Home » Green Ammonia Market and Offtake: What Is Actually Contracted
Green Ammonia Market and Offtake: What Is Actually Contracted
10 min read · Feb 2, 2026 · By Alex
A developer at pre-FID stage asks me one question before anything else: is there a real market behind the announced capacity? My answer is that the market is far larger in announcements than in contracts, since as of May 2025 more than 300 Mtpa of low-emission ammonia projects were announced against a conventional market of 200 Mtpa in 2025, while only 15 Mtpa had reached a final investment decision and 1.3 Mtpa was online as retrofits, and 90 percent of the ammonia actually traded moves on short-term contracts of one to three years. That asymmetry is the whole green ammonia market and offtake problem. I keep the parent page for this branch in the green ammonia guide, where green ammonia means ammonia made from electrolytic hydrogen produced with renewable power.
I will order this page in four moves: how big the announced market is, how the traded market really works, what a bankable offtake contains, and who is actually buying. Each move closes with the consequence for a file built before final investment decision.
In short
- Announced: As of May 2025, more than 300 Mtpa was announced, 35 Mtpa sat in front-end engineering design, 15 Mtpa held a final investment decision and 1.3 Mtpa was online as retrofits.
- Traded: 90 percent of traded ammonia moves on contracts of one to three years with fixed quantity and take-or-pay, priced off the monthly Tampa benchmark.
- Contract length: A producer may hold a 20-year fixed-price power contract while buyers rarely sign beyond a few years, and the price can be two to three times grey ammonia (2024).
- Buyers: Fertiliser and consumer goods firms with scope 3 targets, coal co-firing generators in Japan and South Korea, and shipping, still an order book for 2050.
- Lender test: About 42 percent of electrolyser projects under construction worldwide are ammonia, and the best projects today sit around 3 USD per kilogram (February 2026).
In this article
What the green ammonia market actually is
Here is the direct answer again, because the vocabulary decides how you read every figure that follows. Conventional ammonia is made from unabated fossil hydrogen, green ammonia uses electrolytic hydrogen split from water with renewable power, and low-emission ammonia covers renewable and low-carbon routes together. A retrofit changes an existing plant while a greenfield builds a new one. Front-end engineering design is the FEED stage, the engineering package completed before the final investment decision, the moment the board commits the money. The offtake agreement is the purchase contract that turns planned output into revenue. Take-or-pay makes the buyer pay for the contracted volume whether or not it lifts it. The Tampa benchmark is the monthly reference price for traded ammonia and it follows natural gas. Bankability is simply whether a lender will lend against that contract.
What this means for you: I put these definitions in the file before I quote a figure, because an announcement, a final investment decision and a signed contract are three different objects and a lender prices each one differently.
How big the announced market is
The roadmap from the Hydrogen Council and McKinsey & Company, dated November 2025, puts more than 300 Mtpa of announced low-emission ammonia projects as of May 2025, larger than the conventional market of 200 Mtpa in 2025. Inside that pile, 85 projects holding 35 Mtpa sit in front-end engineering design, 48 projects holding 15 Mtpa have reached a final investment decision, and 1.3 Mtpa is already online as retrofits of existing capacity. The same roadmap notes that more than half of all food grown relies on ammonia fertilisers made in more than 60 countries, that fertiliser production accounts for about 1 percent of global emissions, and that technologies exist to abate more than 80 percent of that footprint. A January 2024 tally sits beside it: 180 million tonnes of low-carbon ammonia plants buildable by 2035 against 187 million tonnes used each year, with 185 tracked projects of which 45 have offtake agreements and 15 are under construction or financed. The power supply behind the hydrogen sits one level down, on the green hydrogen page.
What this means for you: I record how much of that pile sits in FEED and how much has crossed final investment decision, because only the second number can ever stand as collateral.
How the traded market really works
The white paper from BloombergNEF and Climate Technology Coalition, dated January 2024, describes a 76 billion USD market of 187 million tonnes in 2021: 77 percent of ammonia demand goes to fertilisers and 23 percent to industrial uses, 54 percent of all fertilisers are made with ammonia, and production and use account for 2 percent of the world’s carbon dioxide emissions. Capacity is 243 million tonnes a year with China close to a third and utilisation around 80 percent; only 10 percent of supply trades internationally as it is, plus 16 percent as urea; production cost runs between 100 and 1,000 USD per tonne, averaging 305 USD per tonne since 2013, with the marginal producer, meaning the high-cost maker who sets the world price, normally in China. Then the part that governs my file: 90 percent of traded ammonia moves on short-term contracts of one to three years with fixed quantity and take-or-pay, priced off the monthly Tampa benchmark which follows natural gas, and five firms take up to 70 percent of traded volume out of about 820. That structure is exactly what offtake agreements are asked to improve on.
What this means for you: I can only claim a slice of that market with paper, because the traded book is short, concentrated and priced off a benchmark I do not control.
What a bankable green ammonia offtake looks like
A green ammonia developer may have to sign a 20-year fixed-price renewable power contract, so some bankers ask for a 20-year fixed-price offtake in return, while buyers used to gas-indexed pricing rarely sign beyond a few years and face a price that can be two to three times that of grey ammonia (2024). Pooled and aggregated demand reduces counterparty risk, creates bankable offtake volumes and helps producers move from front-end engineering design to final investment decision (2025). Tracking the claimed reduction needs two instruments: a guarantee of origin, which is a certificate stating how the delivered molecules were produced, and book-and-claim, where the environmental claim is transferred separately from the physical cargo. Three barriers are named in the same period: cost competitiveness with conventional supply, the ability to track emission reductions, and the absence of long-term offtake. The regional version of the problem sits on the Southeast Asia offtake page.
What this means for you: I build the term sheet around length, price form and tracking before I discuss volume, because those three decide whether a lender recognises the revenue at all.
Who is actually buying today
Nearly half of the 20 largest fast-moving consumer goods companies, with 850 billion USD of annual food and beverage revenue, have set scope 3 targets (2025), and switching to low-emission ammonia would raise end product cost by 1 to 3 percent while cutting product emissions by up to 30 percent, against organic premiums of 20 to 40 percent. The ladder approach (2024) starts with near-term pockets such as mining explosives and gas power generation before fertilisers and shipping, and a proposed consumer coalition would signal purchase interest. Power buyers are real but small: Japan and South Korea promote ammonia co-firing with coal, Singapore’s strategy allows hydrogen up to 50 percent of projected electricity demand in 2050, Keppel Infrastructure is building a 600 MW hydrogen-ready plant while examining a 60 MW ammonia-fuelled one, and Envision Energy is building a 1.52 million tonne green ammonia plant in China (2024). Shipping remains a promise of 178 million tonnes of ammonia consumption in 2050 in one net zero scenario (2024). The regional demand picture is set out on the Southeast Asia and Singapore market page.
What this means for you: I write the buyer list in ladder order, because the pocket that signs first is rarely the fertiliser contract you planned the plant around.
What I will not count as market
First exclusion: an announced pipeline is not a project. The Global Hydrogen Review 2026 puts the announced pipeline at 27 Mt to 2030, with committed and high-potential production falling from 10 Mt to just above 6 Mt, and 22 Mt at risk of losing its 2030 slot without an investment decision before early 2027. Four more exclusions follow. Announced capacity is not an offtake: 300 Mtpa was announced in May 2025 against 15 Mtpa at final investment decision. An offtake is not a contract: 45 of 185 tracked projects had one in January 2024. A final investment decision is not a delivery: 1.3 Mtpa was online in May 2025. Spare capacity is not demand: utilisation sits around 80 percent on 243 million tonnes of capacity in 2024. Each of these five gaps is where a pre-FID file tends to overstate itself.
What this means for you: I keep a one page exclusions list in the data room, so that nobody in the chain can silently promote an announcement into a contract.
What this changes in Southeast Asia
The December 2025 Southeast Asia briefing from the International Energy Agency puts regional demand at 4 Mt in 2024, ammonia at 49 percent against refining at 31 percent and methanol at 20 percent, split between Indonesia at 35 percent, Malaysia at 22 percent, Viet Nam at 15 percent and Singapore at 12 percent; only Indonesia and Malaysia export, Malaysia taking 73 percent of regional exports and the region 17 percent of world ammonia exports in 2023. Announced regional projects equal 12 percent of current demand while only 6 percent of announced capacity has reached a final investment decision; 11 Mtpa of potential sits below 6 USD/kg by 2030; no certification scheme is yet in place, with work under way in three countries; and 6.6 billion USD of development finance institution loans flowed between 2021 and 2025.
Low-carbon production grew 20 percent in 2025 to almost 1 Mt and should pass 1 percent of global production in 2026, with about 80 percent of high-potential production aimed at chemicals, refining and low-carbon fuels; the barriers named in 2026 are high costs, uncertain demand, slow or complex regulation and insufficient infrastructure. The funding route is set out on the infrastructure project finance page.
What this means for you: I treat certification and offtake as one workstream here, since a region with no scheme in place cannot yet prove the emission reduction a buyer is paying for.
The four lines I would put in front of a lender
Line one, segment: the survey from the World Bank’s Energy Sector Management Assistance Program, dated February 2026, shows ammonia as the largest project segment at about 42 percent of electrolyser projects worldwide under construction. Line two, equipment: installed electrolyser capacity was about 2.15 GW mid-2025, or 0.2 percent of global hydrogen demand, with 16 GW under construction and 3.5 GW at final investment decision, quoted at 500 to 1,500 USD per kilowatt for alkaline systems and 1,000 to 2,000 USD per kilowatt for PEM (February 2026), which is a quote and not an installed cost. Line three, cost of capital: less established technologies carry higher financing costs unless warranties or guarantees step in, and financing requirements can push a project towards established contractors and proven equipment (February 2026). Line four, price: the best projects today sit around 3 USD per kilogram and most sit above it (February 2026).
What this means for you: I take these four lines into the room before the term sheet, because segment share, equipment quote, financing cost and delivered price decide whether the file gets read at all.
Sources
- Hydrogen Council with McKinsey & Company, Fertilizing the future: A roadmap to scale low-emission ammonia fertilizers https://hydrogencouncil.com/wp-content/uploads/2025/11/Fertilizing-the-future-FINAL.pdf, November 2025.
- BloombergNEF and Climate Technology Coalition, Scaling Up Hydrogen: The Case for Low-Carbon Ammonia https://assets.bbhub.io/professional/sites/24/CTC-whitepaper_Ammonia_Final.pdf, January 2024.
- IEA, Global Hydrogen Review 2025, Southeast Asia, 9 December 2025 https://iea.blob.core.windows.net/assets/745a259b-9cb7-4e1d-9ba1-a8b63d1eaae8/GHR2025_SEA_Webinar.pdf, 2025.
- IEA, Global Hydrogen Review 2026, Executive summary https://www.iea.org/reports/global-hydrogen-review-2026/executive-summary, 2026.
- World Bank, ESMAP, Electrolyzers for Hydrogen Production: Technical and Economic Characteristics https://documents1.worldbank.org/curated/en/099022326123011297/pdf/P506220-b45b0865-8706-4862-8792-d8cc71f84569.pdf, February 2026.
Frequently asked questions
How much low-emission ammonia capacity is actually committed?
As of May 2025, 15 Mtpa had reached a final investment decision across 48 projects, 35 Mtpa sat in front-end engineering design across 85 projects, and 1.3 Mtpa was online as retrofits, out of more than 300 Mtpa announced.
What does a bankable green ammonia offtake agreement look like?
It runs far longer than the contracts buyers are used to: a fixed price over a long horizon, since a producer may hold a 20-year fixed-price power contract, with volumes pooled or aggregated to reduce counterparty risk and a way to track the emission reduction claimed.
Who buys green ammonia today?
Three doors: fertiliser and fast-moving consumer goods companies with scope 3 targets, power generators co-firing with coal, and shipping, which is still an order book rather than a bulk market; in 2021 fertilisers took 77 percent of ammonia demand and industrial uses 23 percent.
Why is the green ammonia market bigger in announcements than in contracts?
Because announcements are cheap and contracts are not: 300 Mtpa was announced by May 2025 while only 15 Mtpa held a final investment decision, 45 of 185 tracked projects had offtake agreements in January 2024, and 90 percent of traded ammonia still moves on one to three year contracts.
Not sure your project would survive a credit conversation?
A short call is usually enough to see where your project stands.
If you want the contract itself worked through before the file is built, look at offtake agreement structuring, where I take a draft offtake from first term sheet to a document a lender will read against your revenue line.
I do not provide investment advice or arrange investments. I act as a strategic advisor and facilitator.
Alex, Founder of WeConnect Asia
I help low-carbon fuel and carbon removal project developers in Southeast Asia secure the commercial and financial partners needed to reach FID.
Related articles

Pitching a Climate Tech Company to Strategic Investors: What the Corporate Has to Believe Before It Writes a Cheque
How to pitch a climate tech company to strategic investors: the metric cluster, the readiness evidence and the ask that corporates fund.

Biomethane: What It Is, How It Is Made and Who Buys It
Biomethane is biogas cleaned to pipeline quality. I explain how it is made, how it differs from biogas and who buys it in Southeast Asia.

CO2 Sourcing for e-SAF Projects: What the Rules Allow and What the Contract Must Say
Biogenic CO2, direct air capture or industrial flue gas: which sources an e-SAF plant may use, what they cost and which contract terms make the fuel certifiable.

Operating Performance Guarantees for SAF Plants: What Lenders Ask For
Minimum guarantees, performance damages, retesting and who stands behind them: the operating guarantees a SAF plant needs to keep debt and offtake intact.

EPC and Construction Risk in SAF Plants: What a Lender Actually Tests
FEED scope, convertible EPC, performance guarantees and damages caps: the construction risk questions a SAF project must answer before financial close.

Matching Feedstock and Offtake Risk Back-to-Back in a SAF Project: How Lenders Read the Chain
Lenders do not buy a feedstock plan and an offtake plan separately. They buy the link between the two, and the link is where most SAF files break.