We Connect Asia

Hydrogen

Water Supply for PtL and Hydrogen Plants: The Siting Risk Nobody Models

10 min read  ·  Oct 10, 2025  ·  By Alex

ptl water supply

Three different pipes feed a hydrogen plant, and only one of them is chemistry. Water enters as a feedstock, meaning the input the reaction consumes. It also enters as a cooling medium, the fluid that carries heat away from the reaction. The third entry is the permit condition, the limit the local authority puts on your abstraction. For a water supply hydrogen plant, the volume the stoichiometry burns is not what decides the site. In fact, the cooling design decides it. In addition, local competition for the resource adds on top of it. Siting settles that, not commissioning. I am writing this inside the power-to-liquid branch, where power-to-liquid means liquid fuel made from hydrogen and captured carbon dioxide, and I start from the plant rather than from the process diagram.

What this article covers

Here I walk through the three places water enters the plant, and what each one costs. Then come the two questions I ask before I shortlist a site. I keep modelled volumes, cooling throughput and permit limits apart. The market quotes them as if they were one number.

In short

  • Feedstock: In 2023, around 10 litres of water produce 1 kg of hydrogen through electrolysis, and the machines need water stripped of ions.
  • Cooling: In 2023, heat rejected by evaporation nets 30 to 80 litres per kg of hydrogen. A circuit that returns the water needs 1 500 to 3 000 litres.
  • Fuel: In 2016, a litre of jet fuel needed 1.3 to 1.4 litres of water. A 100 kt plant also needs 170 000 cubic metres a year.
  • Region: In 2023, the best solar sites are often arid, because agriculture and drinking water have already claimed the groundwater.
  • Timing: In 2026, investors judge hub viability on whether water comes from freshwater or seawater. The question therefore belongs in the shortlist.
Facebook
Twitter
LinkedIn

In this article

The three places water enters the plant

The reaction consumes feedstock water, and it never comes back. Cooling water carries heat away from the electrolyser, the machine that splits water into hydrogen and oxygen using electricity. In addition, the permit is the local authority’s view of both volumes plus every other user on the same aquifer. Three failure modes, decided at three different desks.

For example, a 2016 study documents the setting any siting decision inherits. Agriculture consumes about 70% of worldwide water demand, industry and thermal plant cooling some 20%, and drinking water some 10%. Also in 2016, more than 97% of the global water balance is salt water. In addition, less than 3% is fresh water. Therefore, the fresh share a plant can draw is small before any neighbour has asked.

What this means for you: I therefore size the cooling case first. That line moves with the climate and the permit, while the feedstock line stays where the reaction put it.

What the feedstock actually takes

The Role of E-fuels in Decarbonising Transport puts the 2023 requirement at around 10 litres of water per kg of hydrogen. That is the feedstock figure for electrolysis. The same 2023 work states that electrolysers require ultrapure water, meaning water stripped of ions by additional deionisation. Cooling water does not need to be as pure, but evaporative systems must treat it to limit corrosion and fouling.

Also, the chemistry sets the floor. As a result, net water demand for power-to-liquid production follows from the stoichiometry of the reaction. A 2016 figure puts it at 12 moles of water per mole of the average jet fuel molecule. Instead, everything above that floor is cleaning, losses and heat.

That is why I run the water check inside the early screening stage. A wrong aquifer assumption there costs a month rather than a licence.

What this means for you: ask for the feedstock figure as litres per kg and per GJ, dated and sourced. Therefore, treat anything larger as cooling or treatment wearing a chemistry label.

What the cooling design adds

The 2019 Future of Hydrogen gives 9 litres of water per kg of hydrogen, with 8 kg of oxygen as a by-product. Electrolysing today’s dedicated production of around 70 Mt would need 617 million cubic metres, about 1.3% of energy sector water consumption. Steam methane reforming of 52 Mt at around 7 litres of raw water per kg needs roughly twice that.

Air cooling consumes no water but needs a large heat exchanger surface, and it loses efficiency in hot arid climates. Evaporative cooling, heat rejected by evaporating water in a tower, nets 30 to 80 litres per kg of hydrogen. Moreover, it cannot return the water to its source. Once-through cooling, water drawn, warmed and discharged, needs 1 500 to 3 000 litres per kg. It warms the source by about 10 degrees Celsius.

Reverse osmosis desalination pushes seawater through membranes to remove salt. It takes 3 to 4 kWh per cubic metre and costs 0.7 to 2.5 USD per cubic metre. As a result, that adds only 0.01 to 0.02 USD per kg of hydrogen. Feeding seawater straight into the cell still causes corrosive damage and chlorine production (2019). The green hydrogen case rests on it.

What this means for you: I settle the cooling design before I settle the site. The same machine can sit anywhere between the evaporative figure and the once-through figure on that single choice.

What it means per litre of fuel

The German Environment Agency set out the net reaction for jet fuel in 2016. It needs 12 moles of water for one mole of the fuel molecule. That gives a theoretical 0.032 cubic metres per GJ and a real 0.038 to 0.040 cubic metres per GJ. Consequently, the figure is 1.3 to 1.4 litres of water per litre of jet fuel. That is what net water consumption means here: water taken from the basin and not returned. Also in 2016, a 100 kt power-to-liquid plant consumed a net 170 000 cubic metres of water a year. The same 2016 work finds that biofuels from agricultural and short rotation forestry feedstock need far more water. The factor runs from 400 to 15 000 times the water that power-to-liquid from wind and photovoltaic electricity needs.

Fully electrolytic ammonia and methanol in 2030 would need about 0.6 billion cubic metres a year of water as feedstock. That is around 1% of water consumption in the energy sector (2019).

What this means for you: I carry one water line per litre of finished fuel into the offtake discussion. The buyer’s sustainability claim depends on that line. In addition, the basin’s permit and the allocation amount to the same figure from two sides.

What the region does to the number

Less than half of global water consumption comes from rainwater. The largest part comes from lakes and underground reservoirs, so the plant joins a queue that already exists (2016). The sites with the best solar resources are often arid. There, agriculture and drinking water have likely claimed the surface and groundwater already (2023). Desalination cost has fallen to around 1 USD per cubic metre. A kilogram of hydrogen needs roughly 40 litres of water. Desalinated water therefore adds only about 0.04 USD per kg, a few percent of the cost (2023).

Cheap water is not available water: a site still needs a plant to make it, a grid to run it and a permit for what it does not use. I put carbon dioxide capture and storage in the same screening box, because both are geography before they are engineering.

What this means for you: I ask which users hold the rights in the driest month rather than who holds the largest annual allocation, because the annual figure hides the month that ends projects.

What a hub needs before it is a hub

Global Hydrogen Review 2026 states that access to enabling infrastructure shapes the viability of hydrogen hubs. That infrastructure includes electricity and gas grids, rail and roads, and water supply from freshwater or desalination. The same 2026 review puts the largest hydrogen projects in a region served by a single strait. Water is one of several dependencies a site has to carry.

Matching cheap renewable electricity, available water and affordable persistent carbon dioxide sources by location is a significant challenge (2019). Nothing in that sentence resolves itself after the buyer acquires the land.

I run those dependencies through the technical review checklist before any of them reaches a term sheet.

What this means for you: I list water beside grid connection, pipeline access and export route. Water is a site dependency, not a utility the team arranges after the design freezes.

What scale does to the water line

Batteries and hydrogen technology notes in 2020 that electrolysers split water into hydrogen and oxygen using electrical energy. It also calculates what a 5% blend by volume in all European Union natural gas use would do. Low-carbon hydrogen demand would rise by 2.5 Mt a year, and electrolysers would need almost 25 GW of capacity. A water plan has to target that order of magnitude.

An electrolyser plant producing 1 Mt of hydrogen a year consumes 40 to 90 million cubic metres of desalinated water. It needs a minimum desalination capacity of 110 000 cubic metres a day (2023). A level that is an average operating condition for large desalination plants in Kuwait, Israel and the Republic of Korea.

Water capacity is a line you either contract or discover, and I size it at the final investment decision stage rather than after it.

What this means for you: I check the water plan against the full contracted volume, not the first phase. You will operate in year five the desalination unit you build in year one.

The two questions I ask before a shortlist

I ask what the cooling design consumes in the driest month, not on an annual average. The permit applies to the dry month. I also ask who owns the water rights and the discharge permit for the life of the plant. A licence that lapses when the plant is ten years old is not a water plan.

Everything else follows from those two. Feedstock volumes are chemistry, desalination unit costs sit in public reports, and hub infrastructure is a checklist. Both answers should be documents rather than assurances, and both should exist before a developer needs them. The pair above is the only pair that can end a site on its own.

What this means for you: I would rather lose a site in the dry month calculation than in the permit hearing. I run both questions before the shortlist circulates, and I drop any candidate that cannot answer them in writing.

Sources

Frequently asked questions

Two different numbers get quoted as one. Feedstock consumption in 2019 and 2023 figures is around 9 to 10 litres per kg of hydrogen, while cooling water in a circuit that returns it is a throughput rather than a consumption. Ask for a water balance that separates the destroyed volume from the circulated volume.

In 2023 the money case closes easily, with desalination at around 1 USD per cubic metre and, at roughly 40 litres per kilogram of hydrogen, about 0.04 USD per kg added. The engineering case does not close: in 2019 feeding seawater straight into the cell currently causes corrosive damage and chlorine production, so the water still has to be treated before it reaches the stack.

In 2023 air cooling consumes no water but needs a large heat exchanger surface and loses efficiency in hot arid climates. Evaporative cooling nets 30 to 80 litres per kg of hydrogen and cannot return the water to its source, while once-through cooling needs 1 500 to 3 000 litres per kg and warms the source by about 10 degrees Celsius. The choice, not the chemistry, sets the bill.

Before the site is shortlisted, while alternatives still exist. In 2026 the viability of hydrogen hubs is judged partly on access to water supply from freshwater resources or through desalination, and in 2016 less than half of global water consumption is fed by rainwater, so the resource is already spoken for. A contract signed after the permit application is a negotiation you cannot walk away from.

Not sure your project would survive a credit conversation?

A short call is usually enough to see where your project stands.

If you are choosing a site and want the water balance, the cooling case and the permit assumptions tested against the sources before anything is committed, I offer technical review support on exactly that work, from the first shortlist through to the contract package.

I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia

I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.

More about me·Get in touch

Facebook
Twitter
LinkedIn

Related articles