Biogas Project FID Readiness Checklist
10 min read · Sep 22, 2025 · By Alex
FID readiness for a biogas project, where FID is the final investment decision a board takes to commit capital, is a documentary test, not a technical one: the decision can be taken when the feedstock, the permits, the cost line, the offtake, the support scheme and the finance plan are each evidenced by a dated document. On 2020 data, 70 percent to 95 percent of total biogas cost sits in the digester, so the construction package and its fixed price are the first thing I want signed, and the levelised cost of bioenergy electricity was USD 0.087/kWh in 2024, which sets the revenue conversation. I write for developers in the biogas, biomethane and biofuels industry who need to know this quarter whether a biogas project FID can be taken or has to wait a year.
I take the six evidence blocks in the order a board reads them: feedstock and site, permits and tariff, cost line and technical scope, offtake and revenue, support and finance, then delivery capability, and I close with the ten tests and the pack I assemble. Throughout, biogas means the gas produced by anaerobic digestion, the breakdown of organic matter without oxygen, and biomethane means that gas purified to grid quality.
In short
- Documentary test: six evidence blocks, each with a dated document.
- Capital weight: 70 percent to 95 percent of total cost sits in the digester on 2020 data.
- Cost reference: bioenergy electricity cost USD 0.087/kWh in 2024, 19 percent above 2023.
- Support evidence: in most reporting countries, viability has needed investment support or subsidies.
- Regional timing: almost 80 PJ produced in 2025 against potential of almost 65 bcme.
In this article
What FID readiness means for a biogas plant
A project reaches FID when one file answers, for each of six blocks, what the document is and when it was dated. The six blocks are feedstock and site, permits and tariff, cost line and technical scope, offtake and revenue, support and finance, and delivery capability. Feedstock is the organic material the plant converts; an offtake agreement is the contract under which a buyer takes what the plant produces; delivery capability is the team and the schedule that turn a signed contract into a running plant. I built this checklist to stop a project from holding a decision meeting it cannot close, because a meeting without documents produces a date, not a decision.
What this means for you: treat FID as a filing exercise with a deadline. If one block has no dated document, the answer to whether you can decide this quarter is no, and the work of the quarter is to obtain that document rather than to book the meeting.
Block one: feedstock and site
The first block answers one question: where does the material come from and what does it cost. In the IEA biogas and biomethane outlook published in 2020, 70 percent to 95 percent of total biogas cost goes into installing biodigesters, and the rest covers collecting and treating the raw material.
Feedstock can arrive at zero cost or at a negative price, meaning the producer pays to be rid of it, while a gate fee, the fee charged to accept a material, reaches USD 100/tonne for some agricultural materials in some regions in 2020. Production cost in 2020 runs between USD 2/MBtu and USD 20/MBtu worldwide, around USD 9/MBtu in Southeast Asia, and below USD 3/MBtu for landfill gas.
The evidence I want is a signed supply agreement carrying a volume, a quality range and a price mechanism, plus a site with a route to a grid or gas connection. The economics of the feedstock and the choice of plant configuration move together, so I read them in one file: feedstock economics and plant configuration.
What this means for you: if the supply agreement carries no volume or no price mechanism, the cost line behind it is an estimate, and an estimate cannot carry a final investment decision.
Block two: permits, tariff and grid
A feed-in tariff, a guaranteed price paid for electricity fed into the grid, is only revenue when it is written down, dated and attached to a quota. I read the 2020 policy brief from the Energy Studies Institute at the National University of Singapore, and it records three different outcomes in the region.
Malaysia required existing and new mills to install biogas capture by 2020 under its transformation programme, and it revised the purchase tariff in 2014 from RM 0.32/kWh to RM 0.40/kWh. Thailand opened its small power producer scheme in 2002 at THB 2.8/kWh and added an incentive of up to THB 0.50/kWh in 2006. Indonesia introduced a tariff in 2014 to sell to the state utility, but the low rate, the high connection cost and the thin base load in remote regions undercut feasibility.
The evidence I want is the tariff decision in writing, the connection offer, the environmental permit and the quota position, because a tariff without a quota is not revenue. I set the tariff history out in the Malaysian biogas feed-in tariff.
What this means for you: ask for those four documents before you price the revenue line, and treat any tariff you cannot see in writing as zero in the model until it arrives.
Block three: the cost line and the technical scope
The cost line has two parts: capex, the money spent to build the plant, and opex, the money spent to run it. I take the cost line from the IRENA cost review published in 2025, which puts the global weighted average total installed cost of bioenergy projects commissioned in 2024 at USD 3 242/kW, 16 percent above the 2023 average of USD 2 795/kW.
In 2024 the same review records USD 1 858/kW and USD 0.065/kWh in India, USD 2 180/kW and USD 0.066/kWh in China, and USD 3 172/kW and USD 0.118/kWh in Brazil. Variable operation and maintenance, covering replacement parts, incremental maintenance and ash disposal, averages around USD 0.004/kWh in 2024.
The evidence I want is an EPC price, meaning the engineering, procurement and construction contract, with a boundary statement, a schedule with a completion date, and a commissioning test that defines completion. My feasibility and financial model work starts at that boundary, because a price without a boundary cannot be compared with any published benchmark.
What this means for you: fix the boundary first, then compare with published installed cost, and treat any gap you cannot explain as scope you have not yet priced.
Block four: offtake and revenue
I take this from the IEA Bioenergy Task 37 country report of September 2024, which states that in most, if not all, reporting countries production has depended on investment support or subsidies to be financially viable. On end 2022 data in that same 2024 report, the United Kingdom pays an indexed tariff over 15 years in three tiers: 5.51 p/kWh on the first 60 GWh injected, 3.53 p/kWh on the next 40 GWh, and 1.56 p/kWh beyond.
In the same 2024 report, Switzerland usually finances an installation over a 20-year repayment period, and its investment cost compensation covers 50 percent of the costs directly linked to energy production. Digestate, the solid or liquid residue left after digestion, carries most of the nutrients and sells as an amendment or fertiliser, so on 2024 data I ask for a buyer and a price before I count it as revenue.
The evidence I want is an offtake with a volume, a tenor, meaning how long the contract runs, and a price formula, plus a written statement of what the support pays and until when. I set the negotiation sequence out in how to secure offtake agreements.
What this means for you: an offtake without a tenor is a letter of interest, and a support payment without an end date is a number you cannot put in a model.
Block five: the finance plan and the counterparties
The finance plan is the last block because it consumes the other five. According to the IEA renewables report published in 2026, Southeast Asia produced almost 80 PJ of biogases in 2025 against a feedstock potential of almost 65 bcme, where bcme is billion cubic metres equivalent and one bcme equals 36 PJ on 2026 data.
That same 2026 report names Thailand, Indonesia and Malaysia as the region’s most relevant markets and states that the pace of growth will depend on supportive policies in the region.
The evidence I want is a finance plan with the equity identified, the debt providers approached, the support application filed and a closing date that sits before the construction start.
Development finance institutions, or DFIs, are public lenders that fund infrastructure where commercial debt is thin, so I record who has been approached and what they asked for; the counterpart list I work from is development finance institutions. A document is bankable when a lender accepts it as evidence without asking for a rewrite.
What this means for you: write the closing date and the construction start date on the same page, and if the two dates collide, the FID date moves, not the construction date.
The ten tests I run before I sign off FID readiness
I run these ten tests in order before I sign anything:
- Feedstock volume contracted.
- Feedstock quality range defined.
- Site secured with a connection route.
- Tariff or quota in writing.
- Environmental permit issued.
- Construction price with a boundary.
- Operating cost line dated.
- Offtake with a tenor and a price formula.
- Support scheme described in writing with its end date.
- Finance plan with the equity and the debt named.
I score the project on the ten and refuse the decision when two are open. A project at eight of ten is not late; it is a project with two documents to obtain, and I would rather move the meeting than decide on a block that is still verbal.
What this means for you: run the ten tests in order, write the score at the top of the page, and let the two open items set the agenda for the next month.
The FID pack I assemble
I assemble the pack in the order a board reads it: a one page summary of the six blocks, the contract schedule, the cost line, the model with its dated inputs, the permit file and the finance plan.
The pack is finished when a reader who was not in the negotiation can answer, for every number, where it comes from and until when it holds. That test is the whole point of the checklist: a decision taken on documents survives the meeting, and a decision taken on memory does not.
What this means for you: build the pack as you go rather than at the end, because the six blocks that are already dated are the six blocks you can defend in the room.
Sources
- IEA, Outlook for biogas and biomethane, 2020.
- IRENA, Renewable power generation costs in 2024, 2025.
- Energy Studies Institute, Producing Biogas from Palm Oil Mill Effluent in Southeast Asia, 2020.
- IEA Bioenergy Task 37, A perspective on the state of the biogas industry in 12 member countries, 2024.
- IEA, Renewables 2026, chapter Biogases, 2026.
Frequently asked questions
How many documents does a biogas FID need?
Six evidence blocks: feedstock, permits and tariff, cost line and technical scope, offtake, support and finance, and delivery capability. Each block needs one dated document, and the decision can be taken when the six are in the pack.
Why does the digester dominate the FID file?
Because on 2020 data 70 percent to 95 percent of total biogas cost goes into installing biodigesters. That concentration means the construction package, its fixed price and its completion test carry most of the risk the board is asked to accept.
What has to be in writing on the support side?
The instrument, the rate or the compensation share, the period it runs and the end date. Switzerland, for instance, on 2024 data, compensates 50 percent of the costs directly linked to energy production and plants are usually financed over a 20-year repayment period, which gives a schedule a board can read.
What stops a biogas project from reaching FID?
A missing block, most often an offtake without a tenor or a tariff without a quota. Cost evidence is rarely the obstacle once a boundary is fixed, because installed cost benchmarks are published every year.
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If you want the ten tests run against your own project, I take the pack through the six blocks and mark what is missing: my project finance work.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.