A ship ordered today will still be burning fuel in 2030, so the fuel question reaches me as a contract question before it reaches a shipyard as an engineering one. Here is my answer in one line: yes, ammonia as a marine fuel can be financed, but only where three things exist together, an order book for ammonia-capable ships, a port that has proven a safe transfer, and a buyer bound by a contract long enough to cover the fuel premium. I rank a case on those three before I look at the molecule. The wider molecule sits in the green ammonia guide; this page stays on the shipping door.
I will order the evidence in five moves: the ship order book, the fuel price, the vessel cost, the regional demand, and the contract I would ask a buyer to sign. Each figure carries a date, and each step answers the question a lender asks next.
In short
- Order book: 39 ammonia-capable ships were on order in August 2025, mainly carriers and bulkers, with first deliveries at late 2025 or early 2026.
- Fuel price: about 2,900 USD/tMGOe in Europe on a reading taken 17 November 2026, roughly five times marine gas oil.
- Vessel cost: newbuilds run 15 to 20 percent above conventional designs, and a retrofit can reach 60 percent of remaining ship value (2025).
- Region: 4 Mt of hydrogen demand in Southeast Asia in 2024, with ammonia at 49 percent of it and no certification scheme yet in place.
- Contract: 90 percent of traded ammonia moves on one to three year fixed-quantity contracts (2024), while a producer power contract can run 20 years.
In this article
Three things must exist before I call it financeable
I call a shipping case financeable only when an order book, a proven port transfer and a long-dated buyer contract exist at the same time. Before I use any of those words in a memo, I define them. A marine fuel is the fuel a ship burns. An ammonia-capable vessel is one built or converted to burn ammonia. A retrofit converts an existing hull instead of replacing it. Bunkering is refuelling a ship. Energy density is how much space a fuel takes for the same energy. Port readiness is how far a port is from safe ammonia transfers. An offtaker is the party bound to buy. Take-or-pay makes that buyer pay for the contracted volume whether it lifts the cargo or not. Book-and-claim lets a claim travel through a supply chain without moving the molecule. Levelised cost spreads the lifetime cost of a plant across the tonnes it makes.
Context I keep in view: in 2025, more than half of the food grown worldwide relied on ammonia fertilisers made in more than 60 countries, which is why shipping is the youngest of the four doors ammonia has to walk through.
What this means for you: I do not score a project on tonnes of nameplate output. I score it on whether those three doors stand open together, because a lender signs a contract, not a molecule.
The order book is a list of intentions
In August 2025, 39 ammonia-capable ships were on order, mainly ammonia carriers and bulkers, against a conceptual state of play in 2020, with first deliveries at late 2025 or early 2026. Dual-fuel two-stroke engines began delivering from 2025 and 2026, one four-stroke engine carries approval from several classification societies, and demonstration vessels and tugs have run in Japan and China (2025). The regulatory frame runs on classification rules introduced in 2021 and updated each year, plus interim guidelines from the IMO in 2024; binding amendments to the fuel code are unlikely before 2032.
A list of orders is not a fleet, and a delivery is not an operating route. A hull without a bunkering plan sits at the same risk level as a port without a ship.
What this means for you: I treat ordered ships as evidence of shipowner intent and never as demand for your tonnes. The route has to exist before the tonnage does.
The fuel price is the whole case
On the DNV paper’s reading of the market, consulted 17 November 2026, green ammonia trades at about 2,900 USD per tonne of marine gas oil equivalent in Europe, about five times the price of marine gas oil. Its forecasts carry the fuel to 1,000 to 1,900 USD/tMGOe by 2050, approaching parity with marine gas oil only under a carbon price. The same paper states the position plainly: the toughest challenge hinges on the cost barrier, in particular the fuel cost, which remains too high. What narrows that gap is the EU emissions trading system from 2024, the FuelEU Maritime rule from 2025 and a possible mechanism from the IMO.
Carbon pricing, not the molecule, is what I model first (2026).
What this means for you: I build the case on the spread between a carbon-inclusive marine gas oil price and your delivered ammonia price, and I show the buyer the same spread I show the lender.
The ship costs more too
Ammonia-fuelled newbuilds typically cost 15 to 20 percent more than conventional designs, with study premiums of 16 percent on a large containership, 19 percent on an Aframax tanker and 15 percent on midsize gas carriers; on older bulkers a retrofit can reach 60 percent of the remaining ship value (2025). Ammonia needs nearly triple the volume of marine gas oil for the same energy, so range and cargo space become the design trade, and a shipowner weighs the sustainable maritime fuels on that basis before the hull is drawn.
Port readiness is rated 6 to 7 at two major ports, safe transfer demonstrations ran in six countries by 2025, a large pilot transfer was carried out in 2025, and the first dedicated bunkering vessel was ordered for 2027. On the capital side, maritime fuel bankability turns on whether the vessel premium sits inside the same contract that carries the fuel.
What this means for you: I ask the shipowner for the premium and the bunkering plan in the same document, because a lender prices the hull and the fuel as one exposure.
Where this region sits
On the December 2025 Southeast Asia briefing, regional hydrogen demand reached 4 Mt in 2024, with ammonia at 49 percent of it, and the split by country ran Indonesia 35 percent, Malaysia 22 percent, Viet Nam 15 percent and Singapore 12 percent. Malaysia held 73 percent of regional ammonia exports and the region 17 percent of world ammonia exports in 2023. Announced regional projects equal 12 percent of current demand while only 6 percent of announced capacity has reached final investment decision. Nearly 11 Mtpa of potential sits below 6 USD/kg by 2030, mostly in Indonesia, and no certification scheme is yet in place, with work under way in three countries. That is the market the Southeast Asia and Singapore market page maps.
What this means for you: I read regional demand as a floor under a shipping contract, never as a signed buyer. The port that will bunker your fuel and the authority that will certify it should sit inside the same region.
The contract that carries the vessel
According to BloombergNEF and Climate Technology Coalition in January 2024, 90 percent of traded ammonia moves on contracts of one to three years with fixed quantity and a take-or-pay structure, indexed to Tampa. Buyers used to a gas-indexed price rarely commit beyond a few years, while a producer may face a 20 year power purchase agreement, and the green price can be two to three times grey ammonia. Of 185 tracked projects, 45 hold offtake agreements and 15 are under construction or financed. One net zero scenario puts ammonia consumption by shipping at 178 million tonnes a year in 2050.
An order book that arrives through newbuild decisions and bunker infrastructure cannot be underwritten on the terms of a spot cargo (2024). The marine fuel offtake structure is where I write that down.
What this means for you: I take the buyer’s tenor, index and quantity clause to the lender before I take the price, because a price without a tenor is a forecast.
How I would structure it
The Hydrogen Council and McKinsey roadmap of November 2025 puts demand pooling first: it reduces counterparty risk, creates bankable offtake volumes and moves a producer from front-end engineering design to final investment decision. Certification and book-and-claim let a scope 3 claim travel through a global supply chain without moving the molecule. Low-carbon ammonia could add 1 to 3 percent to the finished product cost while cutting product emissions by up to 30 percent. I write two things into the Southeast Asia offtake structure and hold the rest.
- The clause I ask for first: volume, tenor, price formula and delivery point, in one schedule the lender can model without asking me what I meant.
- The proof I withhold: the environmental claim. Where certification does not exist yet, I sell the molecule and refuse to sell the claim.
What this means for you: I would rather sign a shorter contract with a verifiable claim attached than a longer one carrying a claim no authority will back.
The four checks I run before I quote
Check one: the Oxford study of October 2024 models production cost of green ammonia at 407 to 1,239 USD per tonne in 2024, falling to 262 to 696 USD per tonne by 2030 and 202 to 482 USD per tonne by 2050, with the cost of electricity as the decisive factor and policy support the condition of any significant reduction.
Check two: announced low-carbon ammonia capacity passed more than 300 Mtpa in May 2025 against 200 Mtpa of the conventional market, while only 48 projects and 15 Mtpa sit at final investment decision (2025).
Check three: a firm offtake agreement is not a delivery. Of the 15 Mtpa at final investment decision, 1.3 Mtpa was online in May 2025, and that online volume came largely as retrofits.
Check four: 35 GW of electrolysers are expected worldwide by 2030 (2025), and the power price behind them sets the floor under every tonne you sell.
What this means for you: I quote a price only after those four checks clear, because a number that survives them is the only number worth putting in front of a lender.
Sources
- DNV, Ammonia as a marine fuel: Prospects and challenges https://www.dnv.com/expert-story/maritime-impact/ammonia-as-a-marine-fuel-prospects-and-challenges, n.d., consulted 17 November 2026.
- Oxford Institute for Energy Studies, Fueling the future: A techno-economic evaluation of e-ammonia production for marine applications, OIES Paper ET40 https://www.oxfordenergy.org/wpcms/wp-content/uploads/2024/10/ET40-Fuelling-the-future-final.pdf, October 2024.
- BloombergNEF and Climate Technology Coalition, Scaling Up Hydrogen: The Case for Low-Carbon Ammonia https://assets.bbhub.io/professional/sites/24/CTC-whitepaper_Ammonia_Final.pdf, January 2024.
- Hydrogen Council with McKinsey & Company, Fertilizing the future: A roadmap to scale low-emission ammonia fertilizers https://hydrogencouncil.com/wp-content/uploads/2025/11/Fertilizing-the-future-FINAL.pdf, November 2025.
- IEA, Global Hydrogen Review 2025, Southeast Asia, 9 December 2025 https://iea.blob.core.windows.net/assets/745a259b-9cb7-4e1d-9ba1-a8b63d1eaae8/GHR2025_SEA_Webinar.pdf, 2025.
Frequently asked questions
Is ammonia a realistic marine fuel today?
Partly. In August 2025, 39 ammonia-capable ships were on order with first deliveries at late 2025 or early 2026, safe transfer demonstrations ran in six countries by 2025, and binding fuel code amendments are not expected before 2032. I read that as a working pilot phase in which hulls and ports move first, and priced cargo moves last (2025).
Why does ammonia need so much tank space?
Because its energy density is poor: ammonia needs nearly triple the volume of marine gas oil for the same energy, which cuts range and cargo space and pushes the design toward dual-fuel capability and shorter bunkering intervals rather than a like-for-like swap of the fuel tank (2025).
What decides whether a shipowner orders ammonia-capable vessels?
The economics of the vessel and the fuel. Newbuilds cost 15 to 20 percent more than conventional designs, a retrofit on older bulkers can reach 60 percent of remaining ship value, and the fuel cost is named as the toughest remaining barrier. A premium paid once at the yard is easier to carry than a premium paid on every tonne across 20 years (2025).
How do I price ammonia inside an offtake?
I price the molecule against a formula the lender can model, with a take-or-pay volume, a defined delivery point and a tenor long enough to cover the premium, then I check the certification before I sell the claim. Where certification does not exist yet, I price the claim at zero and say so in the term sheet rather than leaving it implied (2024).
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If you want to see how offtake agreements work when a shipping buyer and a producer hold the same volume, I can walk your draft schedule line by line before it reaches a lender.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.