Home » SAF Debt and Public Funding: How the Lender Stack Is Built Before FID
SAF Debt and Public Funding: How the Lender Stack Is Built Before FID
9 min read · Apr 2, 2026 · By Alex
A lender looking at a new fuel plant in Southeast Asia asks three questions before it signs: where the feedstock comes from for a decade, who buys the output, and who absorbs the loss if construction slips. A pre-FID developer weighing SAF debt needs those answers before a credit committee sits. The short version: senior secured bank debt at the top, development finance institution money alongside it, and public guarantees or concessional tranches carrying the risk private lenders will not hold.
That combination is what I test first when I read a SAF capital structure. My working frame starts with how to finance a SAF project, then splits cleanly into the debt side and the public money side. Both have to close at the same time. If one lags, the whole timetable slips.
The market context explains why lenders are writing structures now. The World Economic Forum put global SAF demand at 17 Mt a year by 2030, against 4.4 Mt of installed capacity at the end of 2024, with a further 5.8 Mt expected to reach FID before 2026. Sustainable aviation fuel has moved from pilot finance to project finance, and the terms have tightened accordingly.
In short
- Debt stack. Senior secured facilities first, then development finance institution tranches, syndicated B-loans and parallel loans. Equity closes the gap.
- Feedstock. Long-term supply contracts with price mechanics lenders can model. Competition between HEFA pathways and used cooking oil is a real concern, not a footnote.
- Offtake. A bankable long-term purchase contract. Without it, debt capacity falls sharply.
- Public money. Guarantees, grants and concessional finance absorb the risks that stop a credit committee from approving.
- Sequence. Feedstock, offtake and risk allocation are agreed before debt sizing. Nothing works backwards from a target loan amount.
In this article
What a lender actually finances in a SAF project
A lender finances contracted cash flow, not a technology thesis. Before anything else, the credit team wants to know which assets secure the facility, which accounts receive revenue, and whether the offtake contract can be handed to the lender if the sponsor defaults.
In a normal SAF structure the senior secured facility sits first. It amortises from operating cash flow and takes first claim on the plant and the revenue accounts. Development finance institution tranches and syndicated B-loans sit behind or alongside it. Equity from sponsors and equity investors funds the balance and absorbs the first loss.
The Sheikhupura project, announced in December 2024, shows the proportion. Total debt of 86.2 M USD against a project cost of 141.9 M USD means debt funds just over 60 percent of the build. The rest comes from sponsors and equity partners.
The work of reaching FID is largely the work of making those three layers agree on one set of contracts.
What this means for you: size debt around what the feedstock and offtake contracts can actually repay, then raise equity for the remainder. Reverse that order and the model will not survive diligence.
Why feedstock and offtake decide how much debt you can raise
These two pillars carry equal weight. Lenders will not fund a plant with a strong purchase contract and an unproven feedstock supply, and they will not fund a cheap feedstock supply with no buyer. Both must be contracted, dated and assignable.
Feedstock is where the sharpest commercial argument sits. HEFA pathways compete directly for used cooking oil across Asia, and the supply available is finite.
Offtake does the opposite job: it fixes the revenue line. The Sheikhupura project contracted long-term offtake with Shell Eastern Trading for up to 145,000 t a year against a design capacity of 200,000 t a year. That gap is deliberate. It leaves room for maintenance, yield variance and unplanned outages without breaching a delivery obligation.
The World Economic Forum notes that the tolling model, where capacity is leased to a toller who supplies the feedstock and carries those risks, tends to attract more debt. Guarantees and insurance further improve the credit profile.
What this means for you: negotiate the feedstock contract and the offtake contract in parallel, with the same assumptions on volume and price. A mismatch between them is the fastest way to lose debt capacity.
Development finance institutions: the first port of call
For a first SAF project in this region, development finance institutions are usually where the structure begins. They accept risks commercial banks cannot price, they can hold a tranche through construction, and their participation signals a completed diligence process to everyone else.
The link between these institutions and commercial money matters. My overview sits at development finance institutions, and the practical effect is visible in syndication: a development finance institution anchors the facility, then commercial lenders buy into the B-loans.
In the Sheikhupura financing, ADB was the sole mandated lead arranger and bookrunner, with a senior secured loan of 41.2 M USD. A portion of that ADB financing was activated through IF-CAP, a light climate guarantee mechanism, used for the first time. IFC committed a 35 M USD programme mixing debt and equity, with 20 M USD on its own account and up to 10 M USD through a blended finance programme launched with the UK’s FCDO.
What this means for you: approach development finance institutions early enough for their conditions to shape the contracts, not late enough that they merely approve what banks have already drafted.
Export credit agencies and the OECD Arrangement
Export credit agencies enter when equipment supply crosses borders. Their support can sit under a direct loan, under a guarantee, or under insurance covering commercial and political risk. The OECD Arrangement sets the framework for how much support can be offered and on what terms.
A PwC paper from April 2024, which is older than two years, sets out the main forms: direct lending with or without an exporter connection, indirect finance channelled through commercial banks, and cover for commercial and political risk. The same paper notes that an export credit agency can join a syndicate with commercial banks before financial close, which is often how a first-time borrower gets private money to follow.
The same source counted 115 official export credit agencies in 2021.
What this means for you: identify which equipment origins your procurement plan implies, then test whether an export credit agency can improve pricing or tenor before you fix the equipment contracts.
Commercial banks and private credit for SAF projects
Commercial banks bring the senior secured tranche and, where the deal allows, the underwriting. Private credit funds fill gaps where banks want shorter tenor, tighter documentation or a different position in the stack.
The constraint is simple. A commercial credit committee approves against a model, a security package and a set of contracts it can enforce. Anything outside that gets declined, however strong the strategic case.
ATAG, in a March 2023 paper, put the sector’s investment need at up to 1,450 billion USD to 2050, roughly 48 billion USD a year. That paper is older than two years, and its point still holds: blended finance and development institutions exist to recompose the risk so private money can enter at all.
In the Sheikhupura structure, 40 M USD of syndicated B-loans came from EAAIF and ILX at 20 M USD each, alongside a 5 M USD syndicated parallel loan from IFC. That is private and institutional money following an anchor lender.
What this means for you: give the anchor lender a clean, enforceable security package first. Everything private credit negotiates later depends on what that first facility establishes.
Public funding: guarantees, grants and concessional finance
Public money does three jobs. It guarantees part of the loan, it grants capital that never repays, and it lends at concessional rates to close a viability gap. None of it replaces debt; it changes whether debt can be raised at all.
The cost gap is the reason. ICCT reported in April 2026 that advanced SAF in the European Union costs 4 to 10 times fossil kerosene. The CISAF state aid framework, adopted in June 2025, allows competitive auctions covering up to 100 percent of eligible costs, administrative calls covering 45 percent, and contracts for difference. My note on how policy demand feeds into finance sits at SAF mandates.
RMI, in a March 2024 paper that is older than two years, frames the financier’s three dilemmas: the choice of feedstock, the public guarantee on the loan, and the construction insurance and guarantees package that will pass a credit committee.
What this means for you: treat the guarantee request as a structuring item with its own timetable. Public approval cycles are slower than bank credit cycles, so start both at once.
Green loans and sustainability-linked debt
A green loan ties use of proceeds to defined environmental assets. A sustainability-linked loan ties the margin to performance against key performance indicators, with a step up or down if the borrower misses or beats them. The mechanics differ, and so does the diligence.
For a SAF project, the green loan question is narrow: does the facility finance eligible assets, and can the borrower report on them? The sustainability-linked question is harder, because the indicators must be measurable, material and under the borrower’s control. Feedstock sourcing emissions and lifecycle carbon intensity are natural candidates, but only if the measurement methodology is fixed at signing.
The e-fuel side of the market follows its own rules, which I set out at e-SAF project finance. Where power purchase agreements and renewable certificates enter the structure, the lender’s review shifts toward grid access and certificate integrity.
What this means for you: choose one label and document it properly. A green loan with weak reporting and a sustainability-linked loan with weak indicators both create the same problem at the next refinancing.
The first SAF project financing in Asia Pacific, line by line
The Sheikhupura project in Pakistan, developed by SAFCO Ventures and announced in December 2024, is the first project finance transaction for a SAF project in Asia Pacific. Reading it line by line shows where each layer sits.
- Project cost: 141.9 M USD.
- Total debt: 86.2 M USD.
- Senior secured ADB loan: 41.2 M USD.
- Syndicated B-loans: 40 M USD, with EAAIF at 20 M USD and ILX at 20 M USD.
- Syndicated IFC parallel loan: 5 M USD.
- ADB role: sole mandated lead arranger and bookrunner, with part of its financing activated by IF-CAP, used for the first time.
- IFC programme: 35 M USD mixing debt and equity, 20 M USD on its own account and up to 10 M USD via a blended finance programme launched with the FCDO.
- Capacity: 200,000 t a year of SAF and bionaphtha from waste-derived feedstocks, including used cooking oil.
- Offtake: long-term contract with Shell Eastern Trading for up to 145,000 t a year.
Read the stack against the cost and you see the pattern: one anchor lender bookrunning, development finance money taking senior and parallel positions, syndicated B-loans bringing in institutional lenders, and a mixed debt and equity programme covering what debt will not. Equity partners absorbed the balance, which is where the case for SAF equity in Southeast Asia comes from.
What this means for you: build your lender list in that order. Anchor first, syndicated followers second, equity last to price and first to absorb risk.
Sources
- Clifford Chance, Clifford Chance advises ADB and IFC on the first project financing of a sustainable aviation fuel project in Asia Pacific, December 2024
- PIDG, EAAIF invests in USD 141.9 million sustainable aviation fuel facility in Pakistan, December 2024
- World Economic Forum, Financing Sustainable Aviation Fuels: Case Studies and Implications for Investment, February 2025
- International Council on Clean Transportation, What financial policy levers can help sustainable aviation fuels take off in the European Union?, April 2026
- RMI, Overcoming Three Finance Dilemmas for US SAF Producers in 2024, March 2024
- PwC, Export Credit Agency financing, April 2024
- Air Transport Action Group, Accelerating adoption of sustainable aviation fuel: financing and related issues, March 2023
Frequently asked questions
How much debt can a pre-FID SAF project raise?
It depends on what the feedstock and offtake contracts support, not on a fixed ratio. The Sheikhupura transaction reached 86.2 M USD of debt against a 141.9 M USD cost, just over 60 percent, with a long-term offtake covering up to 145,000 t a year of 200,000 t a year of capacity. Your number will differ. Work backwards from contracted cash flow and stress it.
What does public funding actually cover?
Three things: a guarantee on part of the loan, a grant against eligible costs, and concessional debt priced below commercial terms. Under the CISAF framework described by ICCT in April 2026, competitive auctions can cover up to 100 percent of eligible costs and administrative calls 45 percent. Guarantees and insurance improve the credit profile enough for syndication to happen.
Do I need an offtake agreement before approaching lenders?
Yes. Lenders underwrite a contract, not a market view. A long-term offtake with a creditworthy buyer fixes the revenue line, and without it debt capacity drops immediately. Feedstock supply is the mirror image: both must be signed, assignable and consistent on volume assumptions before a credit committee will size anything.
Are green loans different from sustainability-linked loans?
Yes. A green loan restricts use of proceeds to eligible assets. A sustainability-linked loan lets proceeds go anywhere but moves the margin against key performance indicators. For SAF, lifecycle carbon intensity and feedstock sourcing are natural indicators, provided the measurement method is fixed at signing.
Want your debt stack reviewed before you approach lenders?
A short call is usually enough to see where your project stands.
If you are sizing a SAF capital structure before FID, I can walk through the debt stack, the public funding layer and the lender sequence with you: project finance support.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.