Hydrogen FID Readiness Checklist: What I Check Before the Decision

10 min read  ·  Jan 2, 2026  ·  By Alex

hydrogen fid readiness checklist

A hydrogen project is ready for the final investment decision. The point where the board commits the funds, when committed capital sits behind contracted revenue and the risk allocation survives a lender’s review. In addition, the published record shows how rare that is: in January 2026 only around 13 percent of contracted volumes were supported by fully binding offtake agreements, and in 2025 only 9 percent of announced projects had secured committed investment. Meaning capital the project has actually secured rather than announced. I hold every pre-FID dossier against that standard before I recommend a date. In addition, the wider framing of the work sits in how to finance a hydrogen project. What follows is the hydrogen FID checklist I run, ordered the way a lender meets it.

I do not run these checks as a formality. Each one answers a question a lender will ask anyway, and a dossier that fails any single one is not ready for committee. Whatever the announcement says.

In short

  • Committed money: in 2025 only 9 percent of announced projects had secured committed investment, against 0.5 percent in emerging economies.
  • Public layer: in December 2025 the public money claimed had to be matched to its actual stage of approval.
  • Offtake: the record is 10 to 15 years with take-or-pay at 60 to 80 percent, as reported in August 2025.
  • Buyer: in 2024 only 10 percent of announced projects had identified a buyer.
  • Money stack: by 2030 the world needs 1 000 billion USD, of which 335 billion USD was still unallocated in December 2024.
Facebook
Twitter
LinkedIn

In this article

What readiness actually means

A lender does not fund ambition, it funds cash flows. The Oxford Institute for Energy Studies review of January 2026 defines bankability as the degree to which a project is judged creditworthy and investable. Resting on its own cash flows in limited or non-recourse project finance, where lenders are repaid out of project revenue alone. The same review records that only around 13 percent of contracted volumes are supported by fully binding offtake agreements, so relatively few projects today meet the revenue-certainty conditions required for classic project finance.

  • Final investment decision: the moment the board commits the funds.
  • FEED: front end engineering design, the stage that produces the numbers behind that decision.
  • Bankability: the state in which a lender can size debt against the project’s own cash flows.
  • Committed investment: capital the project has secured rather than announced.
  • Firm offtake: a contract binding a buyer to stated volumes.
  • Take-or-pay: a clause requiring the buyer to pay for those volumes anyway.
  • Equity: the sponsor’s own capital, with the first loss tranche absorbing the first hit.
  • Senior debt: lending repaid ahead of equity in the repayment queue.
  • Development finance institution: a public or multilateral lender.
  • Blended finance: public and private capital mixed so early losses fall on the public side.

In 2024 the announced pipeline remained very large while only a small fraction of capacity was operating or past final investment decision, most of it still at an early stage of development.

What this means for you: put these definitions at the front of the dossier. That is because a lender reads the vocabulary before it reads the model.

Check one: committed money

A term sheet is not money. In 2025 only 9 percent of announced projects worldwide had secured committed investment, against 0.5 percent in emerging economies, and in 2025 the cost of capital could reach 15 percent in emerging economies. Three times the level in advanced economies.

Also, three documents answer this check: proof of equity, proof of the debt commitment, and proof that the two are aligned on the same base date. I reject dossiers where the equity proof is a sponsor statement. In addition, the debt proof is an expression of interest, because neither one is committed capital. For the regional structuring view I use regional project finance for green hydrogen in Southeast Asia.

What this means for you. Ask for dated commitments on both sides, and move the date rather than accept two documents that do not share a base date.

Check two: the public layer

Public money is a layer, not a rescue. In December 2025, 6.6 billion USD of development finance institution loans flowed between 2021 and 2025 alongside 8 billion USD invested in production in 2025, and 38 billion USD of public funding had progressed. Also, in 2025 the electrolyser stack was only 15 to 20 percent of the installed investment. Therefore, most of the money sits in process balance, construction and grid connection.

I ask which layer is claimed, grant, concessional loan or guarantee, and at which stage the request sits, submitted, approved or disbursed. I also price the balance of the plant separately, because an equipment quote is not an installed cost. My working map is how development finance institutions fund hydrogen projects.

What this means for you. Count public money as committed only when it is approved, and carry the rest of the plant without it.

Check three: the offtake contract

The contract is the debt’s collateral in all but name. Also, the Oxford Institute for Energy Studies study of August 2025 reports that hydrogen sale and purchase agreements typically run 10 to 15 years, about half the duration of first-generation international gas and LNG contracts, and that volume provisions should prioritise take-or-pay at levels of 60 to 80 percent against above 90 percent in gas and LNG, with pricing models that stay cost-plus. Netback, fixed or partly fixed in the absence of a transparent market price.

I ask for three lines: the tenor, the take-or-pay level, and who carries the price review risk. The wider mechanics sit in securing offtake agreements.

What this means for you: 10 to 15 years with 60 to 80 percent take-or-pay is the record as of August 2025. In addition, anything weaker has to be carried by more equity.

Check four: the buyer

A contract is only as strong as the name behind it. The Green Hydrogen Organisation paper of 2024 records that only 10 percent of announced projects have identified a buyer, and that of the contracted volume only 13 percent is contractually binding, 7 percent pre-contractual and 80 percent left as memorandums or unspecified. Also, the same paper reports that the NEOM project reached financial close in May 2023, was oversubscribed more than two times, and was financed on a non-recourse basis by 23 banks and investment firms at a total investment value of 8.4 billion USD.

In 2026 some European projects reached FID with contracts of 5 to 7 years, which required an equity contribution of around 50 percent to compensate for the shorter revenue certainty. How that equity was arranged is set out in how the NEOM capital stack was built.

What this means for you: settle the buyer’s credit standing or its credit support first. That is because short contracts are only financeable with more sponsor equity behind them.

Check five: the money stack

The stack has to answer hydrogen’s own problems. Also, the H2Global Foundation report of December 2024 puts the investment needed to align the hydrogen economy with net zero at 1 000 billion USD worldwide by 2030, of which 335 billion USD has yet to be allocated, with infrastructure the largest part of the gap at 190 billion USD and end-use applications at 145 billion USD. It evaluates four support instruments, the capital expenditure support. The fixed premium, the contracts for difference and the anchor capacity bookings, and its donor survey ranks market risks, political and regulatory risks and permitting and compliance risks as the most critical barriers.

In 2024 the conventional partnership, regulated asset base. In addition, special purpose vehicle approaches did not answer the specific problems of hydrogen projects.

What this means for you: choose the instrument that fits the specific risk in your dossier, and do not assume a familiar structure will price the hydrogen premium for you.

What this means for a Southeast Asian developer

The regional record changes the order of work. Also, the IEA briefing of 9 December 2025 records 4 Mt of regional demand in 2024, with ammonia taking 49 percent against refining at 31 percent and methanol at 20 percent, five regional countries holding a national strategy, no certification scheme in place with work running in three countries, announced regional projects equal to 12 percent of current demand while only 6 percent of announced capacity had reached FID. In addition, a high cost of capital named as the first barrier.

In addition, in December 2025 close to 11 Mtpa of potential sat below 6 USD/kg by 2030, mostly in Indonesia. A guarantee of origin is the certificate that tells a buyer which production the molecule came from, and without one the delivery cannot be traced into a support scheme. The regional picture sits in the regional investment picture in Southeast Asia.

What this means for you. With no regional certification scheme in place, build the guarantee of origin path into the contract before you price it.

The checks I take to committee

The last check is what the market has actually signed. Also, the IEA page of five key questions from 2025 shows firm purchase agreements cumulating to less than 2 Mtpa, only 5 percent of the production potential announced for 2030, against 9 percent of announced projects worldwide having secured committed investment and 0.5 percent in emerging economies in 2025. With the cost of capital reaching 15 percent in emerging economies.<\/p>

I run the list in one order: money first, then the public layer, then the contract, then the buyer, then the stack, then the regional conditions. In addition, only then the summary figures a committee will quote. If a step fails, I move the milestone rather than the assumption.<\/p>

What this means for you: take the checks to committee in that order. In addition, let the first failure set the next date.<\/p>

Sources<\/strong><\/p>\n

Frequently asked questions

Committed money standing behind contracted revenue. In 2025 only 9 percent of announced projects worldwide had secured committed investment, against 0.5 percent in emerging economies, and in January 2026 only around 13 percent of contracted volumes were supported by fully binding offtake agreements. When both conditions hold at the same base date, the risk allocation can survive a lender’s review, and that is the gate I apply before I recommend a decision date.

No tenor is published as a rule, so I use the record rather than a preference. In August 2025 hydrogen sale and purchase agreements were reported at 10 to 15 years, about half the duration of first-generation international gas and LNG contracts, with volume provisions expected to prioritise take-or-pay at 60 to 80 percent. Below that record I expect the sponsor to carry more of the risk through equity.

A contract that binds the buyer to stated volumes and to payment anyway, so the revenue arrives whether or not the molecule is taken. In 2024 only 13 percent of contracted volume was contractually binding, 7 percent sat in pre-contractual agreements, and 80 percent remained memorandums or unspecified. A signed agreement that either party can walk away from is not firm, and I do not count it as contracted revenue.

Because the contract and the policy wait on each other. In December 2025 only 6 percent of announced regional capacity had reached final investment decision, with no certification scheme in place and work running in three countries. Buyers hesitate until certification is credible, sponsors hesitate until buyers sign firm, and the dossier waits at that same point until one side moves first.

Not sure your project would survive a credit conversation?

A short call is usually enough to see where your project stands.

If you want the whole dossier tested before the board meets. I run project finance structuring as one review of these eight checks, ending in a written readiness note. In addition, a dated milestone list.

I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia

I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial. In addition, financial partners needed to reach FID.