Fischer-Tropsch for PtL: What the Reactor Chain Actually Does
10 min read · Sep 26, 2025 · By Alex
Power-to-liquid turns renewable hydrogen and captured carbon dioxide into a liquid fuel in three moves: it converts CO2 into the carbon monoxide the reactor needs with reverse water gas shift, it builds long hydrocarbon chains in the synthesis reactor, and it upgrades the syncrude by hydrocracking, isomerization and distillation. In 2016 terms, about 50 to 60 percent of what comes out of the reactor is already in the jet range by energy, and the weakest documented step sits at readiness level 6. That is the Fischer-Tropsch PtL chain I dissect here, and it sits inside the wider power-to-liquid branch, where each move lands on my project rather than on the equipment supplier. Nothing below is my own estimate: every figure carries its source and its year.
I walk it in the order the project feels it: what has to happen before the reactor, what happens inside it, and what each stage asks of my contracts, my power supply and my buyer. Then I set out the readiness ladder, the money trail, and the order I work in.
In short
- Three moves: 2016: CO2 becomes CO by reverse water gas shift, the reactor chains it, then hydrocracking, isomerization and distillation finish it.
- Jet share: 2016: 50 to 60 percent of reactor output is jet range by energy, with approved blends to 50 percent after 2009.
- Weak step: 2016 table: reverse water gas shift at readiness level 6, solid oxide route at 5, CO2 from air at 6.
- Efficiency: 2016: 38 to 63 percent well-to-tank, depending on CO2 source and electrolyser.
- Load factor: 2023: cost rises fast below 40 percent, and at 50 USD per MWh electricity alone adds 25 to 35 USD per gigajoule.
In this article
What the chain commits me to
Power-to-liquid makes liquid fuel from renewable hydrogen and captured CO2. Fischer-Tropsch synthesis is the catalytic step that builds long hydrocarbon chains from carbon monoxide and hydrogen, reverse water gas shift is the step that turns CO2 into the CO the reactor needs, syncrude is what the reactor outputs before refining, and hydrocracking, isomerization and distillation are refinery steps used today at large scale. The German Environment Agency reported in 2016 that Fischer-Tropsch synthesis requires carbon monoxide, that in the Fischer-Tropsch PtL case CO2 from concentrated sources or air is converted to CO by reverse water gas shift, and that the share of Fischer-Tropsch products suitable for jet fuel use is about 50 to 60 percent by energy. Technology readiness level is the ladder I use to rank steps, from laboratory proof to routine operation; on the 2016 ladder the weakest link sits at 6.
What this means for you: I am committing to four pieces of equipment and one supply chain, and the item at readiness level 6 is where I spend diligence first, because it governs whether the rest can run.
Getting to carbon monoxide without a fossil plant
In 2016 the CO2 sources are extraction from air, concentrated renewable sources such as biogas upgrading, sewage and ethanol plants and exhaust gases, and industrial exhaust from steel and cement. In the 2016 process analysis, co-electrolysis of steam and CO2 in a solid oxide cell produces hydrogen and carbon monoxide in a single step and removes the reverse water gas shift step, but co-electrolysis is subject to further research. Also in 2016, with high temperature electrolysis, waste heat of 220 to 250 degrees Celsius from the exothermic Fischer-Tropsch synthesis is reused for steam generation, which lowers the electricity demand. The IEA direct air capture report of 2022 counts 18 facilities operating in Canada, Europe and the United States, the first large-scale plant of up to 1 Mt CO2 per year in advanced development, and capture costs for a plant built today between 125 and 335 USD per tonne of CO2, with potential below 100 USD per tonne with deployment and innovation.
What this means for you: I pick the carbon capture and storage line before I pick the reactor, because the shift step is fixed chemistry while the source is a negotiation I can still reopen.
What the hydrogen side has to deliver
An electrolyser is the machine that splits water with electricity to produce hydrogen. The IEA e-fuels report of 2023 states that large-scale commercial electrolysers operate today at efficiencies of 65 to 70 percent on a lower heating value basis, that the downstream synthesis step is 65 to 85 percent efficient depending on the end product, so the overall thermal efficiency from electricity to fuels ranges from 40 to 60 percent. In that 2023 analysis around 35 percent of the electrical energy is lost to low temperature heat during electrolysis, and the levelised cost of e-fuels starts to increase very quickly when the plant load factor drops below 40 percent. At 50 USD per MWh in the same 2023 figures, the electricity price alone contributes 25 to 35 USD per gigajoule of finished fuel.
What this means for you: I size the green hydrogen electrolyser against the load factor my power contract sustains, not against peak capacity, because below 40 percent in the 2023 modelling the fuel price moves faster than any downstream saving.
What the outlet has to accept
In 2009 Fischer-Tropsch synthetic paraffinic kerosene passed the ASTM D7566 procedure and can now be used in blends of up to 50 percent with conventional jet fuel. A drop-in fuel is one that works in existing aircraft and fuelling systems without modification, and this 2009 approval covers blends rather than neat fuel. The 2016 Annex A1 definition covers synthesis gas converted via the Fischer-Tropsch process using iron or cobalt catalyst, which includes power-to-liquid fuels made by this route. ASTM D1655 and DEF STAN 91-91, read in 2016, evolved on the assumption of fuel from crude oil. In 2016, oligomerization can process the C3 and C4 fraction to raise the share of liquid hydrocarbons and meet Jet A-1 specifications, so the jet share becomes a sustainable aviation fuel pool. In 2016, greenhouse gas emissions for production, transport and dispensing are about 1 g CO2 equivalent per MJ of final fuel with renewable electricity and CO2.
What this means for you: I confirm the blend my buyer must buy before I size the upgrading block, because the specification, not the reactor, decides what leaves the gate.
What the readiness ladder looks like
In the 2016 readiness table the power-to-liquid route sits between 5 and 8, Fischer-Tropsch with low temperature electrolysis sits at 6 with reverse water gas shift as the critical element, Fischer-Tropsch with high temperature electrolysis sits at 5 with the solid oxide cell as critical element, and CO2 extraction from air sits at 6. In the same 2016 table, the methanol route with low temperature electrolysis sits at 8 with ASTM approval and final conversion as the critical elements. IRENA and the Methanol Institute record in 2021 that the e-methanol synthesis step is very similar to fossil methanol synthesis and therefore mature at readiness level 8 to 9, which is why this ladder has two different tops. I ask an independent technical review to grade the critical element, not the route name.
What this means for you: I need the reviewer to score the element I am actually buying risk on, because a route at 8 and a route at 5 in the same 2016 table need different contract terms.
What the money has decided so far
The IEA Global Hydrogen Review 2026 reports that capital spending on low-emissions hydrogen projects reached nearly 7 billion USD in 2025, nearly double the 2024 level and equal to 0.7 percent of global investment in energy supply. In that 2026 review, over 85 percent of investment targets existing hydrogen uses in industry and refineries or hydrogen-based fuels. Venture capital for hydrogen fell from a 13 percent peak in 2023 to 4 percent in 2025, with aviation attracting almost 25 percent. Hydrogen use in industry and synthetic hydrocarbons is only now moving to first-of-a-kind projects, more slowly than more modular end-use sectors such as transport. That is the pattern I take into a power-to-liquid investment decision: money follows established demand, and my route sits in the slower column.
What this means for you: I budget for the first-of-a-kind premium instead of assuming the 2025 investment wave reaches a synthetic hydrocarbon plant on its own.
How I decide for a specific project
Four questions settle this route for one project, and I answer them in this order.
- The blend: what my buyer is obliged to buy, given the 2009 approval of blends up to 50 percent with conventional jet fuel.
- The CO2 source: the line I can contract for the life of the plant, whether air or a concentrated renewable source in 2016 terms.
- The weakest step: reverse water gas shift at readiness level 6 in 2016, or the solid oxide cell at 5 for the high temperature route.
- The load factor: the hours my power contract can actually sustain, since the 2023 modelling shows cost rising fast below 40 percent.
What this means for you: I accept a readiness level of 6 when the steps behind it are proven at large scale, because hydrocracking, isomerization and distillation already run in refineries, so the unresolved risk sits in one element rather than in the whole chain. The four answers then go into one page before any model exists.
The order I work in
The 2016 well-to-tank efficiency range of 38 to 63 percent depends on the CO2 source and the electrolyser, where well-to-tank efficiency is the share of primary energy that survives to the fuel delivered, and a concentrated CO2 source adds about 10 percentage points over direct air capture; the 2023 modelling shows cost rising fast below a 40 percent load factor. In 2016 the difference in efficiency between the Fischer-Tropsch route and the methanol route is negligible, so the spread is a sourcing and electrolyser decision rather than a route decision. Also in 2016, a short-term figure of 45 percent applies to low temperature electrolysis with CO2 from biogas upgrading, while about 42 percent applies to high temperature electrolysis with CO2 taken from air. In 2023, hours available decide the load factor and therefore the weight of the investment in the levelised cost.
What this means for you: I work in this order. First I fix the buyer’s specification and the CO2 contract, then I take the weakest step with its critical element into technical review, and only then do I test the power contract against the load factor the plant can actually hold.
Sources
- German Environment Agency, Power-to-Liquids: Potentials and Perspectives for the Future Supply of Renewable Aviation Fuel https://www.bauhaus-luftfahrt.net/fileadmin/user_upload/Publikationen/161005_uba_hintergrund_ptl_barrierrefrei.pdf, 2016.
- IRENA and Methanol Institute, Innovation Outlook: Renewable Methanol https://www.irena.org/-/media/Files/IRENA/Agency/Publication/2021/Jan/IRENA_Innovation_Renewable_Methanol_2021.pdf, 2021.
- IEA, The Role of E-fuels in Decarbonising Transport https://iea.blob.core.windows.net/assets/9e0c82d4-06d2-496b-9542-f184ba803645/TheRoleofE-fuelsinDecarbonisingTransport.pdf, 2023.
- IEA, Direct Air Capture: A key technology for net zero https://iea.blob.core.windows.net/assets/78633715-15c0-44e1-81df-41123c556d57/DirectAirCapture_Akeytechnologyfornetzero.pdf, 2022.
- IEA, Global Hydrogen Review 2026, Investment and innovation https://www.iea.org/reports/global-hydrogen-review-2026/investment-and-innovation, 2026.
Frequently asked questions
What does Fischer-Tropsch do in a power-to-liquid plant?
It converts carbon monoxide and hydrogen into long hydrocarbon chains. The carbon monoxide first comes from CO2 through reverse water gas shift, and the reactor output, called syncrude, is then upgraded by hydrocracking, isomerization and distillation into finished fuel (2016). I treat that refinery block as part of the plant rather than as an optional add-on, because without it the output stays a raw liquid that no buyer can take.
What is the weakest step in the chain?
Reverse water gas shift, which sits at readiness level 6 in the 2016 table, while the solid oxide electrolysis route sits at 5 and CO2 extraction from air at 6. The critical element attached to each of those scores is what I ask a reviewer to grade, because the route average hides the single part I am actually buying risk on in the first place.
How much of the output can go to aviation?
About 50 to 60 percent of the reactor output is already in the jet range by energy, and the approved blend with conventional jet fuel goes up to 50 percent after the 2009 approval (2016). That is a blend limit, so I never present it as permission to use neat fuel, and I size the upgrading block around what the specification actually allows me to sell.
How do I start for my own project?
I fix the buyer’s specification, the CO2 contract, the weakest step with its critical element, and the load factor the power contract sustains, in that order (2016, 2023). Each answer fits on one line, and I write all four before any financial model exists, because those four are the commitments that survive the model and reach the lender unchanged.
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If this chain is heading into a feasibility study, my technology maturity and scale up support work starts at the critical element of your route and ends with the four answers above, written down, dated and ready to defend.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.