We Connect Asia

WtE

Waste-to-Energy Policy in Singapore, Malaysia and Indonesia: What Public Support Actually Pays For

10 min read  ·  Dec 14, 2025  ·  By Alex

wte policy singapore malaysia indonesia

When I read a waste-to-energy policy, which means burning municipal waste to make power, I look for the instrument, the payer and the date it takes effect. The answer differs by market. In Southeast Asia, the waste to energy policy southeast asia question now splits into three instruments. Indonesia fixes power at USD 0.20 per kWh for a 30-year power purchase agreement, a contract to sell electricity to one buyer for a set term, signed by the state electricity company within 10 working days of construction permits under a regulation of 10 October 2025. Malaysia has put 18 plants and up to 600 megawatts on paper for 2040, with Sungai Udang budgeted at 660 million ringgit and due to run by 2029. Singapore answered a single bid in 2001 with a take-or-pay tender in 2005, meaning the buyer pays for 100 percent of the capacity whether the plant burns or not. I read public support as an instrument with a payer, not as a target.

I take them in the order a developer decides: the instrument each country signed, what the Indonesian text guarantees and what it leaves open, what Malaysia committed, how Singapore pays for the same tonnage, where public support stops, and what it delivered in 2026. Each section closes with the move I would make next.

In short

  • Indonesia: A regulation of 10 October 2025 fixes power at USD 0.20 per kWh for 30 years, signed within 10 working days.
  • Malaysia: 18 plants and up to 600 megawatts targeted for 2040, one plant due by 2029.
  • Singapore: A 2005 take-or-pay tender paying 100 percent of capacity, plant running from 2009 at 800 tonnes a day.
  • Limits: Support stops where the waste stream and the budget line are not guaranteed.
  • Delivery: Five project milestones between March and August 2026.
Facebook
Twitter
LinkedIn

In this article

The instrument each country signed

The August 2026 legal briefing on Indonesia’s new regulation describes one national instrument. Eligibility opens to any city or regency that can supply at least 1,000 tonnes of waste a day throughout operations, with suitable land and funded collection and transport. The power price is a simplified fixed feed-in tariff, which is the price paid for each unit of electricity generated, of USD 0.20 per kWh for a 30-year contract that the state electricity company must sign within 10 working days of the pre-construction permits, with no negotiation and no escalation.

Environmental licences are issued within two months of a complete file and are deemed granted if the period lapses, and each local government must commit the agreed 1,000 tonnes a day for the whole of operations. An earlier regulation of 2018 had already named twelve cities for waste-to-electricity, so what changed in 2025 is eligibility.

What this means for you: I can price the power, date the signature and date the permit, but I cannot price the plant until the local authority signs its volume commitment.

What the Indonesian text guarantees, and what it does not

The programme figure reported in August 2026 is about 33 locations nationwide. That is a statement of programme, not a list of plants in operation. Financing is expected in part from an issuance of about IDR 50 trillion of Patriot Bond, identified principally for waste-to-energy and other renewables. A first phase covers Bali, Bogor, Bekasi and Yogyakarta.

Legok Nangka, the first waste-to-energy public-private partnership in the country, is sized at about 2,131 tonnes a day and 40.79 MW from six Greater Bandung municipalities, and it reached commercial close before ground breaking in July 2026. About 200 entities have expressed interest and 85 qualified in a second selection wave. The tonnage sits behind all of it, and the circular waste view of the sector explains the gap: 56.63 million tonnes of waste generated in 2023, with 39.01 percent managed and 60.99 percent left unmanaged.

What this means for you: I treat 33 locations as a pipeline claim and Legok Nangka as the only dated proof point, then test both against the managed share of the waste stream.

What Malaysia has committed to

The Xinhua report of April 2026 puts 18 waste-to-energy plants nationwide expected to generate up to 600 megawatts of renewable energy by 2040, under a national roadmap targeting 70 percent renewable capacity by 2050. Sungai Udang in Melaka broke ground on 2 April 2026, is budgeted at 660 million ringgit (163 million US dollars), is expected to be fully operational by 2029 and is designed for up to 1,000 tons of solid waste a day and up to 22 megawatts.

Plainly, 18 plants and 600 MW are a target with a year attached, not capacity in operation. The statement names a date, a capacity and a budget for one plant, and stops there. Tonnage, calorific value and emissions limits are plant-level questions, and the plant guide I work from settles them before the target is discussed.

What this means for you: I budget the plant I can build and date every megawatt to the year it is promised, so a 2040 target never enters the base case.

How Singapore pays for the same tonnage

The Infrastructure Asia overview of waste management in Asia records the sequence. The 2001 call for the fifth waste-to-energy plant drew a single bid, because the agency wanted the developer to carry finance, design, operational and demand risk. The 2005 re-tender introduced take-or-pay, under which the government buys 100 percent of the incineration capacity or pays a penalty, so the state carries demand risk through a capacity payment, which is a fixed sum for having capacity available, whatever the utilisation. The plant was awarded in 2005 and started in 2009 treating 800 tonnes a day for about 22 MW.

Waste management in the region runs mostly on public-private partnership and build-operate-transfer models, which makes tipping fees, the payment made for each tonne delivered, feed-in tariffs and refuse-derived fuel, fuel prepared from sorted municipal waste, the critical revenue lines. I map those lines through project finance in Southeast Asia.

What this means for you: where no buyer will take 100 percent of the capacity, I need a guaranteed waste stream and a guaranteed revenue line, because demand risk still has to sit with someone.

Where public support stops

More green financing is coming from development banks, but not every country will have an Asian Development Bank ready to take debt or equity, so the public and private sectors have to work together: the Ramboll interview of January 2025. That is a shared task, not a standing offer, and it leaves the structure of each deal carrying the risk a lender will not.

Malaysia and Thailand are expected to move fastest, with Thailand channeling support through subsidies, tax incentives and an enhanced feed-in tariff for plants below 10 megawatts. Regional electricity demand is expected to grow 4 percent annually to 2035, against 3 percent growth for energy demand overall. Governments must be convinced first, then hold a stable political framework for long-term foreign investment. A public guarantee of the waste stream sits with the public sector and everything else with the private one, so offtake terms for waste-to-energy and biogas are where I start.

What this means for you: I ask who guarantees the tonnage and who guarantees the budget line before any incentive enters the model.

What the support delivered in 2026

The regional roundup of August 2026 lists five milestones. On 19 March 2026 the Tuas South upgrade was contracted to run to 2035 at about SGD 890 million and 3,000 tonnes a day. Construction started on 8 July 2026 in Denpasar, Bali, for more than 500,000 tonnes a year at IDR 3 trillion, about 184 million USD, due late 2027. Sungai Udang launched on 2 April 2026 at 1,056 tonnes a day and 22 MW. On Nut in Thailand first synchronized on 10 April 2026 at 1,000 tonnes a day. A Hung Yen plant was announced on 6 March 2026 at 1,600 tonnes a day and 40 MW.

The driver is energy security: 60 percent of the region’s crude oil and one third of its gas imports came from the Middle East before the crisis that began in March 2026, and the import bill could rise to 245 billion USD by 2035 from 80 billion USD in 2024. Against that bill, the offtake agreements behind these plants are a small line.

What this means for you: five milestones in six months is delivery, and I date every one before I count it as evidence.

What I ask a ministry before I model a subsidy

Five questions, in this order:

  • Which text carries the support, and what is its date of effect?
  • Is there a budget line behind it?
  • Who signs the power purchase agreement, and within how many days?
  • Is the price fixed or negotiated, and does it escalate?
  • What happens to the volume commitment if the local authority cannot deliver?

I ask in writing and I ask for the text, not for the summary, because a date of effect separates a signed instrument from an announced intention. The answers are the model: a 30-year contract, a signature inside 10 working days, environmental licences inside two months of a complete file and a committed 1,000 tonnes a day.

What this means for you: if a ministry cannot date the text, name the payer or commit the tonnage, the subsidy is not yet an input to my cash flow.

How I would write a policy annex in a credit paper

I keep it to four dated rows:

  • Indonesia, October 2025: USD 0.20 per kWh for 30 years, signature within 10 working days.
  • Malaysia, April 2026: 18 plants, up to 600 MW by 2040.
  • Singapore, 2005: take-or-pay, plant running from 2009 at 800 tonnes a day.
  • Region, March to August 2026: five project milestones.

Each row names an instrument, a payer and a date, and nothing else goes into the annex. Announced targets sit in a separate paragraph, labelled as targets, because a credit paper is tested line by line. Where a row has no payer, I mark it as an intention and carry it outside the base case.

What this means for you: an annex that separates a signed instrument from an announced target is the part a lender can actually test, and it is the part I write first.

Sources

Frequently asked questions

A regulation signed on 10 October 2025 opens eligibility to any city that can supply at least 1,000 tonnes of waste a day, fixes the power price at USD 0.20 per kWh for a 30-year contract the state electricity company signs within 10 working days, and requires environmental licences within two months of a complete file. Eligibility also requires suitable land, funded collection and transport, and a local commitment to the agreed volume throughout operations.

18 plants nationwide by 2040 producing up to 600 megawatts under a roadmap that targets 70 percent renewable capacity by 2050, with the first flagship plant budgeted at 660 million ringgit, designed for 1,000 tons a day and 22 megawatts, due to be operational by 2029. It is a target with a year attached, not capacity in operation.

By paying for capacity rather than for electricity: a 2001 tender drew a single bid, and the 2005 re-tender adopted an arrangement under which the government buys 100 percent of the incineration capacity or pays a penalty. The state carries the demand risk through a capacity payment, which is a fixed sum for having capacity available, and the plant has run from 2009 at 800 tonnes a day.

No. 18 plants by 2040 and about 33 locations are programme figures with a year attached, while the measured line is a plant that runs, such as the 800 tonnes a day operating since 2009.

Not sure your project would survive a credit conversation?

A short call is usually enough to see where your project stands.

If you are choosing between these three markets, I map the instrument, the payer and the date onto your cash flow before you commit to a site. The starting point is grants and incentives support, where I set out which public money a given project can be matched to and what conditions come with it.

I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia

I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.

More about me·Get in touch

Facebook
Twitter
LinkedIn

Related articles