Home » Hydrogen Bankability Scorecard: How Lenders Grade a Project
Hydrogen Bankability Scorecard: How Lenders Grade a Project
10 min read · Jan 2, 2026 · By Alex
Lenders grade a hydrogen project on revenue certainty first: the published risk ranking puts off-take and demand risk at the top of the constraints on debt financing, then political and regulatory uncertainty, while technology and environmental questions are handled earlier, in the equity funded development phase. That ordering is what a credit committee applies before it commits to lend. I have turned it into a scoring sheet, and this article is the hydrogen bankability scorecard I grade a pre-FID dossier with, line by line, in the order a lender reads them. It follows on from how to finance a hydrogen project and answers one question: what in your file can the debt actually be sized against, and which line below will stop it?
I order the scorecard the way the file is read: five scoring lines, from revenue certainty to the public layer, each one answered against a single test. I write a score for each line, and I never let a strong line average away a weak one.
In short
- Revenue certainty: the volume under a firm contract, and for how long, is the first thing I count (2025).
- Contract terms: tenor of 10 to 15 years against take-or-pay of 60 to 80 percent (August 2025).
- Buyer credit: only 10 percent of announced projects have identified a buyer, and only 13 percent of contracted volume is binding (2024).
- Capital stack: 9 percent of announced projects have secured committed investment, against 0.5 percent in emerging economies (2025).
- Public layer: support instruments close a cost gap, they do not replace a buyer (December 2024).
In this article
What a lender actually grades
The Oxford Institute for Energy Studies review of January 2026 defines bankability as the degree to which a project is judged creditworthy and investable by financiers and lenders, resting on the project’s own cash flows under limited or non-recourse project finance, where lenders are repaid from project revenue rather than from the sponsors behind it. Its ranking puts off-take and market risk, the risk sitting in the contract under which a buyer commits to take the plant’s output, at the top of the constraints on debt financing, then political and regulatory uncertainty, while technology and environmental questions are handled during the equity funded development phase. Only around 13 percent of contracted volumes are supported by fully binding offtake agreements (January 2026), so relatively few projects today meet the revenue-certainty conditions required for classic project finance, and investment grade off-takers, meaning a credit rating of BBB- or higher, or substantial credit enhancements appear consistently in the projects that get financed (January 2026).
What this means for you: I score the revenue lines before I look at anything else, because a file that fails them cannot be rescued by good technology, a strong sponsor or a large order book.
Line one: revenue certainty
The first number on my sheet is how much of nameplate volume sits under a firm contract, and for how long. The gap is wide: firm purchase agreements cumulate to less than 2 Mtpa, only 5 percent of the production potential announced for 2030 (2025). In the region I work in most, only 6 percent of announced regional capacity has reached FID, while announced regional projects equal 12 percent of current regional demand (December 2025). I keep announced capacity, contracted capacity and firm capacity in separate columns, because only the last one pays debt. The buyer is a counterparty, an entity that signs the contract and is legally bound by it, and I record whether it must take the volume regardless. This is where a project finance structure for Southeast Asia usually breaks first.
What this means for you: write down the firm share of your nameplate volume before you model anything, then test whether the contract runs longer than the debt it is meant to repay.
Line two: the contract terms
The Oxford Institute for Energy Studies study of August 2025 reports hydrogen sale and purchase agreements typically running 10 to 15 years, about half the duration of first-generation international gas and LNG contracts, with volume provisions expected to prioritise take-or-pay, the duty on the buyer to pay for an agreed quantity whether or not it is collected, at 60 to 80 percent against above 90 percent in gas and LNG, in the absence of any transparent market price for clean hydrogen. Some European projects reached FID with contracts of 5 to 7 years, which required an equity contribution of around 50 percent to compensate for the shorter revenue certainty (2026). I score the tenor against the debt tenor, the take-or-pay level, and who carries the price review when the market moves. The way development lenders step into a structure depends on each of them.
What this means for you: a tenor shorter than the debt, or a take-or-pay below what your model assumes, moves the risk straight back onto your equity.
Line three: the buyer's credit
A contract is worth what its signature is worth. The Green Hydrogen Organisation paper of 2024 records that only 10 percent of announced projects have identified a buyer, and that of the contracted volume only 13 percent is contractually binding, 7 percent is pre-contractual and 80 percent is left as memorandums or unspecified. It adds that financiers require long-term, fixed priced offtake arrangements with creditworthy offtakers, and that without an investment grade rating of BBB- or higher the parties may need letters of credit, bank guarantees, parent company guarantees or retention monies. I score the rating of the buyer and the credit support standing behind it, and I read the plant economics underneath to see what the contract is actually securing.
What this means for you: if the buyer is not investment grade, the missing support is a cost and a condition precedent, not a detail to be settled after financial close.
Line four: the capital stack
The capital structure tells me how much of the risk the sponsors carry themselves. 9 percent of announced projects worldwide have secured committed investment against 0.5 percent in emerging economies (2025), and the cost of capital can reach 15 percent in emerging economies, three times the level in advanced economies (2025). The electrolyser stack is only 15 to 20 percent of the installed investment (2025), so an equipment quote tells you little about the installed total. I score how much of the stack is committed rather than announced, and which tranche absorbs the first loss, meaning the layer that is written down before any senior lender takes a hit. The anatomy of a capital stack built at scale is the reference I compare against.
What this means for you: count committed money only, then ask which layer takes the first loss, because an announced tranche cannot support a drawdown.
Line five: the public layer
The H2Global Foundation report of December 2024 evaluates four support instruments: capital expenditure support, a fixed premium, a contract for difference, which pays the producer the gap between an agreed reference price and the market price, and anchor capacity bookings. Its donor survey ranks market risks, political and regulatory risks and permitting and compliance risks as the most critical barriers to hydrogen infrastructure development. The report puts the investment needed to align the hydrogen economy with net zero at 1 000 billion USD worldwide by 2030, of which 335 billion USD has yet to be allocated, infrastructure being the largest part of the gap at 190 billion USD. Blended finance, subordinated tranches and guarantees absorb the first losses and lower the overall cost of capital, but they do not remove the underlying market or off-take risk (January 2026).
What this means for you: I treat the public layer as a bridge over a cost gap, never as the answer to a missing buyer or an unstable policy.
What this means for a Southeast Asian developer
The IEA briefing of 9 December 2025 records 4 Mt of regional demand in 2024, ammonia taking 49 percent against refining at 31 percent and methanol at 20 percent, announced regional projects equal to 12 percent of current demand and only 6 percent of announced capacity at FID. No certification scheme is in place, work runs in three countries, and a high cost of capital is named as the first regional barrier (December 2025); a guarantee of origin is the certificate that records how and where the hydrogen was produced. On the same page of that briefing, 7 Mtpa of offtake was announced between 2021 and 2025 against only 1.6 Mtpa that is firm, while close to 11 Mtpa of potential sits below 6 USD/kg by 2030, mostly in Indonesia (December 2025). For what that means for money on the ground, see the investment case for Southeast Asia.
What this means for you: in this region I score firm volume and certification readiness before I score the price, because both are still being built.
How I run the scorecard
The numbers I keep in front of me are the debt service coverage ratio, project cash available divided by the debt payments due; the loan-to-value ratio, debt divided by the value of the assets; and the merchant exposure, the share of volume sold at market prices with no contract behind it. The IEA page of five key questions, from 2025, closes the sheet: firm purchase agreements cumulate to less than 2 Mtpa, committed investment is secured by 9 percent of announced projects worldwide against 0.5 percent in emerging economies, and the cost of capital can reach 15 percent in emerging economies. I weight revenue certainty and the buyer’s credit above everything else, because a weak revenue line cannot be offset by a strong capital stack. When one line fails I do not average the scorecard, I mark the file as not yet financeable and name the single fix that would move it. The public layer can close a gap, but it never rescues a missing buyer.
What this means for you: bring me the firm volume, the buyer’s rating and the committed tranche, and I can tell you in one pass whether the file is ready for a lender.
Sources
- Oxford Institute for Energy Studies, Bankability of Hydrogen Projects: Key Risks, Financing Challenges and Mitigation Solutions https://www.oxfordenergy.org/wpcms/wp-content/uploads/2026/01/ET52-Bankability-of-Hydrogen-Projects.pdf, January 2026.
- Oxford Institute for Energy Studies, Hydrogen Offtake Agreements https://www.oxfordenergy.org/wpcms/wp-content/uploads/2025/08/ET50-Hydrogen-Offtake-Agreements.pdf, August 2025.
- Green Hydrogen Organisation, Key considerations for green hydrogen offtake agreements https://gh2.org/sites/default/files/2024-05/GH2_Considerations%20for%20Hydrogen%20Offtake%20Agreements_2024.pdf, 2024.
- H2Global Foundation, Bridging the gap: Mobilizing investments in hydrogen infrastructure https://h2-global.org/wp-content/uploads/2025/06/h2global-report-wg-1-bridging-the-gap-mobilizing-investments-in-hydrogen-infrastructure-v12-high-res.pdf, December 2024.
- IEA, Global Hydrogen Review 2025, Southeast Asia, 9 December 2025 https://iea.blob.core.windows.net/assets/745a259b-9cb7-4e1d-9ba1-a8b63d1eaae8/GHR2025_SEA_Webinar.pdf, 2025.
- IEA, Global Hydrogen Review 2025, Five key questions about hydrogen https://www.iea.org/reports/global-hydrogen-review-2025/five-key-questions-about-hydrogen, 2025.
Frequently asked questions
What does bankability mean for a hydrogen project?
It means the debt can be sized against the project’s own cash flows rather than against sponsor guarantees, in limited or non-recourse project finance (January 2026). I read it as a judgement about whether the revenue will be predictable enough to repay the loan on its own, and whether the contract structure and the risk allocation behind it will still hold if policy moves.
What is a good take-or-pay level?
No level is published as a rule: hydrogen contracts are expected to settle at 60 to 80 percent against above 90 percent in gas and LNG, and the tenor typically runs 10 to 15 years (August 2025). What I check is the level against the repayment profile, because a take-or-pay that sits below what the model assumes pushes the uncovered volume onto the merchant side.
Who grades a hydrogen project?
Lenders, who read off-take and market risk first and political and regulatory uncertainty second, while technology and environmental questions are handled earlier in the equity funded development phase (January 2026). The sponsor reads the same file for a different purpose, and a scoring sheet only becomes useful when both readings agree on which line is the weak one.
What makes a project fail the scorecard?
A weak buyer and a short contract: only 13 percent of contracted volume is contractually binding, 7 percent sits in pre-contractual agreements and 80 percent remains memorandums or unspecified (2024), and only 9 percent of announced projects have secured committed investment (2025). A file also fails when the contract runs shorter than the debt, or when the committed layer cannot cover the first drawdown.
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If you want a second reading of your dossier before it goes to a credit committee, I offer a technical review that scores the five lines and returns the single fix that would move the file. It takes one pass over the contracts, the capital stack and the public layer.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.