We Connect Asia

Hydrogen

Hydrogen Offtake, Policy and Risk: The Three Levers That Decide FID

10 min read  ·  Jan 2, 2026  ·  By Alex

hydrogen offtake policy and risk

A hydrogen project reaches its final investment decision, the point at which the board commits the funds, when the contract, the policy framework and the risk allocation are all in place at the same time. I keep this page inside the hydrogen, power-to-liquid and e-fuels branch as the entry point to that question. The three levers of hydrogen offtake policy and risk decide that moment, and the published record shows how rarely they land together: 7 Mtpa of offtake was announced between 2021 and 2025 and only 1.6 Mtpa is firm (December 2025), while only 9 percent of announced projects worldwide have secured committed investment against 0.5 percent in emerging economies (2025).

I order what follows around those three levers, in the order I work them: the contract first, then the policy that pays for the gap and defines the molecule, then the risk allocation that decides who carries what.

In short

  • Contract: Hydrogen sale and purchase agreements typically run 10 to 15 years, with take-or-pay expected at 60 to 80 percent (August 2025).
  • Policy: Only 10 percent of announced projects have identified a buyer, and only 13 percent of contracted volume is contractually binding (2024).
  • Risk: Only around 13 percent of contracted volumes are backed by fully binding offtake agreements, so few projects meet classic project finance conditions (January 2026).
  • Public layer: 1 000 billion USD is needed worldwide by 2030, of which 335 billion USD has yet to be allocated (December 2024).
  • Regional reality: Only 6 percent of announced capacity in Southeast Asia has reached FID (December 2025).
Facebook
Twitter
LinkedIn

In this article

The three levers, and why they move together

I judge every hydrogen project on three levers at the same time, because strength in one never repairs a gap in another. The gap is measurable: 7 Mtpa of offtake was announced between 2021 and 2025 against only 1.6 Mtpa that is firm (December 2025), and only 9 percent of announced projects worldwide have secured committed investment against 0.5 percent in emerging economies (2025). I fix the vocabulary before any negotiation starts:

  • Final investment decision: where the board commits the funds.
  • Offtake: the contract under which the buyer takes the volumes.
  • Firm offtake: the contract that binds the buyer.
  • Take-or-pay: the buyer pays anyway.
  • Contract for difference: a reference price is fixed and the difference is settled.
  • Change of law: the clause that reallocates the cost of a rule change.
  • Guarantee of origin: proof of how the molecule was produced.
  • Investment grade: a credit rating of BBB- or higher.
  • Force majeure: performance is excused when events make it impossible.

What this means for you: put these definitions into the first term sheet you circulate, so contract, policy and risk can be tested in the same language instead of negotiated one after another.

Lever one: the contract

The contract carries the other two levers, so I draft it first. The Oxford Institute for Energy Studies study of hydrogen offtake agreements, published in August 2025, reports that hydrogen sale and purchase agreements typically run 10 to 15 years, about half the duration of first-generation international gas and LNG contracts. Volume provisions are expected to prioritise take-or-pay at 60 to 80 percent, against above 90 percent in gas and LNG. Pricing stays cost-plus, netback, fixed or partly fixed in the absence of a transparent market price, and electricity and gas act as index proxies for green and blue hydrogen.

Two dated agreements show what actually gets signed: in March 2025 RWE and TotalEnergies agreed 30 000 tonnes of green hydrogen per year for 15 years starting in 2030, and in May 2025 ExxonMobil and Marubeni signed about 250 000 tonnes of low-carbon ammonia per year from Baytown (August 2025). A signature is not yet a firm offtake, so I test the volume and payment obligations clause by clause in the process I use to secure an offtake agreement.

What this means for you: if the tenor falls below 10 to 15 years or the take-or-pay share falls below 60 to 80 percent, expect the equity to carry more of the revenue certainty, and price that before you circulate the draft.

Lever two: the policy that pays for the gap

The Green Hydrogen Organisation paper of 2024 sets out the support mechanisms that bridge the price gap, from hydrogen contracts for difference to cost recovery plus margin pricing and demand targets. It records that only 10 percent of announced projects have identified a buyer, and that of the contracted volume only 13 percent is contractually binding with 7 percent pre-contractual and 80 percent left as memorandums or unspecified. It also records that without an investment grade rating of BBB- or higher the parties need letters of credit, bank guarantees, parent company guarantees or retention monies.

Demand policy pulls the same lever: the first subsidy auction of the European Hydrogen Bank had its 800 million EUR budget exhausted several times over (February 2024). That is the signal I look for first in national fuel mandates, since a funded mandate creates the buyer the contract then binds.

What this means for you: before you negotiate a price, confirm that a support mechanism or a demand target in your market is funded and open, because an unfunded target leaves the whole gap sitting on the contract.

Lever two continued: the rules that define the molecule

The Oxford Institute for Energy Studies review of January 2026 describes the fragmentation a developer must navigate: European requirements on additionality and temporal matching of renewable power create a different compliance landscape from the production based tax credits of the United States. It records that lenders require clear alignment with the hydrogen strategy and the certification schemes of the target market, with pre approval for guarantees of origin, compliance with internationally recognised standards and a regulatory due diligence report.

Rules can also move against the project after the plan is fixed. Policy reversals and withdrawn incentives can undermine project economics and investor confidence (January 2026). I therefore read the definitions of renewable fuels of non-biological origin next to the rules of the buyer’s own market before I sign anything.

What this means for you: ask for the regulatory due diligence report and the pre approval for guarantees of origin in writing before you commit, because the certification scheme of the target market sets the value of every molecule you will sell.

Lever three: who carries which risk

Off-take and market risk followed by political and regulatory uncertainty are the most critical barriers to financing in emerging markets and developing economies, with technology and environmental questions handled earlier in the equity funded development phase (January 2026). Only around 13 percent of contracted volumes are supported by fully binding offtake agreements, so relatively few projects today meet the revenue-certainty conditions required for classic project finance (January 2026).

I therefore write four risks into the documents in plain words. Volume: the share of production the buyer must lift, or pay for under take-or-pay. Price: the reference index and the settlement formula behind the contract for difference. Policy: who pays when a rule changes, allocated by the change of law clause. Counterparty: what protects revenue when the buyer drops below investment grade, through letters of credit or guarantees. Force majeure stays a narrow excuse rather than a relief mechanism.

What this means for you: name the owner of each of the four risks in writing, because a lender reads the risk allocation before it reads the price, and an unallocated risk stops the financing conversation.

The public layer that sits between policy and risk

The H2Global Foundation report of December 2024 evaluates four support instruments: capital expenditure support, the fixed premium, the contracts for difference and the anchor capacity bookings. Its donor survey ranks market risks, political and regulatory risks and permitting and compliance risks as the most critical barriers, and it puts the investment needed to align the hydrogen economy with net zero at 1 000 billion USD worldwide by 2030, of which 335 billion USD has yet to be allocated, infrastructure being the largest part of the gap at 190 billion USD.

Blended finance, subordinated tranches and guarantees provide a first loss layer, meaning they take losses before senior lenders, and they lower the overall cost of capital without removing the underlying market or off-take risk (January 2026). That is the role I expect of development finance institutions, public or multilateral lenders created to fund projects in markets private lenders avoid.

What this means for you: treat the public layer as a way to lower the price of risk, never as a substitute for a contract, because a guarantee sitting above an unallocated off-take risk does not make the project financeable.

What this means for a Southeast Asian developer

The IEA briefing of 9 December 2025 records 7 Mtpa of offtake announced between 2021 and 2025 against only 1.6 Mtpa that is firm, and 16.5 Mtpa of export projects announced to 2030 against only 4.2 Mtpa with a buyer identified. Regional demand reached 4 Mt in 2024, with ammonia taking 49 percent against refining at 31 percent and methanol at 20 percent. Announced regional projects equal 12 percent of current demand while only 6 percent of announced capacity has reached FID, and no certification scheme is in place with work running in three countries. Close to 11 Mtpa of potential sits below 6 USD/kg by 2030, mostly in Indonesia (December 2025).

For this region I read the conditions for green hydrogen investment before I read any contract draft, because the certification gap and the cost of capital set the frame.

What this means for you: with no certification scheme in place and only 6 percent of announced capacity at FID, start with the guarantee of origin path and the buyer’s market access, then negotiate volume.

How I sequence the three levers

The IEA page of five key questions from 2025 closes the sequence: firm purchase agreements cumulate to less than 2 Mtpa, only 5 percent of the production potential announced for 2030, 9 percent of announced projects worldwide have secured committed investment against 0.5 percent in emerging economies, and the cost of capital can reach 15 percent in emerging economies, three times the level of advanced economies (2025).

I work the contract first, because nothing prices without it. I work the policy second, because it fixes both the price gap and the definition of the molecule. I work the risk allocation third, in writing, before any board is asked to commit funds.

What this means for you: sequence the three levers in that order and you will know within weeks which single one is holding your FID, instead of reopening all three at once.

Sources

Frequently asked questions

All three levers at once: the contract, the policy framework and the risk allocation. Only around 13 percent of contracted volumes are supported by fully binding offtake agreements (January 2026), and only 6 percent of announced regional capacity has reached FID (December 2025). A project holding two of the three usually waits for the third.

No tenor is published as a rule, so I work from the record: 10 to 15 years, about half the duration of first-generation international gas and LNG contracts, with take-or-pay expected at 60 to 80 percent (August 2025). Where the tenor is shorter, the equity has to compensate: some European projects reached FID with contracts of 5 to 7 years and an equity contribution of around 50 percent (January 2026).

A contract that binds the buyer to the volumes and to payment anyway, through a take-or-pay obligation: 7 Mtpa of offtake was announced between 2021 and 2025 against only 1.6 Mtpa that is firm (December 2025). On contracted volume worldwide, 80 percent sits as memorandums or is unspecified (2024).

The change of law clause decides who pays for the change. Lenders require clear alignment with the certification schemes of the target market and pre approval for guarantees of origin before they size the debt (January 2026). I negotiate that clause before the price formula, not after it.

Not sure your project would survive a credit conversation?

A short call is usually enough to see where your project stands.

If you are at pre-FID structuration and you need to decide which lever to work first, the sequence above is the one I apply in offtake structuring for hydrogen, ammonia and derivative projects.

I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia

I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.

More about me·Get in touch

Facebook
Twitter
LinkedIn

Related articles