PtL Inputs: CO2 and Power, and What a Lender Checks First
10 min read · Feb 2, 2026 · By Alex
A power-to-liquid plant buys two things before it buys anything else, electricity and carbon dioxide. Also, the electricity is the bigger of the two. At 50 USD per MWh the power price alone contributes 25 to 35 USD per gigajoule of fuel. That figure includes no investment yet. The levelised cost starts climbing quickly once the electrolyser load factor falls below 40 percent. In fact, these two figures are the ptl inputs co2 and power this page exists to price. Also, they follow different logic. The carbon runs from 20 to 30 USD per tonne from a fermentation stream. Direct air capture runs from 400 to 670 USD per tonne. I put this branch under the power-to-liquid explainer. Read that first for the process, then come back here for the two contracts.
I will price four things in order. The power contract comes first, the hydrogen behind it second. The carbon you have to buy comes third. Finally comes what ties them together in one model. I work only from published figures. Every figure carries the date where it appears. I say plainly what is not a secured input.
In short
- Power: At 50 USD per MWh the electricity price alone adds 25 to 35 USD per gigajoule of fuel before any investment or consumable, December 2023.
- Hydrogen: Electricity is the most significant operating cost, so its price is highly site dependent. The technology choice follows the local energy profile, February 2026.
- Carbon: A fermentation stream costs 20 to 30 USD per tonne. Flue gas costs 60 to 80 USD per tonne. Direct air capture costs 400 to 670 USD per tonne, December 2023.
- Load factor: Below 40 percent the levelised cost starts increasing very quickly. The worked example answers with a 40 to 50 percent solar share, December 2023.
- Demand: Cumulative firm offtake agreements stand at less than 2 Mtpa. That is 5 percent of what announced projects could produce by 2030, 2025.
In this article
What a power-to-liquid plant buys
For example, a power-to-liquid plant buys two things and builds one thing. In addition, the purchases are electricity and carbon dioxide, and what comes out is a liquid fuel. Specifically, power-to-liquid means making that fuel from hydrogen and captured carbon dioxide. The electrolyser, for example, is the machine that splits water into hydrogen and oxygen using electricity. Moreover, the load factor is the share of hours the plant runs at rated output. As a result, the levelised cost spreads the investment over the fuel actually made. Therefore, a low load factor pushes more of the plant into every gigajoule.
Meanwhile, CO2 feedstock is the carbon you buy. Also, it arrives from three sources at three very different purities and prices. Fermentation is the biological process that already emits a nearly pure stream. Flue gas is the exhaust of combustion. Direct air capture is carbon pulled out of ambient air. In addition, the balance of plant is everything around the stack, the piping, purification, compression and cooling. Offtake is a contract to buy the fuel later, and final investment decision is when the buyer commits the money.
What this means for you: I write these definitions down before I price anything. They are the vocabulary your technical adviser and your lender will use back at you.
The power contract sets the floor
The 2023 e-fuels report from the International Energy Agency puts the floor plainly. At 50 USD per MWh the power price alone contributes 25 to 35 USD per gigajoule of fuel. That equals 1,000 to 1,500 USD per tonne of oil equivalent before any investment or consumable. The IEA published those figures in December 2023. Annual available hours matter just as much. They set the load factor. Therefore, they decide how much plant investment sits in every gigajoule. With a constant average price the levelised cost starts increasing very quickly once the load factor drops below 40 percent. In its worked example, a 40 to 50 percent share of solar photovoltaic capacity minimises cost. Annual curtailment is 6 percent, against 18 percent on solar alone. Wind alone would curtail 23 percent.
Modelled cases pair 30 and 50 USD per MWh of electricity with 800 and 2,000 USD per kilowatt of electrolyser. In addition, they assume 5 percent cost of capital over a 25 year economic life.
IRENA set the same levers from the other direction in 2020. Electricity falls from 53 to 20 USD per MWh. Full load hours rise from 3,200 to 4,200. Cost of capital falls from 10 percent to 6 percent. Efficiency rises from 65 to 76 percent. I carry that floor into the structuring work that leads to final investment decision.
What this means for you: sign the power side first. Let the rest of the model fall in behind it. On these ranges electricity already sets the floor. That happens before a single equipment quote enters the file.
The hydrogen behind the liquids
For example, the World Bank survey of February 2026 starts where I start: electricity is the most significant operating cost. Also, its price is highly site dependent, so the technology choice has to follow the local energy profile. Moreover, operational flexibility lets a plant take low cost power, and developers are using hybrid designs and battery storage. Also, grid connected projects on power purchase agreements face a different electrolyser choice from projects running their own renewable assets. Efficiency runs 51 to 56 kWh per kilogram for alkaline. PEM runs 53 to 56, and solid oxide runs 35 to 42. Meanwhile, stack durability runs 60,000 to 90,000 hours for alkaline against 40,000 to 60,000 for PEM. Minimum load is 10 percent for modern atmospheric alkaline and 30 percent for pressurised alkaline. PEM needs 10 percent, and solid oxide needs 50 percent.
Modules typically run 5 MW to 100 MW. Utility-scale plants cycle stacks individually. As a result, units can stop when power is expensive.
The five key questions section of the 2025 review adds the share that matters for capital planning. The stack is only 15 to 20 percent of the installed investment. I wrote the molecule side on the green hydrogen page.
What this means for you: match the electrolyser to the local power profile before you price it. Efficiency, minimum load and stack hours are what a lender tests first.
The carbon you have to buy
In fact, apart from ammonia, every e-fuel needs carbon in the form of CO2. Also, stream concentration largely sets the cost of capturing it, as published in December 2023. Fermentation gives a stream that is nearly 100 percent pure, so capture costs around 20 to 30 USD per tonne. Biomass combustion produces flue gas at 10 to 20 volume percent. That raises the cost to 60 to 80 USD per tonne. By contrast, from the atmosphere, direct air capture cost estimates span 400 to 670 USD per tonne. The modelling behind those ranges uses 30, 80 and 400 USD per tonne for the three sources. It also uses water at 2 USD per cubic metre. Meanwhile, the same work flags biogenic CO2.
This is carbon that living matter absorbed recently, and it pairs naturally with biofuels production. Reverse water-gas shift reactors turn CO2 and hydrogen into a synthesis gas. That synthesis gas feeds Fischer-Tropsch synthesis. Engineers still have to demonstrate these reactors at scale. The capture side of that chain is on the carbon capture and storage page.
What this means for you: I quote three carbon numbers, not one. The source you can actually contract decides both your price. It also decides the treatment train you have to build.
Why the two inputs are priced together
Therefore, read them as one contract set rather than two memos. The same load factor that decides the power bill also decides how much purchased CO2 passes through the plant. The purity of the carbon source decides its price. It also decides the treatment needed before synthesis.
The 2026 review frames the surrounding conditions. Global demand passed 100 Mt in 2025. Moreover, low-emissions production grew 20 percent in 2025 to almost 1 Mt. The announced pipeline has shrunk to 27 Mt by 2030. Committed and high-potential output for 2030 fell from 10 Mt. Output now stands just above 6 Mt over the same period, as of 2026. In addition, the barriers it lists are high costs, uncertain demand, complex regulation and missing infrastructure. Also, its infrastructure recommendation points at industrial and port clusters where production and users sit together. I tie the two input decisions to how EU compliance rules finally count the molecule.
What this means for you: negotiate both inputs against the same load factor assumption. A power contract may imply one duty cycle. A carbon contract may assume another. The two will not survive a single model review together.
What I will not accept as a secured input
Four exclusions, and I apply all of them before I let a line into the model.
A letter of intent for CO2 is not a supply contract. The price moves with concentration. For example, a near-pure fermentation stream costs 20 to 30 USD per tonne. Flue gas at 10 to 20 volume percent costs 60 to 80 USD per tonne.
In fact, a handful of cheap hours is not a load factor. Consequently, below 40 percent the levelised cost climbs steeply. Also, the worked example answers with a 40 to 50 percent solar share and storage rather than with opportunistic buying.
A headline electrolyser price is not an installed price. The stack is only 15 to 20 percent of the installed investment, 2025. In fact, the balance of plant, construction and integration carry more of the saving.
An announced offtake is not demand. Firm agreements across 2021 to 2025 reached 1.6 Mtpa, out of 7 Mtpa announced globally. Cumulative firm offtake stands under 2 Mtpa. That is 5 percent of what announced projects could produce by 2030.
What this means for you: I would rather lose a month defending these four exclusions. I would rather not explain them to a credit committee after issuing the term sheet.
What this changes for a Southeast Asian project
You can site the two inputs together or apart. The choice shows up in the fuel rather than in the slide. A plant on grid power with purchased carbon carries one set of load factors. By contrast, a plant on its own renewables with captured carbon carries another. The two also carry different carbon costs and different treatment trains.
On the technology side the answer is operational rather than rhetorical. For example, hybrid supply, battery storage and stack level cycling all matter. The technology choice follows the local energy profile, as published in February 2026. On the geography side, concentrate infrastructure where production and users meet. Industrial and port clusters are the natural place for it. 22 Mt of announced production risks losing its 2030 slot. That needs an investment decision by early 2027, as published in 2026.
For the fuel itself, the ambition studied is a 10 percent share of e-fuels in aviation and shipping by 2030. Analysts published that ambition in December 2023. That is where the outlet shows up. I set that outlet out on the sustainable aviation fuel page.
What this means for you: decide the siting question before you draft either contract. In this region the same two inputs produce two different files. It depends on whether the power and the carbon travel to the plant. They may instead sit beside it.
The four lines I would put in front of a lender
Line one, the power: 25 to 35 USD per gigajoule at 50 USD per MWh. The levelised cost rises once load factor drops below 40 percent, dated December 2023.
The carbon is line two: 20 to 30 USD per tonne from fermentation. Flue gas costs 60 to 80 USD per tonne. Direct air capture costs 400 to 670 USD per tonne, dated December 2023.
Line three, the equipment: the stack is only 15 to 20 percent of installed investment. Efficiency runs 51 to 56 against 53 to 56 kWh per kilogram. Stack life runs 60,000 to 90,000 against 40,000 to 60,000 hours, dated February 2026.
Line four, the commitment: 1.6 Mtpa firm out of 7 Mtpa announced. Cumulative firm offtake stays under 2 Mtpa. That is 5 percent of announced production for 2030, dated 2025.
What this means for you: put these four lines on one page, each with its date. Let the model argue underneath them. A lender reads the dated lines first and the spreadsheet second.
Sources
- IEA, The Role of E-fuels in Decarbonising Transport https://iea.blob.core.windows.net/assets/9e0c82d4-06d2-496b-9542-f184ba803645/TheRoleofE-fuelsinDecarbonisingTransport.pdf, December 2023.
- World Bank, ESMAP, Electrolyzers for Hydrogen Production: Technical and Economic Characteristics https://documents1.worldbank.org/curated/en/099022326123011297/pdf/P506220-b45b0865-8706-4862-8792-d8cc71f84569.pdf, February 2026.
- IRENA, Green hydrogen cost reduction: Scaling up electrolysers to meet the 1.5 C climate goal https://www.irena.org/-/media/Files/IRENA/Agency/Publication/2020/Dec/IRENA_Green_hydrogen_cost_2020.pdf, 2020.
- IEA, Global Hydrogen Review 2026, Executive summary https://www.iea.org/reports/global-hydrogen-review-2026/executive-summary, 2026.
- IEA, Global Hydrogen Review 2025, Five key questions about hydrogen https://www.iea.org/reports/global-hydrogen-review-2025/five-key-questions-about-hydrogen, 2025.
Frequently asked questions
Which input decides the cost of an e-fuel?
Electricity, on the modelled ranges. At 50 USD per MWh the power price contributes 25 to 35 USD per gigajoule of fuel before any investment or consumable, and operating cost beyond electricity runs at 1.5 percent of capital for electrolysis and 3 percent for synthesis each year, as published in December 2023.
What is the cheapest source of CO2?
Fermentation, where the stream is nearly 100 percent pure and capture costs around 20 to 30 USD per tonne, against 60 to 80 USD per tonne for flue gas at 10 to 20 volume percent and 400 to 670 USD per tonne from direct air capture, as published in December 2023.
Why does the load factor matter so much?
Because the investment is spread over the fuel actually made. With a constant average price the levelised cost starts increasing very quickly once the load factor drops below 40 percent, which is why the worked example mixes 40 to 50 percent solar with storage and cuts curtailment to 6 percent.
How much of the investment is the electrolyser stack?
15 to 20 percent of the installed investment, which is why balance of plant, construction, system integration, warranty terms and the supplier’s record carry more of the financing case than the stack specification, as of 2025.
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If you are at pre-FID structuring and need these two contracts read together rather than separately, I offer contracting and risk management support for exactly that pass, and I keep it to the two inputs and the model they sit in.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.