Home » SAF Bankability Scorecard: How Investors Rank Projects Before FID
SAF Bankability Scorecard: How Investors Rank Projects Before FID
9 min read · Jul 2, 2026 · By Alex
Before a project reaches its final investment decision (FID), the investor or lender who may fund it marks the file against a fixed list. In practice that mark comes from a SAF bankability scorecard: 10 weighted criteria, each scored 1 to 5, where feedstock security and contracted revenue carry the decision. I apply that sheet to every pre-FID file I review, and I place it inside the wider route described in how to reach FID on a SAF project.
This is not a public rating. It is the internal worksheet an investment committee completes before committing capital, and the same file gets scored twice, once by the sponsor and once by the party paying. I wrote it out because sustainable aviation fuel (SAF) projects lose the second score more often than the first.
In short
- Scale: Each of the 10 criteria scores 1 to 5, then reads into four bands: 80 to 100 Bankable, 65 to 79 Near Bankable, 50 to 64 In Development, 0 to 50 Early Stage.
- Two pillars: Feedstock security and contracted revenue are scored separately, and I fix both before any engineering spend.
- Evidence: A signed contract scores. A memorandum of understanding does not.
- Engineering: A Class 3 cost estimate, a completed FEED and a licensor guarantee carry the technology, construction and delivery lines.
- Timing: I score the file myself, then re-score after each contract closes and before a lender opens the sheet.
In this article
1. What a SAF bankability scorecard is
A scorecard is the sheet an investor or lender fills in before taking a project to committee. The ICAO Finvest Hub publishes one: 10 criteria, each scored 1 to 5, read in order from the project narrative through to policy support. The reason the sheet exists is visible in the market. About 600 SAF production announcements have been made since 2016 against about 35 producing facilities, 2.4 million tonnes of SAF production is forecast in 2026, and most announced projects sit in the economic valley of death, where the development axis is marked at 12, 24, 36, 48 and 96 months from the start of the cycle. By 2050 several thousand SAF and cleaner energy projects will be required. Between those two facts sits a long queue of files that never climb out of In Development. The financing mechanics around this sheet sit in how to finance a SAF project.
What this means for you: I open your file with this sheet and a date on it. Announcements do not score. Contracts, permits and estimates do.
2. The ten criteria, in the order a committee reads them
- 1. Project narrative: clarity and credibility of the investment story, and why it is attractive.
- 2. Technology readiness: maturity, performance reliability and commercial viability of the pathway.
- 3. Construction risk: scope, cost, timeline and delivery risks defined and properly allocated.
- 4. Delivery capability: the sponsor team and governance that will execute and operate.
- 5. Feedstock security: availability, sustainability and price stability of the inputs.
- 6. Infrastructure and permits: site readiness, consents and enabling utilities.
- 7. Capital structure: credibility of the financing approach and the likelihood of debt and equity on acceptable terms.
- 8. Contracted revenue: long-term, predictable and bankable revenue underpinning cashflow, normally through offtake, meaning the contract under which a buyer takes the plant’s output.
- 9. Creditworthy counterparties: strength and reliability of the parties on the other side of the contract.
- 10. Policy support: clarity and durability of the demand mechanisms.
Each line carries a named red flag: unsupported claims, ambitious first-of-a-kind scale-up assumptions, materials inflation, an inexperienced team, a single supplier, uncertain critical infrastructure, reliance on a future funding round, revenue dependent on future market assumptions, counterparty weakness, and economics resting entirely on policy.
What this means for you: I read your file in this order, so the narrative has to survive line 5. A strong story over an unsecured feedstock is still a weak score.
3. How the score is built and what the bands mean
Each criterion is scored 1 to 5: 5 is investment-ready and gives strong confidence; 4 means minor issues remain and the risk is manageable; 3 means promising but further development is required; 2 means significant concerns and little chance of attracting finance; 1 means a critical weakness and a major barrier. The same criterion can also be marked Yes, Partial or No. Yes means fully in place, clearly evidenced and consistent with investor expectations. Partial means material gaps. No means not in place or unclear.
The 10 scores are then read together against four bands: 80 to 100 Bankable, strong fundamentals and readiness for immediate investor engagement; 65 to 79 Near Bankable, core elements in place with one or more areas still to de-risk; 50 to 64 In Development, a viable concept with significant gaps; 0 to 50 Early Stage, substantial uncertainty. The framework was developed with financial institutions and is stated as a guide, not a pass mark. In the Finvest process only the entry checklist and the bankability checklist are required stages, and a project may enter at any stage.
What this means for you: I want your number before the meeting, not after it. Print the 10 scores, name the band, and say which two lines you are fixing first.
4. Feedstock security and contracted revenue: two equal pillars
I fix both pillars before any engineering spend, and the sheet scores them separately. On feedstock: long-term contracts of up to 20 years, diversity of suppliers, and sustainability certified under CORSIA, the Carbon Offsetting and Reduction Scheme for International Aviation. A project that leans on one supplier is a red flag. On revenue: a long-term binding offtake, revenue visibility and demand certainty. Revenue that depends on future market assumptions is marked down.
Lender practice is specific. Most project finance banks want feedstock supply covering 70 percent of nameplate capacity for the first five years, and an offtake of at least 10 years covering 70 to 100 percent of plant output. RMI asks for long-term take-or-pay structures with creditworthy counterparties, and SimpliFlying reports the RMI and World Energy playbook calling for firm multi-year commitments of ideally 7 to 10 years or more. HEFA is the most mature pathway and it depends on used cooking oil, which is why so many projects chase the same supply. The feedstock score doubles as a competition test. Contract structures sit in how to secure SAF offtake agreements.
What this means for you: I do not start engineering until both contracts are on paper. Until then the score is provisional whatever the process design says.
5. Technology, construction and delivery: the engineering half of the score
Criteria 2, 3 and 4 are the engineering half of the score. A committee accepts a proven pathway with performance guarantees from the licensor, a completed FEED (front-end engineering design), a defined EPC (engineering, procurement and construction) strategy, and contingency planning against materials inflation and cost creep.
Cost discipline is judged on AACE classification: Class 5, minus 50 percent to plus 100 percent for concept screening; Class 4, minus 30 percent to plus 50 percent for pre-FEED; Class 3, minus 20 percent to plus 30 percent for early FEED; Class 2, minus 15 percent to plus 20 percent; Class 1, minus 3 percent to plus 10 percent for EPC bidding. Most project finance lenders require a Class 3 estimate or better at FID, built on a detailed equipment list and at least 30 percent engineering completion. A FEED that lenders cannot accept costs 10 to 20 million USD to produce, P&IDs should be at least 60 percent complete, and the lender commissions an independent engineer report covering technology, construction and operating risk. Getting pathway and licensor selection right at pre-FEED also saves 5 to 15 percent of CapEx (capital expenditure) against late-stage scope changes. First-of-a-kind (FOAK) pathways carry the highest score risk, and the red flag named by ICAO is ambitious FOAK scale-up assumptions. The engineering-finance side is covered in e-SAF project finance.
What this means for you: I bring the estimate class and the FEED status into the first meeting, because that is where three lines move at once.
6. Capital structure, counterparties and the money behind them
Criteria 7 and 9 carry the money. Committed sponsors, a balanced capital stack, identified financing pathways, and no excessive reliance on a future funding round or a single option. Counterparties rated investment grade or close, with a proven track record, because counterparty weakness cascades through the whole contract set.
The scale behind that caution is large. ICAO frames the investment need under the long-term aspirational goal at up to USD 3.2 trillion for fuels suppliers and USD 4.07 trillion for operators in aviation clean energies by 2050, while the World Economic Forum figure carried by SimpliFlying is 19 to 45 billion USD of SAF investment needed by 2030. Contracted revenue can also come from certificates: one power-to-liquid producer has booked 260 million gallons of neat e-SAF over 14 years with a European airline, and RMI’s playbook insists that cashflow stability must hold for both the environmental attribute certificate (EAC) and the physical fuel. Equity from the region sits in sustainable aviation fuel in Southeast Asia: equity, and on the patient-money side a development finance institution (DFI) sits in development finance institutions.
What this means for you: I map every counterparty and every funding source before I show the capital stack, and I delete any line that depends on a round nobody has committed.
7. How a public allocator scores the same file
The Advanced Fuels Fund run by the UK Department for Transport, as presented by ICAO ACT-SAF, shows the public version of the same exercise: 15 scoring criteria in 4 categories, covering project relevance, technical approach, commercial approach and project implementation. A weighted total must sit above 65 percent to be eligible, against a 50 percent threshold in windows 1 and 2. Multipliers between 50 and 100 percent apply to two criteria, progression towards construction of a FOAK commercial plant and the strength of the funding case including match funding. Projects may be invited to interview and asked for clarifications within 5 working days, with due diligence started in that period.
The reading is simple. Your internal 10-point view and the funder’s view are two scorecards of one file, and the funder’s arithmetic is public.
What this means for you: I score your file with the funder’s categories open beside mine. Where the two sheets disagree, the funder’s arithmetic wins.
8. Running the scorecard on your own file
I score the 10 criteria 1 to 5 today and keep the sheet, because the gap between two dated assessments is the argument for financing. In the ICAO case study, the three moves that most improved the score were a 15-year offtake with a major airline for 60 million litres a year, feedstock repositioned to an aggregator with risk guarantees for supply failure, and a 5 percent carbon intensity reduction mandate passed with introduction from 2030.
The economics have to survive stress. I test that the project stays viable at 50 percent credit value and with feedstock cost 20 percent above the base case, then re-score before a lender does.
What this means for you: I re-score the same sheet after each contract and send it to the lender with the date on it. The movement between two dated sheets is the case for financing.
Sources
- ICAO Finvest Hub, 1 July 2026.
- ICAO ACT-SAF, 2025.
- RVN Inc., undated page consulted in 2026.
- SimpliFlying, 29 October 2025.
- RMI, 2025.
Frequently asked questions
What score do I need before I approach a lender?
There is no published pass mark. The framework is a guide, not a gate. In practice a file sitting at 50 to 64 In Development gets questions rather than term sheets, and 65 to 79 Near Bankable is where committees start real work. I target the two pillars first, because that is where the largest single moves come from.
Can a project score well on technology and still fail?
Yes. Criteria 2, 3 and 4 can all read 5 while criteria 5 and 8 read 2, and the file still lands in Early Stage. The 10 areas are read together, so a single-supplier feedstock or an unsigned offtake is enough to sink an otherwise strong engineering file.
What is the difference between my self-assessment and the investor's?
Same sheet, different tolerance. Your self-assessment marks what you have built. The investor marks what can be evidenced and enforced. The Yes, Partial and No descriptors exist for that reason: a signed contract is Yes, a memorandum of understanding is Partial, and a letter of intent with no volume or price is No.
How often should I re-score?
I re-score at every material change: a signed offtake, a feedstock contract, a completed FEED, a cost estimate that moves a class. In the ICAO case study the file was re-scored six months after the first assessment, and three contract and mandate changes moved it. Keep the original sheet so the movement stays visible.
Want this scorecard run against your own file?
A short call is usually enough to see where your project stands.
If you want me to run this scorecard against your file before a lender does, look at how I work on project finance.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.