SAF Project Development Stages: From Concept to Final Investment Decision

10 min read  ·  Oct 2, 2026  ·  By Alex

saf project development stages

A sustainable aviation fuel project advances through a fixed sequence of gates between the first idea and committed capital: concept development, feasibility, pre-FEED (pre-front-end engineering design), FEED (front-end engineering design), FID (final investment decision), EPC (engineering, procurement and construction contract) and operations, and my page on how to reach FID covers that route in depth. Each stage delivers one defined output, costs a defined amount and ends in one defined decision, so you are crossing a chain of separate approvals rather than one gap.

I have read that chain in three places: the World Economic Forum and Kearney white paper of February 2025, the ICAO Finvest Hub guide of October 2026, and the e-fuels.com timeline of February 2026. They agree on the order of the stages and differ mainly in how they group them, which changes how you budget for them.

In short

  • Sequence: concept, feasibility, pre-FEED, FEED, FID, EPC, operations, each a gate with one output, one cost and one decision.
  • Timing: 5 to 7 years from concept to first fuel, or 2 to 3 years for HEFA co-processing on existing refinery infrastructure.
  • Cost: 0.5 to 2 million USD to reach a feasibility verdict, 10 to 15 million USD for engineering and licensing, 15 to 30 million USD to negotiate financing and offtake.
  • Pillars: feedstock and offtake (the contract that sells your fuel), both fixed before the FEED is finished.
  • Money: equity first, then concessional and development capital, then debt, spread across 10 financial levers.
Facebook
Twitter
LinkedIn

In this article

What the stages actually are

The ICAO Finvest Hub names the chain without gaps: concept development, feasibility, pre-FEED, FEED, FID, EPC and operations. The World Economic Forum and Kearney compress the same journey into five phases, from conceptualisation and pre-feasibility through feasibility and FEED, project financing and FID, construction and implementation, to commissioning and operation. Neither account leaves a discretionary step in the middle.

Each stage is a gate in the strict sense. It has one defined output, one defined cost and one defined decision taken by people who are not you: a lender, an offtake buyer, a permit authority or your own board. As of August 2024, 90 refineries had produced at least one batch of SAF, about 60 had passed FID and were under construction, and more than 200 sat between conceptualisation and preparing for FID. ICAO marks on its chart the zone it labels the economic valley of death, where the capital requirement is low and the project risk is high, and it places most announced SAF projects there. The financing logic behind the same gates is set out in how to finance a SAF project.

What this means for you: treat every stage as a submission with an acceptance test. Write down the output, the cost and the decision owner for each of the seven gates before you spend anything, and you will always know which gate you are standing in front of.

How long each stage takes

The e-fuels.com timeline of February 2026 gives the durations I plan against: feasibility 6 to 12 months for site selection, technology choice and preliminary economics; pre-FEED 6 to 12 months for process design, a cost estimate at plus or minus 30 percent and the environmental assessment; FEED 12 to 18 months for detailed engineering, a cost estimate at plus or minus 15 percent and permitting; FID plus financial close 6 to 12 months, when the offtake is signed, debt is committed and equity is closed; construction 24 to 36 months; commissioning 3 to 6 months.

Add that up and you get 5 to 7 years from concept to first fuel for a standalone plant. HEFA co-processing is the exception at 2 to 3 years because it uses existing refinery infrastructure instead of building new. The same source reports that 88 percent of the SAF pipeline is pre-FID, and that the bottleneck is the 2 to 3 years of development before FID. ICAO marks its development cycle axis at 12, 24, 36, 48 and 96 months since the start, which is a useful ruler for a plan of your own.

The World Economic Forum puts the journey from conceptualisation to FID at 2.5 to 5 years, then 2 to 3 years to reach commissioning, then a further couple of years to full-scale operations. A FOAK facility can take up to 8 years from a project’s inception to becoming operational.

What this means for you: budget the calendar before you budget the money. The 2 to 3 years before FID is where most projects die, so put cash, sponsor attention and a monthly milestone plan against that window first, and treat construction as the easy part of the schedule.

What each stage costs

The World Economic Forum bands the pre-FID spend clearly. Feasibility studies, initial market research and concept development run about 0.5 to 2 million USD. Engineering, licensing and feasibility studies typically cost 10 to 15 million USD, and costs exceed 100 million USD for FOAK advanced pathways. Legal fees, financial structuring and support to negotiate and finalise financing and offtake agreements come to 15 to 30 million USD.

The plant sits on top of that, and the pathway sets the number: 0.7 billion USD for a 500 kt HEFA plant, rising to more than 6 billion USD for a 500 kt PtL plant. The same white paper puts total CapEx (capital expenditure) for the sector at 19 billion to 45 billion USD by 2030.

The first real cheque a developer writes is FEED. Everything before it can be funded from the sponsor balance sheet, grants and a small study budget. Everything after it requires lenders to believe the estimate.

What this means for you: separate your budget into study money and plant money, and never mix the two in a pitch. The 10 to 15 million USD engineering line is what convinces a lender that the 0.7 billion USD plant number is real, so protect it.

Pathway, feedstock and offtake

Feedstock and offtake are two equal pillars, and both must be fixed before the FEED is finished. The pathway choice, HEFA, alcohol-to-jet, gasification Fischer-Tropsch or power-to-liquid, drives CapEx, schedule and permit complexity, and it cannot be chosen apart from the feedstock you can actually contract for.

HEFA is the most mature pathway but it is feedstock-limited: the same used cooking oil is contested by biodiesel, renewable diesel and SAF producers, so a letter of intent is not security. e-SAF depends on renewable power availability, hydrogen cost and CO2 sourcing, and it carries the highest CapEx of the four. AFRY’s undated ecosystem page, which I consulted in November 2026, reports that projects stall on the same hurdles: high costs, uncertain offtake, regulatory complexity and pathway decisions. The commercial shape of an e-SAF plant is set out in e-SAF project finance.

What this means for you: write the feedstock contract and the offtake contract in the same week, and let neither be signed alone. If your pathway works with only one supplier and one buyer, you do not yet have a project, you have a hope.

Permits, certification and policy

Site consents and enabling infrastructure rank 6 on the ICAO bankability checklist, and policy support ranks 10, which tells you both matter but neither is the first thing a lender reads. Permitting sits inside the FEED window for a reason: the environmental assessment starts at pre-FEED and the detailed permit work runs alongside detailed engineering.

Certification runs on a separate clock. ASTM approval of a technology follows a four-step approach from fuel specification review to full aircraft and engine testing, which can take 3 to 6 years and cost up to 6 million USD. A CORSIA (Carbon Offsetting and Reduction Scheme for International Aviation) certification plan and audit are needed before international credits can be claimed.

Policy support is not a buyer. A mandate sets a floor you must beat, not a customer who will sign, and my page on SAF mandates explains where those floors sit and what they do not cover.

What this means for you: start the ASTM clock and the permit scoping at pre-FEED, not at FEED. A 3 to 6 year approval process left on the critical path will otherwise arrive after your offtake is supposed to start.

The money that closes the gate

Equity comes first, then concessional and development capital, then debt. The World Economic Forum identifies 10 financial levers, from research and innovation grants to guarantees, strategic investors, long-term offtake agreements, infrastructure investors and green bonds. Blended finance, where public and private capital are combined, is how most of these get assembled in practice.

The most persuasive lever is a long-term offtake. IAG’s 14-year agreement with PtL producer Twelve is the example the white paper uses, and it is the reason a lender can underwrite a plant that will not produce fuel for years. Debt without offtake is a conversation about risk; offtake without debt is a conversation about pace.

For a Southeast Asian developer the equity question comes early, and my notes on sustainable aviation fuel Southeast Asia equity set out who writes those cheques. Where public capital has to de-risk the early stages, development finance institutions are the natural counterpart.

What this means for you: sequence the asks instead of making them all at once. Take equity and guarantees to the point where the offtake and the permit path are credible, then bring debt in, because the order in which you ask determines the price you pay.

What I check at each gate

The ICAO Finvest Hub bankability checklist gives me the reading order for any file. Rank 1 is the project narrative, rank 3 is construction risk, rank 6 is infrastructure and permits, and rank 10 is policy support; other ranks exist, but these four decide most first impressions. The process itself has only two required stages, the entry checklist and the bankability checklist, with partner-led support available afterwards for projects in later stages.

A submission has to be complete before it is useful: a named sponsor, project lead and focal point, the scope, location and scale, study findings and current status, the estimated total funding required and the immediate funding goal. ICAO puts the submission and guidance step at about 0 to 2 months. Pitch to investors is hosted at events such as GSAM in June 2027.

What this means for you: run the bankability checklist on your own file before a lender runs it on you. If the project narrative, the construction risk, the infrastructure and permits, and the policy support sections are thin, no amount of energy in the room will close that gap.

The five decisions I would take first

First, fix the feedstock and offtake before any engineering spend, because they are two equal pillars and the FEED cannot be priced without them. Second, choose the pathway against the feedstock you can actually get, not the pathway that reads best on paper. Third, budget the pre-FID window as a 2 to 3 year cash plan with monthly milestones. Fourth, run the bankability checklist on your own file first. Fifth, sequence the equity, guarantee and debt asks in that order.

Those five moves are also the quickest test of whether a concept survives contact with reality. AFRY notes that successful projects align commercial, regulatory, infrastructure, technical and financing dimensions from the outset, and by 2050 several thousand SAF and cleaner energy projects will be required, so the bar will not get lower with time.

What this means for you: fix feedstock and offtake first, choose the pathway against the feedstock you can actually contract, carry the 2 to 3 years to FID as a funded plan, check your own file, then sequence equity, guarantees and debt. Two pillars, one sequence, seven gates.

Sources

Frequently asked questions

pre-FEED is a stage of its own: it delivers process design, a cost estimate at plus or minus 30 percent and the environmental assessment in 6 to 12 months. FEED delivers detailed engineering, a cost estimate at plus or minus 15 percent and the permitting package in 12 to 18 months. The first tells you whether the project is worth engineering; the second gives a number a lender can size debt against.

Plan on 2.5 to 5 years. The e-fuels.com breakdown gives 6 to 12 months for feasibility, 6 to 12 months for pre-FEED, 12 to 18 months for FEED and 6 to 12 months for FID and financial close, which is where the 2 to 3 years of pre-FID development sits. HEFA co-processing can compress the whole route to 2 to 3 years because it sits inside an existing refinery.

About 0.5 to 2 million USD for feasibility studies, initial market research and concept development; 10 to 15 million USD for engineering, licensing and feasibility studies, with costs exceeding 100 million USD for FOAK advanced pathways; and 15 to 30 million USD for legal fees, financial structuring and support to negotiate financing and offtake agreements.

The window before FID. 88 percent of the SAF pipeline is pre-FID, and the 2 to 3 years of development between concept and FID is the zone where the capital requirement is low and the project risk is high, which ICAO labels the economic valley of death.

Want this stage sequence mapped onto your file?

A short call is usually enough to see where your project stands.

If you want your own file read against these gates before a lender sees it, I do that work inside my project finance practice, from the concept note through the bankability checklist to the FID submission.

I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia

I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.

More about me·Get in touch

Facebook
Twitter
LinkedIn

Related articles