Demand Adoption Risk: Will Vessels Really Run on Green Methanol?

10 min read  ·  Nov 2, 2026  ·  By Alex

methanol demand adoption risk

In fact, shipyards keep taking orders for methanol-capable vessels, but an order is not demand for fuel. DNV records 61 methanol ship orders in 2025 against 149 in 2024. Meanwhile, the wider newbuilding market fell to 2,403 orders from 4,405. Moreover, analysts expect more than 1,000 methanol-classed vessels to enter service over five years. The Methanol Institute’s 2025 milestones, citing Clarksons Research, record it. The answer is to separate orders, deliveries and contracted tonnes. I therefore look for the long-term offtake that carries the debt. That separation is the whole of methanol adoption risk at pre-FID. The green methanol industry page sets the product these three numbers describe.

I translate those three words every time a demand assumption lands on my desk. An order is a shipyard contract, a delivery is a hull handed over. Also, an offtake is a commitment to take tonnes a year for a stated term. Only the third one services debt.

In short

  • Orders: a shipyard contract, not a fuel purchase; methanol orders fell to 61 in 2025 from 149 in 2024.
  • Deliveries: hulls handed over; 59 in 2025 and 38 in the first half of 2026.
  • Contracted tonnes: the only line that services debt; one published agreement covers 500,000 tonnes a year.
  • Buyer horizon: buyers hesitate beyond two to three years, shorter than the construction loan.
  • Financing gate: most planned fuel facilities have not reached final investment decision.
Facebook
Twitter
LinkedIn

In this article

Three numbers that get mixed up

I start with definitions, because the three numbers answer three different questions. An order is a shipyard contract for a hull. Also, an orderbook is the running total of such contracts still to be delivered. A delivery is the day the yard hands the vessel over and it enters service. An offtake is therefore a contract for a stated number of tonnes a year. The buyer commits to that volume for a stated term.

The first number tells me what shipowners expect to burn. The second tells me when burnable capacity actually arrives. The third tells me whether a plant has contracted revenue to service its debt. Also, it is the only one I can underwrite. A methanol-capable hull can also burn conventional fuel. Therefore, even a delivered ship is an option rather than a purchase commitment. The published record keeps these three objects in separate columns. Also, the confusion begins when they are merged into a single sentence about demand.

What this means for you: I ask which of the three numbers a seller quotes. I do that before I accept any demand assumption. Only contracted tonnes therefore repay a loan.

What the fleet commits to, and what it does not

The fleet numbers are commitments to ships, not to fuel. The 2025 milestones from the Methanol Institute, citing Clarksons Research, record the fleet. There were 50 methanol dual-fuel vessels in service at the start of 2025. Meanwhile, the orderbook held 350 methanol-capable newbuildings and close to 700 methanol-ready ships. Analysts expect more than 1,000 methanol-classed vessels to enter service over five years.

The fuel numbers sit far below that. Total methanol supply in 2024 reached 94 million tonnes. However, renewable product sold only 400,000 to 500,000 tonnes. Developers have announced more than 200 renewable and low-carbon projects. They promise 45.8 million tonnes of capacity by 2030. However, only 20 to 40 percent may move forward, leaving 7 to 14 million tonnes. About 4 million tonnes were operational or under construction in February 2025. Meanwhile, China holds half of the global bio-methanol and e-methanol project pipeline. In fact, none of those three capacity figures represents fuel sold. The methanol demand from shipping page is where a vessel order is converted into tonnes.

What this means for you: I treat fleet growth as evidence of optionality. I therefore accept demand only where a signed offtake turns a hull into contracted tonnes.

Orders are not deliveries

Maritime Propulsion recorded on 3 November 2026 a delivery story rather than an ordering story. Singapore started issuing commercial methanol bunkering licences on 1 January 2026, and in October 2026 a dual-fuel vessel took about 5,000 tonnes of certified bioethanol in Singapore as a direct substitute in methanol engines. A.P. Moller – Maersk operates about 20 methanol-capable container ships, with an offtake of 500,000 tonnes a year of green methanol from Goldwind whose first stem, meaning the first bunkering delivery, was expected in 2026, and a long-term bio-methanol agreement with LONGi. Hapag-Lloyd ordered 8 dual-fuel ships of 4,500 TEU in December 2025 for delivery in 2028 and 2029. This is an order again, not a delivery.

Methanol ship deliveries numbered 59 in 2025 and 38 in the first half of 2026. Methanex contract prices in November 2026 stood at 700 USD a tonne in Asia Pacific. They were 625 USD a tonne in China and 875 EUR in Europe. In fact, buyers measure every low-carbon offer against those fossil methanol prices. The marine fuel offtake page looks at the demand behind those hulls.

I date each hull to its delivery year and each fuel contract to its first stem. Therefore, a delivery scheduled for 2028 carries no methanol demand today.

Who signs for the fuel, and for how long

Global Maritime Forum records, on a page consulted on 17 November 2026, more than 100 methanol-capable ships in service and more than 300 on order, alongside close to 50 ammonia-capable ships in the pipeline. Most planned fuel production facilities have not reached final investment decision. Also, the key obstacle is the lack of long-term offtake agreements, generally required to secure financing.

For shipowners, such contracts often exceed 1 million dollars over 10 years or more. Only a limited number of shipowners are therefore willing or able to take that risk. FuelEU Maritime imposes tightening emission intensity targets. The non-compliance fee is 2,400 euros per tonne of very low sulphur fuel oil equivalent. In fact, 2026 was the first compliance year for ships trading with or within the European Union. A compliance pool balances ships in compliance against ships in deficit inside one fleet. It can become a form of demand aggregation for e-fuels. Specifically, multi-year commitments and more stable price structures make that possible. Experts cite H2Global and the Zero Emission Maritime Buyers Alliance as examples. It reduces uncertainty and spreads risk. It does not close the cost gap. The how to secure offtake agreements page takes that contract apart.

What this means for you: I read the offtake term against the construction timeline and the compliance calendar. A deficit fee absorbed in a single compliance year is therefore not the same commitment as multi-year contracted tonnes.

What the buyer side looks like

The European Investment Bank and Roland Berger recorded this in May 2024. They consulted 34 companies from a longlist of more than 100. The data was current to February 2024. As a result, buyers hesitate to commit beyond two to three years. The construction loan therefore runs considerably longer. Buyers trade on standardised futures markets. They therefore wait for a marked fall in production costs with scale.

Even with a long-term offtake, some first-generation buyers. This matters for buyers of a fuel with no trading history, such as airlines. As a result, lenders do not consider them creditworthy enough. Creditworthy means able to meet payment obligations to the debt provider. Analysts therefore expect the cost gap between sustainable and conventional fuels to persist. Also, the EU emissions trading system will not close it in the medium term. The sustainable maritime fuels page holds that regulatory and demand context.

What this means for you: I check who signs, for how long and with what balance sheet. Consequently, a two to three year horizon in front of a longer construction loan leaves the tail uncovered.

The price line that decides adoption

BloombergNEF recorded on 18 June 2024 that low-carbon methanol costs 1.2 to 12 times fossil methanol. The range therefore depends on the feedstock. That difference is therefore the green premium, the extra cost a buyer pays. In fact, above 500 USD a tonne, shipping companies may find it cheaper to pay the carbon price. They prefer that to buying green fuel until 2030. Close to 70 percent of grey methanol supply comes from China. Planned global low-carbon methanol capacity could therefore consume 1.65 million tonnes of clean hydrogen a year. Producers first sign long-term offtake or obtain investments from maritime transport buyers. They therefore approach port infrastructure operators to secure storage capacity or co-invest in its extension.

The 2026 orderbook data show the market choosing elsewhere for now. There were 275 alternative-fuel vessel orders in 2025, down 47 percent. Meanwhile, the wider market took 2,403 orders against 4,405 in 2024. Alternative fuels hold 38 percent of gross tonnage ordered, with 188 LNG orders at 31 percent. Meanwhile, methanol orders fell to 61 from 149 in 2024. Container ships split 58 percent LNG, 36 percent conventional and 6 percent methanol. The IMO net-zero framework page explains the rule that is supposed to move that split.

What this means for you: I test the offtake price against the carbon price the buyer can legally pay. Consequently, adoption stops where the cheaper compliance route begins.

The five numbers I ask for before I believe an adoption story

I ask five questions in writing. First, I count the ships in service against the ships ordered. There were 50 in service and 350 plus close to 700 methanol-ready on order at the start of 2025. Second, the yards delivered 59 hulls in 2025 and 38 in the first half of 2026. Third, the tonnes contracted a year: one published agreement stands at 500,000 tonnes a year. Fourth, what the offtake costs the buyer: above 500 USD a tonne the carbon price becomes the alternative until 2030. Fifth, has the fuel project reached final investment decision? Most planned facilities had not. Also, only 20 to 40 percent of announced projects were expected to move forward.

An answer without a date goes back to the sender. Meanwhile, an announced capacity never enters my demand column.

What this means for you: five dated answers let me test the demand assumption behind the offtake. Instead, I do not trust a fleet announcement.

How I would underwrite adoption if it were my own credit memo

I keep four dated rows in the file. The fleet row, from the 2025 milestones, carries 50 ships in service and 350 ordered. It also shows more than 1,000 vessels expected over five years. The orderbook row carries 61 methanol orders in 2025 against 149 in 2024. It also carries a 38 percent alternative-fuel share from the 2025 DNV data. The delivery row carries 59 deliveries in 2025 and 38 in the first half of 2026, dated 3 November 2026. The contract row carries the long-term offtake obstacle. That is the 1 million dollars over 10 years or more hurdle for shipowners. It also carries the two to three year buyer horizon from the 2024 studies.

I read the four rows together. The fleet row shows interest, the orderbook row shows direction. The delivery row shows arrival, and only the contract row shows cash. Every row carries its date, and any row I cannot date does not go in the file.

What this means for you: a credit memo names the date and object of each number. It therefore lets a lender test methanol adoption risk without shipyard press releases.

Sources

Frequently asked questions

It is one of the options, not the winner. The 2025 orderbook data show LNG at 188 orders and 31 percent of gross tonnage ordered against 61 methanol orders, with container ships split about 58 percent LNG, 36 percent conventional and 6 percent methanol. Alternative fuels as a whole hold 38 percent of gross tonnage ordered, so the split inside that share is where the decision sits.

50 methanol dual-fuel vessels were in service at the start of 2025, mostly chemical tankers, against an orderbook of 350 newbuildings plus close to 700 methanol-ready ships. Deliveries were 59 vessels in 2025 and 38 in the first half of 2026. The running fleet is therefore small compared with what is promised, and I count deliveries, not intentions.

The ship is the cheaper side of the bet. Dual-fuel capability lets a vessel burn conventional fuel, while the producer carries the upfront cost and needs long-term demand certainty. Above 500 USD a tonne the buyer may prefer paying the carbon price on its emissions rather than the green fuel, at least until 2030, so a built ship does not guarantee a green purchase.

Contracted tonnes and final investment decisions. The financing study of May 2024 records buyers hesitating beyond two to three years against a considerably longer construction loan, and the page consulted in November 2026 records that most planned fuel facilities had not reached final investment decision because long-term offtake is missing. Those two facts, dated, are the evidence I accept.

Not sure your project would survive a credit conversation?

A short call is usually enough to see where your project stands.

If you want a second read on the demand assumption inside your offtake file, the strategic partnerships service is where I work through the dated rows, the buyer credit and the contract term with the developer before the lender does.

I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia

I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.

More about me·Get in touch

Facebook
Twitter
LinkedIn

Related articles