We Connect Asia

SAF

DFIs and ECAs Financing SAF Projects

9 min read  ·  Jun 2, 2026  ·  By Alex

saf dfi eca financing

A sustainable aviation fuel plant is an infrastructure project before it is a fuel project: a reactor train, storage, a feedstock contract and a buyer contract, all locked for a decade or more. Interest arrives early. What arrives late is lenders willing to hold tenor, cover imported equipment and accept waste-feedstock risk.

Development finance institutions and export credit agencies can finance your plant, and DFI and ECA financing follows two different rulebooks. DFIs lend, take equity positions and issue guarantees. ECAs cover exported equipment and related civil works through insurance, direct loans or interest support. That is the direct answer to the question you are asking. The wider route sits in how to finance a SAF project.

This article covers what each institution type funds and what it refuses, the rules that fix ECA terms, how bilateral and multilateral players fit together, and two financings that already closed, in Pakistan and Brazil.

In short

  • Development finance institutions bring long tenor, guarantee instruments and project preparation capacity that commercial lenders will not supply alone.
  • Export credit agencies cover the exported equipment portion, typically 85% to 95% of eligible risks, with commercial banks keeping the remainder.
  • OECD Arrangement rules fix maximum coverage, local cost limits, maximum repayment tenor and minimum pricing for every participating ECA.
  • Blended finance uses a small concessional tranche as a catalyst to pull senior commercial debt in on competitive terms.
  • Long-term offtake with a credible buyer is the condition that unlocks flows, and it carries as much weight as feedstock.
Facebook
Twitter
LinkedIn

In this article

What development finance institutions actually bring to a SAF project

A DFI brings three things a commercial bank rarely brings before FID: tenor matched to the asset, instruments that absorb political and transfer risk, and a preparation process that forces the project to become bankable.

The Air Transport Action Group fact sheet of March 2023, more than two years old as I write this, sizes the opportunity at up to 1,450 billion USD of investment to 2050, an average of 48 billion USD a year. The same source argues that multilateral development banks and DFIs matter as much on project preparation and pipeline availability as they do on capital itself.

Two pillars decide whether money moves. Feedstock and offtake carry equal weight. A plant with secure waste supply and no buyer contract fails credit committee. A plant with a buyer contract and no reliable feedstock fails technical review. Competition for HEFA feedstock, used cooking oil in particular, is a real concern across Southeast Asia, and lenders now diligence it as hard as they diligence the offtaker.

What this means for you: use DFI preparation as a hard stress test. Its environmental and social review, its feedstock checks and its reading of your offtake will shape the package long before a commercial bank prices the debt.

What an export credit agency covers, and what it will not touch

An ECA exists to support exports from its own country. That single fact drives everything. National content is required, often 50% or more of contract value, and eligible costs follow the equipment. Machinery comes first. Civil works and local costs are covered only marginally.

The product set is wider than most sponsors expect: full-cover export credit insurance for commercial and political risk, political-risk-only insurance, direct loans as offered by US Exim and JBIC, interest support through the CIRR rate, and pure guarantees. Eligibility is screened on national content, eligible costs, country risk, borrower creditworthiness, and environmental and social review.

In practice an ECA covers 85% to 95% of eligible risks. The rest stays with commercial banks, which is why an ECA package and a bank syndicate are built together rather than in sequence. Two pages sit next to this one: development finance institutions and SAF mandates.

Scale matters when you choose a counterpart. PwC reported in April 2024, a source now more than two years old, that 115 ECAs were officially active in 2021, with average medium and long-term official support led by China at 11 billion USD, Italy at 10.9 billion USD, Germany at 7.2 billion USD, France at 5.9 billion USD and Sweden at 5.4 billion USD.

What this means for you: ask early which equipment packages carry national content in the ECA’s home country. If your main equipment qualifies, the conversation starts there. If nothing qualifies, the ECA route closes fast.

The OECD Arrangement: the rules that fix ECA terms

The OECD Arrangement, commonly called the OECD Consensus, sets the ceiling for every participating ECA. Maximum cover is 85% of the value of the export contract, with 15% paid as down payment. Local costs are eligible up to 40% under Category I and 50% under Category II. Maximum repayment runs to 15 years, with longer tenor available for climate projects. Pricing follows a minimum CIRR rate plus a minimum premium set by country risk on a scale from 0 to 7. Principal repayments must be at least semi-annual.

One practical point: China is not a Participant to the OECD Arrangement, so equipment sourced there is priced under a different regime.

Three pages sit next to the Arrangement in your own process: how to reach FID on a SAF project, sustainable aviation fuel equity in Southeast Asia and e-SAF project finance.

What this means for you: work the tenor rule backwards from your offtake. If your buyer contract runs shorter than the ECA’s maximum repayment period, you have a gap to close before you approach anyone.

DFI and ECA financing: bilateral DFIs, multilaterals and the World Bank Group

Two families sit on this market. Bilateral institutions answer to a home government, and an ECA answers to a home government plus a national export mandate. The non-export-tied DFIs named in the market are DFC from the United States, British International Investment from the United Kingdom, DEG from Germany, Proparco from France and FMO from the Netherlands.

Multilaterals split by instrument. IBRD offers partial risk guarantees and partial credit guarantees. IFC provides A loans, B-loans and equity without requiring a sovereign guarantee. MIGA sells political-risk insurance. IDA provides concessional finance. ADB operates across lending and guarantees in Asia.

Coordination is normal at scale. Outside SAF, the Mozambique LNG project shows the pattern: JBIC committed up to 3 billion USD in direct loans, NEXI provided 2 billion USD of political-risk insurance over 18 years, and the senior package reached 14.9 billion USD.

What this means for you: map institutions by instrument, not by name. Decide whether you need a guarantee, a direct loan or equity first, then shortlist the two or three that issue it.

A SAF plant financed by development money: the Pakistan deal, line by line

The Asian Development Bank announced on 4 December 2024 a package of 86.2 million USD to build and operate a SAF plant at Sheikhupura for SAFCO Venture Holdings. The structure reads as follows.

  • 41.2 million USD comes from ADB ordinary resources.
  • 45 million USD comes from syndicated loans, including B-loans issued with the EAAIF, the emerging markets infrastructure debt fund owned by PIDG and managed by NinetyOne, and with the ILX.
  • IFC provides a parallel syndicated loan.
  • ADB is lender of record for the B-loans and mandated lead arranger and bookrunner.
  • The ordinary-resources component is activated under IF-CAP, making this the first project financed under that climate leverage guarantee mechanism.

The project carries firsts: the first privately led SAF initiative in Asia and the Pacific, the first SAF project financed by ADB, and the first private SAF operation in ADB’s developing member countries outside China.

The plant is sized at 200 kilotonnes a year on waste-based feedstock including used cooking oil. Long-term offtake is signed with Shell Eastern Trading for up to 145,000 tonnes a year. Output is 145,000 tonnes of SAF and 18,000 tonnes of bio-naphtha a year, avoiding up to 500,000 tonnes of CO2 equivalent a year. The operator already runs a 50,000-tonne-a-year biodiesel plant at Sheikhupura. Aviation accounts for roughly 2.5% to 3.5% of global CO2 emissions, and waste-based bio-SAF cuts those emissions by up to 85%.

What this means for you: the package is a template. Ordinary resources for the sponsor-side credit, syndicated B-loans for institutional debt, a parallel loan from another DFI, and a named offtaker holding a long-term contract.

Blended finance, guarantees and concessional tranches: what public money absorbs

Public money does not fund the plant. It absorbs the risks that keep commercial debt out.

The Air Transport Action Group fact sheet of March 2023, more than two years old, describes the mechanism plainly: a small share of concessional public funds acts as a catalyst, long-term subordinated debt that is partly concessional makes room for senior commercial debt on competitive terms, and public money helps with currency risk.

Guarantees do the same job on the risk side. MIGA sells political-risk insurance. IBRD issues partial risk guarantees and partial credit guarantees. ADB’s ordinary-resources tranche in the Pakistan deal was unlocked by IF-CAP, a climate leverage guarantee mechanism.

The order matters. Concessional and subordinated layers sit first, senior commercial debt sits behind them, and the offtaker’s credit sits under all of it.

What this means for you: size the concessional tranche to the specific risk you cannot place, currency risk or political risk for instance, rather than to the whole debt requirement.

When commercial banks join DFI and ECA financing: what the Brazil package shows

Commercial banks re-enter once the risk stack is settled. The Asset reported on 27 May 2026 that Acelen Renewables signed a financing package of 1.5 billion USD for a SAF plant in Bahia, in the north of Brazil, with a capacity of 20,000 barrels a day of SAF and diesel, and HSBC leading the financing. Beyond that lead, the article sits behind a paywall and I will not add to it.

The read-across for Southeast Asia is about sequencing. An ECA covers 85% to 95% of eligible risks and leaves the rest with the banks, and PwC noted in April 2024, more than two years ago, that an ECA can form a syndicate with commercial banks before financial close and operate as a group.

What this means for you: treat the bank syndicate as an instrument you assemble alongside the public money, not as a step that follows it.

How to approach DFI and ECA financing with your own SAF project

Order of operations, based on what these institutions actually screen for.

  • Fix the two pillars first: a long-term offtake contract with a credible buyer, and a feedstock position you can evidence, including used cooking oil supply under HEFA competition.
  • Decide which instrument you need. An equipment-heavy import cost points to an ECA. Preparation, tenor and guarantee needs point to a DFI.
  • Check national content. ECA eligibility starts with exported content, often 50% or more of contract value.
  • Prepare for environmental and social review before you ask for a term sheet. Both routes screen it.
  • Build the layers: concessional or subordinated public money first, senior commercial debt behind it, equity from your investors alongside.
  • Expect multiple institutions. The Pakistan deal ran through ADB, IFC, EAAIF, ILX, PIDG and NinetyOne on one plant.

Preparation is where most time is lost. The ATAG fact sheet of March 2023, more than two years old, is explicit that multilateral banks and DFIs matter as much on project preparation and pipeline availability as on capital itself.

What this means for you: arrive with offtake, feedstock, national content and a preferred instrument already decided. The institutions will run the rest of the screening themselves.

Sources

Frequently asked questions

Neither has to come first, but they answer different screens. An ECA starts from exported content and eligible equipment costs. A DFI starts from project preparation, environmental and social review and the borrower’s credit. In the Pakistan deal the two ran in parallel: ADB held ordinary resources and acted as lender of record for the B-loans, while IFC provided a parallel syndicated loan.

Only partly. Equipment is the eligible core, and civil works and local costs are covered marginally. Under the OECD Arrangement local costs are eligible up to 40% under Category I and 50% under Category II, against a maximum cover of 85% of export contract value with a 15% down payment. Beyond that, an ECA generally covers 85% to 95% of eligible risks and commercial banks hold the rest.

Yes, treat it as a precondition. The ATAG fact sheet of March 2023, more than two years old, names long-term contracts with rated buyers as the condition that unlocks flows. The Pakistan deal shows what good looks like: long-term offtake with Shell Eastern Trading for up to 145,000 tonnes a year, matched to a plant producing 145,000 tonnes of SAF.

Public money covers risk, not the plant. A small concessional share acts as the catalyst that makes senior commercial debt feasible, and guarantees or political-risk insurance cover the rest, through MIGA, IBRD partial risk and partial credit guarantees, or an ECA product.

Want a clear read on which institution fits your instrument?

A short call is usually enough to see where your project stands.

If you are building a SAF project in Southeast Asia and want a clear read on which institutions fit your instrument, your feedstock and your offtake, let’s talk through it. I offer project finance support for teams heading into diligence and FID.

I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia