SAF Term Sheet Red Flags: What a Developer Must Catch Before Signing Equity

10 min read  ·  Nov 2, 2026  ·  By Alex

saf term sheet red flags

The clauses that must alert you before signing equity are open-ended conditions precedent. An uncapped veto list, exit economics that place the investor first in line, and a funding schedule whose gates you do not control. I run that read on every draft, for a sustainable aviation fuel developer in Southeast Asia who is pre-final investment decision (FID) and asks which clauses must alert him. The wider context sits on the parent page for equity funding for sustainable aviation fuel in Southeast Asia; here I isolate the clause-level warnings. Also, the checklist itself is my SAF term sheet red flags read, in the order the clauses appear.

I keep the scope to clause-level wording rather than market commentary, read the way the investor’s counsel reads it.

In short

  • Conditions precedent: Open-ended wording, especially satisfaction of the investor’s own due diligence, turns signed money into money you cannot date.
  • Control: A reserved matters list reaching your budget, feedstock supply and offtake leaves a minority stake and no operating freedom.
  • Funding: Tranches, escrow and reimbursable fees mean the investor’s cash follows the investor’s comfort, not your construction programme.
  • Offtake and feedstock: Short or vague contracts on either side are priced as risk, then handed back to you as conditions.
  • Exit: Liquidation preference, participation, redemption and full ratchet anti-dilution decide who is paid first, and rarely you.
Facebook
Twitter
LinkedIn

In this article

What an equity term sheet is, and the clauses that should stop you

A term sheet is a preliminary document setting out the terms on which outside equity would be invested. In addition, it is the basis on which the closing documents are drafted (Carofin). What gets negotiated here decides the rest: conditions precedent (CP), use of proceeds. Anti-dilution, reserved matters, information rights, exit, exclusivity and the investor’s fees. In addition, expenses (Squire Patton Boggs, undated).

The project sits on a chain of milestones: indicative interest, term sheet, credit approval, documentation, satisfaction of conditions, financial close, then drawdown. These are not equivalent events, and a term sheet means neither committed money nor drawable money (Projects RH, 11 Nov. 2026). I check that sequence against how to finance a SAF project.

What this means for you: I treat the term sheet as a map of obligations, not as a cheque. Before I sign, I name the clause that will be argued again at closing; if I cannot, I keep reading.

Conditions precedent: where a signed term sheet stops being money

Conditions precedent are contractual requirements that must be satisfied, or waived where permitted. Before the agreement becomes effective. Also, before a lender is obliged to fund, or before a borrower is entitled to draw (Projects RH). They cover corporate authority, sponsor equity, project agreements, permits, land rights, insurance, security, legal opinions, the financial model, reserve accounts, hedging, construction arrangements and the absence of default or material adverse circumstance.

I read three gates separately. Conditions to effectiveness (execution of required agreements, corporate authorisations, legal opinions, constitutional documents); conditions to first drawdown (evidence of sponsor equity, insurance, completed security, project accounts, permits, construction contracts, technical certifications). In addition, Conditions to subsequent drawdowns (construction progress, updated certificates, covenant compliance, cost-to-complete, updated budgets, absence of default).

Corporate conditions get heavier with joint ventures, offshore holding companies, government shareholders or complex SPV (special purpose vehicle) structures. Capital becomes available when the agreed funding conditions are satisfied, not when the project needs the money. I apply that discipline through how to reach FID on a SAF project.

What this means for you: I write every condition as a dated evidence item before I sign. A condition I cannot picture as a document on a specific date will be argued after financial close.

The funding schedule: tranches, escrow, fees and use of proceeds

Sponsor equity is itself a condition. Lenders may require an agreed amount of equity invested before debt is drawn, or equity funded on a contribution schedule, evidenced by amount committed. Amount injected, source of funds, shareholder approvals, shareholder loans. In addition, compliance with the agreed debt-to-equity arrangements (Projects RH).

On my side the same pattern appears as staged funding: an offering period with an extension option, escrow while a minimum subscription is raised, funds returned if the minimum is not reached. In addition, a possible restriction on use of proceeds (Carofin, a page originally published in 2018 and updated in 2025). Fees come too: an arrangement fee may be payable. In addition, the investor’s due diligence and legal expenses are usually reimbursed whether or not the deal closes (Squire Patton Boggs, Carofin).

The delay pattern to fear: a delayed condition leads to a delayed drawdown, then a delayed contractor payment, procurement delay, construction delay. In addition, additional cost (Projects RH).

What this means for you: I ask who holds each gate. If the investor holds the extension option, the escrow release and the use-of-proceeds restriction, my cash timing is their decision.

Control: reserved matters, vetoes and your own budget

External passive investors typically ask for veto rights over changes to share capital and new share classes, and the list can extend to disposing of capital assets or taking on debt. The extent depends on the shareholdings held (Squire Patton Boggs, undated). A minority investor will also want a written list of reserved matters. The areas the company cannot carry out without consent. Also, the mirror question for me is how far that list reaches into a feedstock supply contract, an offtake (the contract under which a buyer takes the plant’s output), or the approved budget.

Information rights sit in the same package: periodic financial statements plus a budget, with budgets usually subject to prior approval of investors. In addition, those rights can lapse below an agreed ownership level. Preemption rights on new issues and transfers, drag-along rights that let an agreed percentage of shareholders force a full share sale. In addition, tag-along rights sit in the same cluster (Squire Patton Boggs).

What this means for you: I count consents, not clauses. If a feedstock contract or an offtake needs a consent request, the veto list has taken over the operating business.

Offtake and feedstock conditions written into your equity

Market risk in this sector is price uncertainty when no fixed-price structure exists, vague or non-binding demand signals, short-term or small offtake agreements, offtaker creditworthiness and the risk of buyers or producers defaulting (World Economic Forum with Kearney, February 2025). At the project financing and FID phase the same report places offtake at the centre: it is meant to overcome revenue uncertainty but is hard to firm up because fuel is one of the main operating costs for an airline in a low-margin market.

On the feedstock side, investors are wary of short contracts, described as recontracting risk. In addition, of sub-investment grade suppliers, and those contracts need to be as airtight as, or more airtight than, offtake so that debt. In addition, equity can both participate (RMI, 22 March 2024, older than two years). A long binding offtake is what makes the equity story credible: the World Economic Forum cites a 14-year agreement between IAG and a power-to-liquid producer as the example that passes FID. The drafting route I use is how to secure SAF offtake agreements.

What this means for you: I read the equity conditions against my offtake and feedstock durations side by side. If the term sheet demands a contract length my counterparties will not sign, the condition is really a refusal.

What the term sheet assumes about your pathway

The same report groups the risk in four categories: policy, market, technology and feedstock, and warns they are interconnected, with policy longevity driving the willingness of buyers to sign long-term offtake (World Economic Forum with Kearney, February 2025). Its lifecycle runs from pre-feasibility and FEED through project financing and FID, construction, then commissioning and operation.

First-of-a-kind (FOAK) facilities can take up to eight years from inception to becoming operational, which collides with an investor who wants a market for the project in 5 to 7 years when it exits (RMI). At commissioning, bankable process guarantees from the process licensors and EPC (engineering, procurement and construction contract) contractors are what allow the project to progress.

The pathway decides which of my numbers are unproven: a power-to-liquid or alcohol-to-jet file is tested on integration. In addition, delivery risk, a HEFA (hydroprocessed esters and fatty acids) file on feedstock traceability. In addition, competition for the same used cooking oil. I compare the structures in e-SAF project finance.

What this means for you: I check whether my technology choice is the reason a condition exists. If it is, I look for the instrument that absorbs that risk instead of a clause that only transfers it.

Exit economics, return requirements, and what lenders will ask of your equity

A liquidation preference puts the investor at the top of the list to receive cash on a liquidation or deemed liquidation, typically a merger or asset sale and sometimes an initial public offering (Squire Patton Boggs, undated).

Investors generally also want their preference shares to participate alongside ordinary shares once the preference is paid. Sometimes with a cap. A fixed dividend, where there is one. Typically sits around 6 to 12 percent of the amount invested and may accumulate. A redemption right, a buyback at the original purchase price plus accrued unpaid dividends, can be treated as debt under some accounting standards. Anti-dilution comes as a full ratchet or a weighted average. Full ratchets give the investor the strongest protection and are generally resisted.

Return expectations are not generic. SAF project finance participants put a private equity-backed energy transition fund at around 15 percent levered equity internal rate of return (IRR) for operating projects, above 20 percent when there is development risk, and venture capital north of 40 percent for pre-offtake projects with novel technology configurations (RMI, 22 March 2024).

My equity is also what a lender tests: sponsor equity evidence, contribution schedule. In addition, debt-to-equity arrangements are conditions to the debt drawdown itself (Projects RH). The structuring route I work from is SAF joint venture structuring.

What this means for you: I compare the return the investor asks for with the return my offtake can support. When those numbers do not meet, the gap appears as a preference, a condition or a veto, on the first page rather than at closing.

How I would run this if it were my file

I read the term sheet against the closing documents rather than the pitch. With legal counsel specialised in private finance in the room from the first draft (Carofin, originally published in 2018 and updated in 2025).

Then the sequence I insist on: convert every vague condition into an objective evidence item with a named document. In addition, a date; push anti-dilution from a full ratchet to a weighted average, because full ratchets are the off-market marker; cap warranty exposure, where a de minimis limit. An aggregate cap around 5 to 10 percent of the amount invested, and a claim period of seven years for tax. In addition, two years for other claims are customary; keep the reserved matters list short enough that I can still contract without a consent request; and test the package against a first-of-a-kind timeline of up to eight years rather than a five-year exit assumption.

Where the risks are genuinely first-of-a-kind, the World Economic Forum’s levers point at grants for early-stage risk, guarantees and insurance instruments. Strategic industry investors, long-term offtake and blended finance, in that order of who absorbs what. A term sheet that prices every risk onto you is a transfer, not a term sheet.

What this means for you: I sign only when every condition has an owner, a document and a date. In addition, only when the risk I am asked to carry is one I can carry.

Sources

Frequently asked questions

A term sheet is a framework rather than an obligation to complete the investment: both parties can generally walk away before the definitive agreements are signed, and it is the basis on which those documents are drafted. A few provisions survive signature, such as confidentiality, exclusivity and the payment of the investor’s fees. Holding one means neither financial close nor cash.

Conditions to effectiveness determine whether the financing agreement becomes effective at all: required agreements, corporate authorisations, legal opinions and constitutional documents. Conditions to first drawdown determine whether the borrower can make the first utilisation: evidence of sponsor equity, insurance, completed security, project accounts and permits. Conditions to subsequent drawdowns attach to later utilisations: construction progress, updated certificates, covenant compliance, cost-to-complete and absence of default.

An open-ended one: conditions left to the satisfaction of the investor’s own due diligence, plus reimbursement of its expenses. On your own side, redemption rights coupled with a preferred dividend, because they can be treated as debt on the balance sheet, and a full ratchet anti-dilution clause.

The sequence runs from term sheet to credit approval to documentation to satisfaction of conditions to financial close to drawdown, and these are not equivalent milestones. A condition satisfied for financial close does not make every future drawdown unconditional: a delayed condition becomes a delayed drawdown, a delayed contractor payment, procurement delay, construction delay and additional cost.

Not sure your project would survive a credit conversation?

A short call is usually enough to see where your project stands.

If you want this clause list read against your own draft before you sign, start with investor introductions.

I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia