomes available once a baseline exists.

Offer the one you can measure continuously and defend externally: the lifecycle emissions intensity of the fuel and the emissions intensity of your plant. The aviation market’s common KPIs, fleet renewal, share of fleet on SAF and CO2 per passenger kilometre, belong to carriers. Whatever you choose, the target must be material, beyond business as usual and beyond what regulation requires, and recalculated yearly.

Want a second pair of eyes before the file goes to a lender?

A short call is usually enough to see where your project stands.

If you want a second pair of eyes on the file before it goes to a lender, I offer project finance support for SAF and renewable fuel ventures in Southeast Asia.

I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia

I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.

More about me·Get in touch

Facebook
Twitter
LinkedIn

Related articles