Home » ISCC Certification for Green Methanol: What Each Scheme Proves and What It Does Not
ISCC Certification for Green Methanol: What Each Scheme Proves and What It Does Not
10 min read · Nov 2, 2026 · By Alex
One system, two schemes and three chain of custody options. Under ISCC EU the permitted options are mass balance and physical segregation. ISCC PLUS adds controlled blending, as the support centre’s answer shows, modified on 26 May 2026. Every site handling alternative materials must hold its own certificate. Each certificate covers one site and lasts 12 months, as the support centre’s answer shows. The PLUS page shows the same, consulted on 17 November 2026. The certificate shows origin and chain, not carbon intensity. An RFNBO must still stay under 70 percent of a 94 gCO2eq/MJ fossil comparator. The limit is no more than 28.2 gCO2eq/MJ, as the Observatory’s directive page shows, updated on 3 November 2026. Those three sentences are the whole answer. The rest of this piece, sitting inside the green methanol branch, shows how I read the file.
I write for a developer at feasibility stage who must choose a scheme before a plant exists. The buyer’s compliance reviewer will open that choice later. The two readers want different things from the same folder, and the folder only survives if it was built once.
What ISCC certification for green methanol covers at a glance
In short
- One system, two schemes: ISCC EU serves the regulated route, ISCC PLUS serves the voluntary route.
- Three options: physical segregation, controlled blending, mass balance, ordered from most strict to less strict.
- One certificate per site: issued site by site, valid 12 months, with every chain element certified.
- Intensity sits outside the certificate: the ceiling is 28.2 gCO2eq/MJ against a 94 gCO2eq/MJ comparator.
- Read the periods: certificate 12 months, mass balance period at most 3 months, System Document valid until 31 December 2026.
In this article
One system, two schemes
The certificate answers where the carbon came from and how the chain tracked it. The intensity calculation covers how much fuel reaches the atmosphere when it burns. In addition, it answers how a plant produces the fuel. A reviewer can challenge any dossier that confuses the two at the first review. The reviewer is looking for two different documents and will treat a substituted one as a gap.
The scheme chosen at feasibility stage determines which bookkeeping rules the plant lives under for the whole certificate period, and every downstream step inherits that choice. What follows reads the file the way a reviewer does. The order is the scheme that covers what, the books, and the source of the intensity figure.
What this means for you: I decide the scheme before I decide the process diagram, because the option I pick fixes the accounting the plant runs for the next 12 months and every 12 months after.
What ISCC EU and ISCC PLUS each cover
The support centre’s answer, modified on 26 May 2026, records that under ISCC EU the possible chain of custody options are mass balance and physical segregation, and that ISCC PLUS also provides controlled blending. In fact, the same answer shows that these approaches sit in three documents. One is ISCC EU 203 Traceability and Chain of Custody. Another is the ISCC PLUS System Document, valid until 31 December 2026. A third is ISCC PLUS 203-1 Chain of Custody. Three documents, one per decision point, so I check the version date on each before I cite it.
The PLUS page, consulted on 17 November 2026, records that ISCC PLUS is a voluntary scheme validating the sustainability characteristics of alternative feedstocks beyond regulatory compliance. The scheme must certify every element of the supply chain. Each site handling alternative materials must hold a valid certificate for one site and 12 months. By contrast, transport operators need no certificate of their own. It lists seven chain elements: origin, the first gathering point or central office, the processing unit, the trader with storage, the second processing unit, final product refining, and the brand or market owner. The RFNBO page explains why the regulated route and the voluntary route are answered by different documents.
What this means for you: I confirm which of the two schemes my buyer’s reviewer trains on. In addition, I must certify the sites that fall inside it, not the company name on the letterhead.
The three chain of custody options
Chain of custody is the process of transferring, monitoring and controlling the input and output of sustainable materials. Also, their documentation as they move through the supply chain, as the 2026 chain of custody document records. The same document records that ISCC certifies three methods: physical segregation, controlled blending and mass balance, in an order of strictness from the most strict to the less strict. Physical segregation keeps certified material physically separate; mass balance keeps it separate only in the books. Controlled blending sits between them.
The same source shows one rule about mass balance. A plant that applies mass balance at one step must apply it in all subsequent steps. A system user who holds another option’s certificate cannot accept mass balanced material. By contrast, in hard identity preserved, the input must stay under hard segregation throughout the whole supply chain. In soft identity preserved, batches with the same sustainability characteristics but different origins can merge in the bookkeeping. It records the attribution options: attribution determined by energy, by mass, free attribution, output categorisation with fuel use excluded, measurement of the sustainable share by 12C/14C analysis, proportional attribution, and the trace-the-atom option new from 2025. The methanol bunkering page covers the last handover where those declarations change hands.
What this means for you: I pick the option that my downstream steps can all inherit, because one downstream step on a different option breaks the chain I just paid to certify.
What mass balance promises on paper
The 2026 chain of custody document sets out the accounting rules. First, the mass balance is site specific and scope specific. Second, the period runs for at most 3 months, and the output must not exceed the input within it. Third, the balance must not be negative at the end of the period. As a result, no entity may sell more certified product than it has sourced once conversion factors apply. The same source records that conversion factors are verified against operational data and certified volumes. Also, the plant must communicate the attribution option to the downstream supply chain through sustainability declarations.
Those rules are what a buyer’s reviewer checks against the sales ledger. The obligation they have to serve is separate: the European Commission’s FuelEU Maritime page, consulted on 16 November 2026, records Regulation (EU) 2023/1805 applying since 1 January 2025 to ships above 5,000 gross tonnes, with intensity reductions of 2 percent from 2025, 6 percent from 2030, 14.5 percent from 2035, 31 percent from 2040, 62 percent from 2045 and 80 percent from 2050 against the 2020 baseline. The FuelEU Maritime page sets that obligation out in full.
What this means for you: I treat the 3 month period as a closing date in my calendar, not as a rolling licence, and I reconcile the closed period before the next one opens.
What the certificate does not prove
The European Hydrogen Observatory directive page, updated on 3 November 2026, records that the maximum greenhouse gas intensity threshold is 70 percent of a fossil fuel comparator of 94 gCO2eq/MJ, so an RFNBO delivered to the final consumer must be no more than 28.2 gCO2eq/MJ. It records that RED III has been in force since November 2023 with a 2030 transport choice between a 14.5 percent greenhouse gas reduction and a 29 percent renewable share, a 5.5 percent combined sub-target of advanced biofuels and RFNBOs, and a 1 percent RFNBO sub-sub-target. In fact, an audit certificate covers none of those thresholds.
The framework FAQ of the IMO, consulted on 16 November 2026, records that emissions. Also, a scheme recognised by the MEPC must verify fuel sustainability independently. Zero and near zero emission fuels generally sit at up to 19.0 gCO2eq/MJ. The current average is 93.3 gCO2eq/MJ. Those two figures are an intensity statement. Also, they come from a separate calculation with a separate comparator. The green methanol carbon intensity page sets out that calculation and the comparator it uses.
What this means for you: I keep the certificate in one folder and the intensity calculation in another. As a result, each one answers only its own question.
When the claim travels without the molecule
The VPS methanol page records that the industry bunkers 230 million tonnes of fuel a year for 716 million tonnes of carbon dioxide equivalent, that 13 ports now offer methanol bunkering while that methanol is predominantly grey with tank-to-wake emissions close to conventional fossil fuels, and that the sustainable options are e-methanol, bio-methanol and blue methanol. The same source records that 39 methanol powered ships are at sea with 262 on order. Also, that the methanol fleet carries a flash point of only 12 degrees Celsius.
It also records that in November 2024 the ISO published the first edition of ISO 6583:2024 with requirements and limits for three marine methanol grades, and that the Singapore standard announced at SIBCON-24 in October 2024 refers to ISO 6583 for quality requirements at custody transfer, naming IMPCA for the underlying quality specification. The chain of custody rules stay with the bookkeeping rather than with the cargo. This is exactly why a claim can move to a buyer. The molecule stays where the plant produced it. The book and claim page covers that separation.
What this means for you: I write the delivery documentation. The claim can then move separately from the physical parcel. In addition, I check that the quality specification and the sustainability declaration sit on the same delivery note.
What I would read in an audit file
I read six things in order. Which scheme and which scope the certificate covers. In addition, I read the site names and the issue date of each certificate. Which chain of custody option the plant uses and whether every downstream step applies the same one. Which attribution option carries the certified share and whether the period closed positive. Whether the sustainability declaration travels with each delivery note. And whether the intensity figure sits in the same folder, calculated against the same comparator.
I read them in that order because each one only makes sense after the previous. A scope without a site tells me nothing about what the auditor checked. A period without the attribution option tells me the balance exists but not how the plant allocated it.
What this means for you: I ask for the file in this order at the first review, so a missing line shows up as a missing line rather than as a plausible summary.
How I would keep the evidence
I keep three dated rows. The certificate row carries the site name, the issue date and the 12 months of validity. The bookkeeping row carries the period of at most 3 months, the conversion factors and the attribution option. The intensity row carries the value against 94 gCO2eq/MJ and the 28.2 gCO2eq/MJ ceiling.
Every row carries its document reference and its date. Therefore, a buyer’s reviewer can check the folder without asking me a question. When one row moves, the other two do not move with it: a certificate renewal does not recalculate an intensity figure, and an intensity recalculation does not extend a certificate. That separation is what keeps an audit quiet.
What this means for you: I build the three rows at feasibility stage, before there is anything to file, so that filling them later is a recording task rather than a reconstruction.
Sources
- ISCC PLUS, page consulted 17 November 2026.
- ISCC System GmbH, ISCC PLUS Chain of Custody, document 2026.
- ISCC Support Centre, answer modified 26 May 2026.
- European Hydrogen Observatory, page updated 3 November 2026.
- VPS, Methanol as a marine fuel, opened 17 November 2026.
- European Commission, FuelEU Maritime, page opened 16 November 2026.
- IMO, The IMO Net-Zero Framework FAQs, opened 16 November 2026.
Frequently asked questions
What is the difference between ISCC EU and ISCC PLUS?
ISCC EU serves the regulated route and allows mass balance and physical segregation, while ISCC PLUS is the voluntary scheme for alternative feedstocks and adds controlled blending. Both sit in ISCC EU 203, the ISCC PLUS System Document valid to 31 December 2026, and ISCC PLUS 203-1. The PLUS page shows ISCC PLUS goes beyond regulatory compliance, so it is not a regulatory approval.
Which chain of custody option should a methanol plant use?
Physical segregation is the strictest option; mass balance keeps certified and non certified material apart only in the bookkeeping. Controlled blending sits between them, under ISCC PLUS only. If mass balance is used at one step it must be used in every step after it, so I check my downstream steps before I choose.
Does an ISCC certificate guarantee a low carbon intensity?
No: the certificate proves origin and chain of custody, while intensity is a separate calculation. The Observatory sets a ceiling of 28.2 gCO2eq/MJ against a 94 gCO2eq/MJ fossil comparator, met at 70 percent. The framework FAQ shows zero and near zero emission fuels at up to 19.0 gCO2eq/MJ against a 93.3 gCO2eq/MJ average. It is an intensity statement, not a certificate statement.
How often does a plant need to be audited?
A certificate is issued per site and valid for 12 months, and a mass balance period runs for at most 3 months. The rhythm is a closed period every quarter and a full audit inside the 12 month window. I keep the period close date and the audit date as two separate entries so neither turns up late.
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If you want a second pair of eyes on which scheme fits your plant and how the folder should look before a buyer opens it, start with the EU compliance and carbon intensity service.
I do not provide investment advice or arrange investments. In addition, I work as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.