We Connect Asia

Hydrogen

Alkaline vs PEM Electrolysers: Which One Will Lenders Accept?

10 min read  ·  Feb 2, 2026  ·  By Alex

electrolyser alkaline vs pem

There is no universally superior electrolyser, the water splitting machine at the centre of a hydrogen plant, and the choice between the two mature families depends on the end use and on the power supply. Those two sentences are the answer you need before a lender even opens the technology question. In the alkaline vs PEM electrolyser comparison, where PEM stands for proton exchange membrane, alkaline held 64 percent of installed capacity against 36 percent for PEM as of mid-2025 and holds 84 percent of what is under construction; the stack, the core module where the splitting happens, runs 60,000 to 90,000 hours for alkaline against 40,000 to 60,000 for PEM, and stack replacement in a PEM system can reach 15 percent of total system cost. I treat those figures as the baseline evidence you will find inside the green hydrogen production process.

I will compare four things: what the market has already bought, what the two technologies cost once installed, what happens to a stack over ten years, and what your power supply does to the choice. Each one changes how a lender reads the same file.

In short

  • Market split: alkaline holds 64 percent of installed capacity and 84 percent of the construction pipeline against 36 percent and 11 percent for PEM, as of mid-2025.
  • Installed cost: 500 to 1,500 USD/kW for alkaline against 1,000 to 2,000 for PEM as of February 2026, with the stack at only 15 to 20 percent of the installed investment.
  • Stack: 60,000 to 90,000 hours for alkaline against 40,000 to 60,000 for PEM, degrading 0.1 to 0.25 percent per 1,000 hours against 0.2 to 0.5.
  • Power supply: pressurised alkaline typically runs to 30 to 40 percent of rated load, modern atmospheric alkaline and PEM to 10 percent.
  • Lender’s test: warranty terms, service record and supplier depth decide more than the efficiency figure on the datasheet.
Facebook
Twitter
LinkedIn

In this article

What a lender checks before the technology question

I do not start with which technology is better. I start with whether the file reaches FID, the final investment decision, with a supplier that will still be answering when the first stack needs attention. Bankability is my word for that state: the point at which a lender accepts your technology choice instead of discounting it.

The vocabulary I use in that conversation is short. An electrolyser splits water into hydrogen and oxygen using electricity, and the stack is the core module where the splitting happens, cell stacked on cell. Alkaline uses a liquid alkaline electrolyte, while PEM uses a solid polymer membrane, which is why it is compact and why it leans on platinum group metals. The balance of plant is everything around the stack: piping, cooling, purification, power electronics and interconnection. Degradation is the slow loss of performance that ends in a stack replacement. A warranty is the supplier’s written commitment on performance, degradation and spare parts, and an offtake is the contract that sells the hydrogen.

What this means for you: defend the technology on power profile, installed cost and service coverage, because those three settle the file long before anyone argues about efficiency.

What the market has already chosen

The World Bank survey of February 2026, built on interviews with more than 50 suppliers and developers, puts 2.15 GW of electrolyser capacity in operation worldwide as of mid-2025, enough for 0.2 percent of global hydrogen consumption, with 16 GW under construction and 3.5 GW having reached FID. China holds 56 percent of that operating fleet and Europe 20 percent.

The technology split is what your lender quotes back to you: 64 percent alkaline against 36 percent PEM as of mid-2025, and in the construction pipeline 84 percent alkaline, 11 percent PEM, 5 percent solid oxide and anion exchange membrane combined. Manufacturing capacity runs 61 GW a year, of which 43 GW is alkaline and 13 GW is PEM. Plants run below utilisation, and restructurings, bankruptcies and mergers have followed among suppliers.

That buyer’s market is where a lender finds competing bids, warranties with spares behind them and a service network that already exists. I read how the choice looks for a project in Southeast Asia before I fix anything.

What this means for you: record how many qualified suppliers can serve your chosen stack before you commit, because that count is what turns a preference into a negotiable package.

What the two technologies cost once installed

An installed alkaline system runs 500 to 1,500 USD/kW against 1,000 to 2,000 for PEM as of February 2026, while solid oxide sits above 3,000 and anion exchange membrane above 3,500. Annual non-electricity operating cost runs 2 to 3 percent of installed capital for alkaline against 3.5 to 5 percent for PEM, before the electricity bill that dominates both.

The headline price hides the structure underneath it. Direct capital expenditure on the stack, the stack balance and the process balance carries the same weight as indirect spend on engineering, procurement, construction and installation, and the largest savings sit in balance of plant, construction and system integration rather than in the stack, which is only 15 to 20 percent of the installed investment. The best projects today make hydrogen at around 3 USD per kilogram, and most sit above that.

I turn those ranges into a figure a lender can underwrite on the plant economics that carry capital expenditure into cost of production.

What this means for you: budget the plant, not the stack, because most of your installed cost sits outside the module a supplier quotes first.

What happens to the stack over ten years

Both families start at comparable efficiency, but PEM stacks degrade faster, and stack replacement in a PEM system can reach 15 percent of total system cost as of February 2026. A stack is replaced once performance has fallen by more than 10 percent. Durability runs 60,000 to 90,000 hours for alkaline against 40,000 to 60,000 for PEM, degradation runs 0.1 to 0.25 percent per 1,000 hours against 0.2 to 0.5, and electricity consumption runs 51 to 56 kWh per kilogram against 53 to 56 for PEM.

The IRENA comparison from 2020 gives alkaline a system efficiency of 50 to 78 kWh per kilogram, a 60,000 hour stack life and a stack cost of 270 USD per kilowatt from 1 MW. It also shows what PEM buys in space: a stack about 60 percent smaller, a facility footprint 20 to 24 percent smaller, 8 to 13 hectares for 1 GW of PEM against 10 to 17 hectares for alkaline.

I carry those hours into the 2026 cost case for Southeast Asia.

What this means for you: price the replacement, not just the purchase, and date every degradation figure you put in front of a lender.

What the power supply does to the choice

Pressurised alkaline, the configuration that dominates the market, typically runs down to 30 to 40 percent of rated load, while modern atmospheric alkaline and PEM both reach 10 percent as of February 2026. Solid oxide needs 50 percent of rated load and anion exchange membrane 5 percent, so the newer families are harder to match to a supply that swings. Projects on intermittent renewable power still favour alkaline on cost and availability, and some developers use hybrid alkaline and PEM configurations or battery storage to smooth supply.

Electricity is the largest operating cost line in the model, so the technology choice has to follow the local energy profile rather than the datasheet. Integrated modules typically run 5 MW to 100 MW, and utility-scale plants cycle stacks individually inside multi-unit arrangements, which a single unit cannot do. That flexibility earns its keep when cheap power arrives for a few hours and stops again.

I treat the asset as the thing that must survive your profile in the production plant design.

What this means for you: match the machine to the hours your power actually arrives, then check that the supplier’s service map covers those hours.

What I would not accept as evidence

Four traps. First, a supplier’s stack efficiency is not the plant efficiency your model will run, and the gap between the two is where budgets break. Second, a headline price that excludes balance of plant, interconnection and soft costs is not an installed price, which is why equipment quoted far below the published ranges is usually quoted that way. Third, a technology preference is not a financing commitment: less established technologies carry higher financing costs unless warranties, guarantees or other mitigants cover them, and financing requirements can push you toward proven suppliers and established contractors. Fourth, a manufacturing capacity is not supply: 61 GW of annual capacity stood against 2.15 GW operating as of mid-2025, and Chinese capacity of 20 GW a year met demand of about 2 GW in 2024.

I also treat the data itself with care. Real multi-year operating data at scale remain scarce and contradictory, and the 2026 review still lists high cost, uncertain demand and slow or complex regulation as the standing barriers to investment.

What this means for you: I only accept installed cost, degradation measured over years, and written warranty terms as evidence, and I ask every other figure for its date and its definition.

What this changes for a Southeast Asian project

The International Energy Agency’s 2025 review puts global installed electrolysis capacity at 2 GW in 2024, with more than 1 GW added by July 2025, and China at 65 percent of installed and FID capacity and close to 60 percent of manufacturing capacity. Installing a Chinese system outside China cost 2,000 to 2,600 USD/kW in 2024 against 600 to 1,200 inside China, more than half of the total going to engineering, procurement, construction and contingency, and 1,500 to 2,400 once transport and tariffs are added.

The five key questions section of that same review adds that China makes renewable hydrogen 40 to 45 percent cheaper than Europe or the United States and represents about one third of global hydrogen demand, and that the stack is only 15 to 20 percent of the installed investment. The scale comparison is blunt: NEOM targets 2 GW by 2027, against a largest project of 30 MW in 2021 and a 500 MW unit commissioned in China in 2025.

I put your project next to that scale in how a capital stack is assembled for a project of that size.

What this means for you: state your module size, your installation date and your supply chain location early, because your file is read against that scale.

The four lines I would put in front of a lender

  • Line one, the split: 64 percent alkaline against 36 percent PEM of installed capacity, and 84 percent of what is under construction, as of mid-2025.
  • Line two, the installed cost: 500 to 1,500 USD/kW for alkaline against 1,000 to 2,000 for PEM as of February 2026, with the stack at only 15 to 20 percent of the installed investment as of 2025.
  • Line three, the stack: 60,000 to 90,000 hours for alkaline against 40,000 to 60,000 for PEM, degradation 0.1 to 0.25 percent per 1,000 hours against 0.2 to 0.5, and a replacement exposure of 15 percent of total system cost in a PEM system, as of February 2026.
  • Line four, the power profile and the warranty: pressurised alkaline down to 30 to 40 percent of rated load against 10 percent for PEM, plus the supplier’s warranty terms and service record, which is where risk perception among financiers is settled, as of February 2026.

What this means for you: four dated lines, each one a claim your supplier can sign against, and together they answer the technology question in under a minute.

Sources

Frequently asked questions

Alkaline, on installed system ranges of 500 to 1,500 USD/kW against 1,000 to 2,000 for PEM as of February 2026, with annual non-electricity operating cost of 2 to 3 percent of installed capital for alkaline against 3.5 to 5 percent for PEM. Electricity remains the largest operating cost for both, so the gap moves with your power price rather than with the equipment price alone.

On paper yes, since PEM reaches 10 percent of rated load, and modern atmospheric alkaline also reaches 10 percent while pressurised alkaline, the configuration that dominates the market, typically runs down to 30 to 40 percent. In practice, large projects on intermittent renewable power still favour alkaline on cost and availability, and some developers use hybrid configurations or battery storage to smooth supply.

The degradation rate and the running hours. A stack is replaced once performance has fallen by more than 10 percent, with alkaline degrading 0.1 to 0.25 percent per 1,000 hours against 0.2 to 0.5 for PEM as of February 2026, and replacement in a PEM system can reach 15 percent of total system cost. Durability then sets the calendar: 60,000 to 90,000 hours for alkaline against 40,000 to 60,000 for PEM.

15 to 20 percent, which is why balance of plant, construction, system integration, warranty terms and the supplier’s track record decide more of the financing case than the stack specification. Direct and indirect capital expenditure carry equal weight, so a cheaper stack does not automatically produce a cheaper plant.

Not sure your project would survive a credit conversation?

A short call is usually enough to see where your project stands.

If you are weighing these figures against your own power profile and schedule, I offer technology maturity and scale-up support to pressure test the technology choice before it reaches due diligence, and I can walk the file line by line against the questions your lender will put to you.

I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.

Alex, Founder of WeConnect Asia

Alex, Founder of WeConnect Asia

I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.

More about me·Get in touch

Facebook
Twitter
LinkedIn

Related articles