We Connect Asia

Hydrogen

Hydrogen Demand in Southeast Asia: Who Buys, and How Much Is Signed

10 min read  ·  Dec 2, 2025  ·  By Alex

hydrogen demand southeast asia

Southeast Asia consumed about 4 Mt of hydrogen in 2024, and that consumption sits in three uses that already exist: ammonia at 49 percent, refining at 31 percent and methanol at 20 percent of the 2024 total. If you read hydrogen demand southeast asia by buyer rather than by project, the country split of that same 2024 total is Indonesia at 35 percent, Malaysia 22 percent, Viet Nam 15 percent and Singapore 12 percent. Announced low-emissions projects in the region add up to 12 percent of that current demand, and only 6 percent of the announced capacity had reached a final investment decision by December 2025. Who buys is therefore a narrower question than who consumes, and I start from the hydrogen, PtX and e-fuels hub above this page.

I separate three things that write-ups in this region routinely blur: what the region actually consumes today, who signs for it, and what the announced pipeline really promises. Announcements, national strategies and export intentions each read like demand on a slide, and none of them is. I take those three apart below.

In short

  • Consumption: 4 Mt used in Southeast Asia in 2024: ammonia 49 percent, refining 31 percent, methanol 20 percent.
  • Concentration: Indonesia 35 percent, Malaysia 22 percent, Viet Nam 15 percent, Singapore 12 percent of that 2024 total.
  • Commitment: firm offtake below 2 Mtpa worldwide, 5 percent of announced output for 2030.
  • Pipeline: announced regional projects equal 12 percent of current demand, with 6 percent at final investment decision in December 2025.
  • Gate: capital costs at 15 percent in emerging economies in 2025, three times the advanced-economy level.
Facebook
Twitter
LinkedIn

In this article

What the region actually buys

Hydrogen demand means hydrogen consumed, not hydrogen announced: molecules that are burned or fed into a process and paid for by a buyer. Low-emissions hydrogen means production by electrolysis, which splits water using electricity, or by a fossil route with carbon capture. On that definition, Southeast Asia consumed 4 Mt in 2024, from the December 2025 Southeast Asia briefing published by the International Energy Agency.

The three uses that carry that volume already exist and already pay. Ammonia combines hydrogen with nitrogen and moves as a fertiliser; refining uses hydrogen to remove sulphur and upgrade heavy crude fractions; methanol is a chemical feedstock. These buyers invoice today, which is why I start there rather than with a list of projects.

Three contract words finish the vocabulary: an offtake is the agreement under which a buyer takes the molecule, a firm offtake is one the buyer is committed to, and a final investment decision is the point at which capital is committed to build.

What this means for you: I size a plant against consumption paid for today, and I look for a hub, meaning a concentrated industrial or port location where production and users sit close together, because that is where a buyer already stands.

Where that demand sits in the world

Global hydrogen demand passed 100 Mt in 2025, driven almost entirely by industry and refining, with new applications still a very minor share, in the 2026 review. Low-emissions production grew 20 percent in 2025 to almost 1 Mt, and may pass 1 percent of global production for the first time in 2026.

The 2025 review puts the earlier year at close to 100 Mt in 2024, up 2 percent on 2023, with new applications under 1 percent and concentrated in biofuels production, while producing that hydrogen still consumed 290 bcm of natural gas and 90 Mtce of coal in 2024.

A market that is large, old and grey is not by itself a market for what you want to build, because the grey volume is the incumbent your plant prices against. I set out what low-emissions hydrogen means for a project there.

What this means for you: I do not read regional consumption growth as demand for your product, since almost all of it is conventional hydrogen that a new plant has to undercut rather than supply.

Who signs, and for how long

Cumulative firm offtake agreements amount to less than 2 Mtpa, merely 5 percent of what announced projects could produce by 2030, and the five key questions section of that review warns that demand uncertainty can put the whole sector at risk, because producers need reliable buyers to justify large investment.

The wider stack reads the same way: 7 Mtpa of offtake announced across 2021 to 2025, of which only 1.6 Mtpa is firm, and 16.5 Mtpa of export projects for 2030, of which only 4.2 Mtpa has an identified buyer.

Announced volumes therefore look contracted while mostly they are not. I treat the paper as the only evidence: the offtake agreement, read clause by clause, tells me whether a buyer is obliged or merely interested.

What this means for you: I ask for the firm slice before I size anything, because with less than 2 Mtpa of firm offtake in 2025 the rest of the announced sector has no committed buyer.

The three uses that already carry the volume

By use, Southeast Asia in 2024 ran ammonia 49 percent, refining 31 percent and methanol 20 percent. By country in 2024, Indonesia took 35 percent, Malaysia 22 percent, Viet Nam 15 percent and Singapore 12 percent. In 2024 hydrogen was 1 percent of regional energy-related carbon dioxide emissions and 8 percent of gas supply.

The region is a net ammonia exporter, though only Indonesia and Malaysia export; in 2023 Malaysia alone stood at 73 percent of regional exports and the region at 17 percent of world ammonia exports. Regional crude steel output covers 60 percent of its own hydrogen demand in 2024.

What the region already trades is a derivative, meaning a molecule that carries hydrogen to a buyer in a form easier to move and store than the molecule itself. Ammonia is that first door, and I look at green ammonia as the way through it.

What this means for you: I pitch a local plant to an ammonia, refining or methanol counterparty that already consumes the volume, because those three uses carried all of the 4 Mt in 2024.

What the announced pipeline promises

Announced low-emissions projects in Southeast Asia total 12 percent of current regional demand, and only 6 percent of announced capacity had reached a final investment decision in December 2025. The region could hold nearly 11 Mtpa of production potential below 6 USD/kg by 2030, most of it in Indonesia. The three named barriers are a high cost of capital, low renewable penetration in the electricity mix and weak incentives to switch fuels in existing industrial uses.

Nationally owned companies have set targets: Gentari at 1.2 Mtpa by 2030 with proprietary PEM technology, Pertamina New Renewable Energy at 1 Mtpa by 2030 with 17 projects totalling 1.8 Mtpa in 2025, nine pilot projects from the Philippines, a 1.2 Mtpa ammonia plant with 5 percent blending for power generation by 2030 in Thailand, and a refiner running 180 kbpd and 83 ktpa of hydrogen.

Across emerging economies more than 9 Mtpa is possible by 2030, about 25 percent of announced global production, yet in 2025 only 0.5 percent of projects carried committed investment against 9 percent worldwide, 80 percent were export-oriented, meaning built to ship the molecule abroad rather than sell it locally, and capital costs reached 15 percent, three times the advanced-economy level.

What this means for you: cost of capital, the return a project must promise its financiers, is the first number I test against 15 percent in 2025, and I check who is actually building with the regional developers map.

What I do not count as demand

First, announced capacity is not demand: 12 percent of the 4 Mt used in 2024, with only 6 percent of announced capacity at final investment decision in December 2025, is not a market. Second, a national strategy is not a scheme: five countries have strategies as of December 2025, three are working on certification, and none has a scheme in place.

Third, consumption of conventional hydrogen is not demand for low-emissions hydrogen, because the buyer has to pay the difference. Fourth, an export intent is not a contract, given that only 4.2 Mtpa of 16.5 Mtpa of export projects for 2030 has an identified buyer.

Fifth, a supply curve below 6 USD/kg is potential, not a pipeline, since only 6 percent of announced capacity has committed capital in 2025. Nearly 11 Mtpa below 6 USD/kg by 2030 tells me where cost could land, not who will pay it.

What this means for you: I strike all five from my demand case before I model revenue, and what survives that filter is what I take to a buyer.

What this changes for a project in Southeast Asia

Nearly 45 percent of the hydrogen from announced production projects worldwide is destined for export, more than 16 Mtpa equivalent by 2030 if all of them materialise, while only 5 percent of export-oriented projects had reached the investment stage, in the full 2025 report from the IEA.

Regional demand also sits physically in a few industrial sites, with existing refining capacity and bunkering concentrated in a handful of locations, and Singapore is the world’s largest bunkering hub. That is the practical case for building next to a hub rather than next to a resource.

Bunkering is where a fuel buyer arrives with a schedule, so I read sustainable maritime fuels as the demand that can be contracted earliest inside a port cluster.

What this means for you: I place the plant inside an industrial or port cluster where refining, ammonia and bunkering already concentrate, because a first buyer is far more likely to sit there than beside the cheapest renewable resource.

The four lines I would put in front of an offtaker

I keep the pack to four dated lines, no more.

Line one, the consumption I can evidence: 4 Mt in 2024, ammonia 49 percent, refining 31 percent, methanol 20 percent, dated December 2025.

Line two, the buyer concentration: Indonesia 35 percent, Malaysia 22 percent, Viet Nam 15 percent and Singapore 12 percent of that 2024 volume.

Line three, the commitment gap: less than 2 Mtpa of firm offtake against 5 percent of announced production for 2030, with only 1.6 Mtpa of 7 Mtpa announced across 2021 to 2025 firm.

Line four, the regional gate: 6 percent of announced capacity at final investment decision in December 2025, and capital costs at 15 percent in emerging economies in 2025.

What this means for you: those four lines, each dated, are what I put in front of an offtaker, because every one of them is checkable and none depends on an announcement.

Sources

Frequently asked questions

About 4 Mt in 2024, equal to 1 percent of regional energy-related carbon dioxide emissions and 8 percent of gas supply that year, with crude steel production covering 60 percent of its own hydrogen demand. Almost all of it is conventional hydrogen, because announced low-emissions projects in the region add up to only 12 percent of that consumption.

Ammonia at 49 percent, refining at 31 percent and methanol at 20 percent of use in 2024; Indonesia at 35 percent of consumption, Malaysia 22 percent, Viet Nam 15 percent and Singapore 12 percent in 2024. The region is a net ammonia exporter, and Malaysia alone accounts for 73 percent of regional exports.

Not at scale. Announced low-emissions projects equal 12 percent of current regional demand and only 6 percent of announced capacity has reached a final investment decision, while nationally owned companies have set targets of 1.2 Mtpa and 1 Mtpa by 2030. Firm offtake worldwide is below 2 Mtpa, or 5 percent of announced production for 2030.

Anchor demand in an existing use and a physical cluster. Firm offtake across 2021 to 2025 was only 1.6 Mtpa out of 7 Mtpa announced, so a long-term contract with a creditworthy buyer in an industrial or port cluster is what the rest of the project waits on.

Not sure your project would survive a credit conversation?

A short call is usually enough to see where your project stands.

If you want the demand side written the way a buyer reads it, I offer offtake agreement support, from evidence pack to contract terms, so the volume you pitch matches consumption somebody already pays for.

I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia