Home » Power Supply Risk in Hydrogen Projects: What Happens When the Electricity Is Not There
Power Supply Risk in Hydrogen Projects: What Happens When the Electricity Is Not There
10 min read · Feb 2, 2026 · By Alex
When a lender opens a hydrogen file. For example, The first thing I want settled is whether the electricity will be there for as long as the debt runs. Consequently, That is where most projects lose their financing, long before anyone argues about the equipment. Instead, Power supply risk in a hydrogen project is the risk that the electricity is not there when the plant needs it, or is there only at a price the model did not assume, and a lender tests it through hours contracted rather than hours available, curtailment treatment and the origin rules the fuel must still meet when the contract starts. By contrast, The question sits inside hydrogen, power-to-liquid and e-fuels, where the electricity contract decides whether the fuel can be sold, certified and financed at all.
Hydrogen power supply risk: five lines
I order this piece along five lines: the rules that decide whether the power counts, what the power price does to the plant, what the equipment has to tolerate, what the cost curve does with it, and the lines I write for a lender.
In short
- Rules: Three conditions decide whether the electricity behind the fuel counts at all, and the matching period tightens over time (2024).
- Price: At 50 USD per MWh the power alone adds 25 to 35 USD per gigajoule of fuel before any capital is spent (2023).
- Equipment: Minimum load, stack durability and module cycling decide how much of a cheap hour a plant can use (2026).
- Cost curve: The pathway assumes cheaper electrolysers, cheaper power and more full load hours, and none of that is contracted for you (2020).
- Lender: Contracted hours rather than available hours, a written curtailment treatment and the certification test at delivery are the three lines I write first.
In this article
What power supply risk means in a hydrogen project
Electricity is the most significant operating cost of an electrolyser and its price is highly site dependent (2026). Furthermore, The levelised cost of the fuel climbs quickly once the electrolyser load factor, meaning the share of the year the plant runs, drops below 40 percent (2023). Furthermore, The vocabulary I use from here is plain: a power purchase agreement buys the plant its electricity under contract; curtailment is power the plant is told or allowed not to take; hybrid supply mixes grid power with the project’s own renewable generation; firm capacity is power guaranteed when called; temporal correlation puts production and generation in the same period; availability is the share of time the equipment is ready; a stack is the block of cells that splits the water; a final investment decision is where the sponsor commits the money and the lenders close.
What this means for you: I turn every power offer into three lines before anyone sees it. Also, The hours contracted, the price at those hours, and the certification result the fuel must still produce at first delivery.
The rules that decide whether the power counts
The origin rules for renewable hydrogen decide whether a kilowatt hour counts at all. Therefore, The Green Hydrogen Organisation paper on offtake of 2024 sets three conditions on the electricity behind renewable hydrogen. Therefore, Additionality, geographic correlation and temporal correlation, which means that production has to fall in the same period as the generation contracted to feed it. Also, Until 31 December 2029 production must take place in the same calendar month as that contracted generation, and in the same hour from 1 January 2030. Consequently, The United States applies annual matching until 2027 and hourly matching from 2028. However, The same 2024 paper records national intensity thresholds: 20 gCO2e per megajoule in the United Kingdom standard version 3 of December 2023, and under 2 kg of CO2 per kg of hydrogen measured over 12 months in the Indian standards of August 2023.
A contract written for one regime and sold into the other fails at the gate.
What this means for you: I ask for the matching calendar, the metering arrangement and the certification route in writing before I accept a headline price, because an hour that cannot be counted is not a cheap hour.
What the power price does to the plant
The report The Role of E-fuels in Decarbonising Transport of December 2023 puts numbers on the exposure. In fact, At 50 USD per MWh, the electricity price already contributes 25 to 35 USD per gigajoule of fuel, before any investment or consumable. The annual hours available set the load factor and therefore the weight of the investment in the levelised cost. For example, In its worked example, production cost is minimised at a 40 to 50 percent solar share in the capacity mix, with annual curtailment of 6 percent against 18 percent on solar alone and 23 percent on wind alone.
The same modelling pairs 30 and 50 USD per MWh with 800 and 2 000 USD per kilowatt of electrolyser, a 5 percent cost of capital over 25 years, and operating cost beyond electricity at 1.5 percent a year for electrolysis and 3 percent a year for synthesis. For example, Carbon dioxide adds a layer of its own: 20 to 30 USD per tonne from high concentration sources, 60 to 80 from biomass flue gas and 400 to 670 from direct air capture. Moreover, The technology choices behind a Southeast Asian plant follow from this shape.
What this means for you: I price the power hour by hour and let the plant tell me what it can afford to run, rather than assume an average that no month will deliver.
What the equipment has to tolerate
The power-to-liquid chain asks an electrolyser to follow a supply that moves. However, The World Bank electrolyser survey of February 2026 starts from electricity as the most significant operating cost. Also, a highly site dependent one, so selection follows the local energy profile. For example, Operational flexibility lets the plant take low cost power, developers use hybrid designs and battery storage. Also, a grid connected project on power purchase agreements chooses differently from a project running its own renewable assets. For example, The largest capital cost reductions sit in process balance, construction and system integration, not in the stack. Also, Selection criteria are electrical efficiency and operational flexibility, degradation and stack replacement, technological maturity and bankability, and equipment reliability. By contrast, Efficiency runs 51 to 56 kWh per kg for alkaline, 53 to 56 for PEM, 35 to 42 for SOEC.
Stack durability runs 60 000 to 90 000 hours for alkaline against 40 000 to 60 000 for PEM, and PEM replacements reach 15 percent of total system cost. Specifically, Minimum load runs 10 percent for modern atmospheric alkaline, 30 percent for pressurised alkaline, 10 percent for PEM, 50 percent for SOEC, 5 percent for AEM. Specifically, Modules run 5 MW to 100 MW, and multi-unit stack cycling lets a project stop or modulate units as electricity availability and maintenance allow.
What this means for you: I match the technology to the shape of the supply before I match it to a brochure, because a plant that cannot turn down is a plant that must be paid for idle hours.
What I treat as firm and what I treat as available
A price quoted for a few good periods is not a contract for the year, and I keep the two apart on my page. Specifically, Hours that are cheap for a handful of periods are not the hours committed for the whole tenor of the debt. Also, only the second kind carries a fixed charge. For example, Even the mix that minimises production cost in the 2023 worked example still loses 6 percent of annual generation to curtailment, where solar alone loses 18 percent and wind alone 23 percent. Consequently, A unit that can modulate down to 10 percent of its nominal load in 2026 gives the plant a floor, not a production profile. A stack replaced once performance has fallen by more than 10 percent in 2026 is a scheduled maintenance event the cash flow has to carry.
What this means for you: I ask for one table showing hours committed by month, price at those hours, curtailment assumed and the reserve that pays for stack replacement. Therefore, the lender can see the gap between an average and an obligation.
What the cost curve does with the power price
Cost curves do not remove the power risk, they move it. The plant economics I model follow the IRENA cost study of 2020, which puts electricity at a large share of green hydrogen production cost with the electrolyser as the second largest cost item and expects falling renewable power prices to narrow the gap. Its pathway runs to an electrolyser 80 percent cheaper, 3 200 to 4 200 full load hours a year, a life of 10 to 20 years, a cost of capital from 10 percent to 6 percent, electricity from 53 to 20 USD per MWh and efficiency from 65 to 76 percent on a lower heating value basis.
The same 2020 study gives alkaline the lowest installation cost, with 50 to 78 kWh per kg and a charge range of 15 to 100 percent, puts green hydrogen at two to three times the cost of blue hydrogen on average, and sees cost cuts of 40 percent in the short term and up to 80 percent in the long term, with production below 2 USD per kilogram possible within the decade.
What this means for you: I treat every assumption in that curve as a variable the lender will reprice. Also, i ask what happens to the debt if the power price never reaches the level the model assumes.
What I put in front of the lender
The contracting work I do starts where market data stops. The IEA’s five key questions page of the Global Hydrogen Review 2025 puts firm purchase agreements at less than 2 Mtpa cumulated, only 5 percent of the potential output announced for 2030. The same 2025 page has cost of capital reaching 15 percent in emerging economies, three times the level of advanced economies, with only 9 percent of announced projects worldwide having secured committed investment against 0.5 percent in emerging economies. It puts the stack at 15 to 20 percent of installed investment, so most of the money sits in process balance, works, grid connection and indirect costs. On scale it traces a path from a 30 MW unit in 2021 to a 500 MW unit in China in 2025 and 2 GW targeted in the Gulf by 2027, a 75 times increase in six years.
What this means for you: I use that page to set expectations early, since the power contract, not the equipment brochure, is what closes the distance between an announced project and a financed one.
The four lines I write in front of a lender
I write four lines and nothing else on the first page. One: the hours, written as contracted volume and matching obligation, never as an annual average. Two: the curtailment treatment, with the blended case that minimises cost losing 6 percent of annual generation against 18 percent and 23 percent for the single-source cases (2023). Three: the minimum load and the cycling arrangement that lets units stop when power is short (2026). Four: the certification test the fuel must still pass when deliveries start, month by month and then hour by hour as the rules tighten.
What this means for you: the rule I extract for a developer is to buy hours rather than averages and to price the certification test into the same contract that prices the power. I would model a smaller plant that runs on written hours than a larger one that runs on a favourable average.
Sources
- Green Hydrogen Organisation, Key considerations for green hydrogen offtake agreements, 2024 https://gh2.org/sites/default/files/2024-05/GH2_Considerations%20for%20Hydrogen%20Offtake%20Agreements_2024.pdf, 2024.
- IEA, The Role of E-fuels in Decarbonising Transport, December 2023 https://iea.blob.core.windows.net/assets/9e0c82d4-06d2-496b-9542-f184ba803645/TheRoleofE-fuelsinDecarbonisingTransport.pdf, 2023.
- World Bank, ESMAP, Electrolyzers for Hydrogen Production, February 2026 https://documents1.worldbank.org/curated/en/099022326123011297/pdf/P506220-b45b0865-8706-4862-8792-d8cc71f84569.pdf, 2026.
- IRENA, Green hydrogen cost reduction: Scaling up electrolysers to meet the 1.5 C climate goal, 2020 https://www.irena.org/-/media/Files/IRENA/Agency/Publication/2020/Dec/IRENA_Green_hydrogen_cost_2020.pdf, 2020.
- IEA, Global Hydrogen Review 2025, Five key questions about hydrogen https://www.iea.org/reports/global-hydrogen-review-2025/five-key-questions-about-hydrogen, 2025.
Frequently asked questions
What is power supply risk in a hydrogen project?
It is the risk that the electricity is missing when the plant needs it, or arrives only at a price the model did not assume, which shows up as lost production, a higher levelised cost or a fuel that fails its origin test. It is what separates a good average price from a bad year of production, and it appears in the file long before anyone compares equipment quotes.
Why does the load factor decide the financing?
Because the levelised cost climbs very quickly once the electrolyser load factor drops below 40 percent (2023), and electricity is the most significant operating cost, highly site dependent (2026), so a few cheap hours do not pay for the investment. The fixed side of the plant is paid for by hours that actually run, not by hours that could have run.
What do matching rules require from my power contract?
Renewable hydrogen must meet additionality, geographic correlation and temporal correlation: production in the same calendar month as the contracted generation until 31 December 2029 and in the same hour from 1 January 2030, with annual matching in the United States until 2027 and hourly from 2028 (2024). Your contract therefore has to show when the power was generated as well as what it cost.
What proof do lenders want about electricity?
Contracted hours rather than available hours, a written curtailment treatment, a minimum load and cycling arrangement, and evidence that the supply satisfies the certification rules of the market the fuel is sold into. I assemble those four items into one dated schedule, because that is the document a lender reads first.
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If you want the power side written the way a lender reads it, I provide contracting and risk management support for hydrogen and power-to-liquid projects, covering contracted hours, curtailment treatment, minimum load and the certification route from first delivery. I work with developers, buyers and their banks on the same document.
Consequently, I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.